Word Document PDF Document |
COM/DGX/ALJ/JHE/gd2 Date of Issuance 4/14/2010
Decision 10-04-027 April 8, 2010
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California Gas Company (U904G) for Approval of Advanced Metering Infrastructure. |
Application 08-09-023 (Filed September 29, 2008) |
DECISION ON APPLICATION OF SOUTHERN CALIFORNIA GAS COMPANY FOR APPROVAL OF ADVANCED METERING INFRASTRUCTURE
DECISION ON APPLICATION OF SOUTHERN CALIFORNIA GAS COMPANY FOR APPROVAL OF ADVANCED METERING INFRASTRUCTURE 1
1. Summary 2
2. Procedural Background 3
3. Late-Filed Exhibits 5
4. Summary of the Application 8
5. Standard of Review and Criteria for Review of Proposals 8
6. Overview of Party Positions 10
7. Reasonableness and Feasibility of Technology Choices 11
7.1. Communications System 14
7.1.1. SoCalGas Proposal 14
7.1.2. Party Positions on Communications System 16
7.1.3. Discussion of Proposed Communications System 16
7.2. Battery Choice 18
7.3. Additional Elements 21
7.3.1. Analysis of Additional Elements 21
8. Consistency with State Energy Policy Objectives 22
8.1. Party Positions 23
8.2. State Policy Supports Development and Implementation of
Cost Effective AMI for Gas or Electric Utilities 24
9. Cost Effectiveness 25
9.1. Benefits 26
9.1.1. Terminal Value 26
9.1.2. Cost Savings from Elimination of SoCalGas
Meter Reading Workforce 28
9.1.3. Conservation Benefits 30
9.2. Costs 37
9.3. The SoCalGas AMI Proposal is Cost Effective 39
9.4. The SoCalGas AMI Project is Approved 40
9.5. Ratepayer Protections 41
10. Categorization and Assignment of Proceeding 46
11. Comments on Proposed Decision 46
Findings of Fact 47
Conclusions of Law 50
ORDER 50