ALJ/ANG/avs Date of Issuance 5/30/2012
Decision 12-05-022 May 24, 2012
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
In the Matter of the Application of The Nevada Hydro Company for a Certificate of Public Convenience and Necessity for the Talega-Escondido/Valley-Serrano 500 kV Interconnect Project. |
Application 10-07-001 (Filed July 6, 2010) |
DECISION DISMISSING APPLICATION AND
DENYING PETITION TO MODIFY DECISION 11-07-036
TABLE OF CONTENTS
Title Page
DECISION DISMISSING APPLICATION AND 22
DENYING PETITION TO MODIFY DECISION 11-07-036 22
2. Should the Application be Dismissed? 55
2.1. The Parties' Positions 55
3. Should the Petition to Modify D.11-07-036 be Granted? 1313
4. Categorization and Need for Hearings 1717
DECISION DISMISSING APPLICATION AND
DENYING PETITION TO MODIFY DECISION 11-07-036
In this decision, we dismiss The Nevada Hydro Company's (Nevada Hydro) Application (A.) 10-07-001 for a Certificate of Public Convenience and Necessity for the Talega-Escondido/Valley-Serrano 500 kilovolt Interconnect Project. We take this action because, despite over 18 months of work, the application is not complete and does not conform to our requirements. We cannot continue to expend Commission or party resources on A.10-07-001. Although we dismiss this application without prejudice, we impose a series of conditions that must be met if we are to consider an application for this project (or similar projects) in the future. We also deny Nevada Hydro's Petition to Modify Decision (D.) 11-07-036, and require Nevada Hydro to comply with the performance/surety bond requirements specified by Ordering Paragraph 2 of D.11-07-036.