ALJ/JSW/lil Date of Issuance 8/1/2011
Decision 11-07-052 July 28, 2011
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
In the Matter of the Application of San Diego Gas & Electric Company (U902G) and Southern California Gas Company (U904G) for Authority to Revise Their Rates Effective January 1, 2009, in Their Biennial Cost Allocation Proceeding. |
Application 08-02-001 (Filed February 4, 2008) |
ORDER REGARDING JOINT PETITION FOR
MODIFICATION OF DECISION 09-11-006
The settlement agreement that was approved and adopted in Decision (D.) 09-11-006 provides that San Diego Gas & Electric Company (SDG&E) and Southern California Gas Company (SoCalGas) are to file their next cost allocation proceeding for their natural gas transmission, distribution, and storage operations no later than September 1, 2011. SDG&E, SoCalGas, and ten other parties filed a joint petition to modify the filing date in D.09-11-006 from September 1, 2011 to November 1, 2011.
Today's decision grants the joint petition to modify D.09-11-006 so as to require that the next cost allocation proceeding for SDG&E and SoCalGas be filed no later than November 1, 2011, instead of September 1, 2011.