Filer Requested Category:
Ratesetting
Preliminary Category:
Ratesetting
Commission Designated Category:
Ratesetting
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
|
DOCUMENTS
Number of Documents: 152
(only the most current 100 are displayed)
Display all documents for this proceeding
|
Type:
PROPOSED DECISION
|
Filing Date:
October 21, 2008
|
Filed By:
ALJ/O'DONNELL/CPUC
|
|
Description:
Decision Modifying Decision 05-12-040 to Allow use of an Alternative Transportation Route for Replacement Steam Generators at San Onofre Nuclear Generating Station. Opening Comments which shall not exceed 15 pages are due November 10, 2008; Reply Comments which shall not exceed 5 pages are due 5 days after the last day to file Opening Comments.
|
Type:
PETITION FOR MODIFICATION
|
Filing Date:
July 23, 2008
|
Filed By:
Southern California Edison Company
|
|
Description:
of Decision No. 05-12-040.
|
Type:
PROPOSED DECISION
|
Filing Date:
September 18, 2006
|
Filed By:
ALJ/O'DONNELL/CPUC
|
|
Description:
Comments are due October 8, 2006; reply comments - 5 days after comments are filed.
|
Type:
COMMENTS
|
Filing Date:
July 31, 2006
|
Filed By:
Southern California Edison Company
|
|
Description:
Opening; on Attachments to ALJ Ruling.
|
Type:
RULING
|
Filing Date:
June 22, 2006
|
Filed By:
ALJ/O'DONNELL/CPUC
|
|
Description:
ADMINISTRATIVE LAW JUDGE'S RULING CONCERNING REHEARING OF DECISION 05-12-040; No later than July 31, 2006, parties shall file and serve their opening
comments on how the Commission should take into consideration the correct net present value calculations for Southern California Edison Company's Steam Generator Replacement Program (SGRP) and calculate the greenhouse gas (GHG) adder using an accurate source of data; Reply Commernts shall be filed and served no later than 08/14/06.
|
Type:
MOTION
|
Filing Date:
April 21, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Strike California Earth Corps' First Amendment to Request for Award of Compensation.
|
Type:
REPLY
|
Filing Date:
April 7, 2006
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
to (Edison's) Response to Request for Award of Compensation.
|
Type:
REQUEST
|
Filing Date:
April 7, 2006
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
First, Amended; for an Award of Compensation for Substantial Contribution to Decision 05-12-040.
|
Type:
RESPONSE
|
Filing Date:
March 23, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to California Earth Corps' Request for Award of Compensation.
|
Type:
REPLY
|
Filing Date:
March 15, 2006
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
to Edison's Response to California Earth Corps' Motion to Late-File Request for Award of Compensation.
|
Type:
RESPONSE
|
Filing Date:
March 10, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to California Earth Corps' Motion to Late-File Request for Intervenor Compensation.
|
Type:
COMPLIANCE FILING
|
Filing Date:
March 6, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Written Notice in compliance with Decision 05-12-040, O.P. 30.
|
Type:
MOTION
|
Filing Date:
March 3, 2006
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
to Late-File Request for Award of Compensation for Substantial Contribution to Decision 05-12-040; ATTACHED - REQUEST.
|
Type:
REQUEST
|
Filing Date:
February 17, 2006
|
Filed By:
TURN
|
|
Description:
For Award of Compensation for Substantial Contribution to D05-12-040
|
Type:
REQUEST
|
Filing Date:
February 15, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
for Award of Compensation.
|
Type:
RESPONSE
|
Filing Date:
February 2, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
(PUBLIC & CONFIDENTIAL VERSIONS) to Application for Rehearing of Decision 05-12-040 of TURN and California Earth Corps.
|
Type:
REHEARING REQUEST
|
Filing Date:
January 18, 2006
|
Filed By:
CALIFORNIA EARTH CORPS
UTILITY REFORM NETWORK
|
|
Description:
of D05-12-040.
|
Type:
EXPARTE
|
Filing Date:
December 15, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
December 12, 2005, Matthew Freedman, attorney for The Utility Reform Network (TURN), met with Robert Lane, advisor to Cmmr. Bohn, in San Francisco. Also present were Stephen St. Marie, advisor to Cmmr. Bohn, and Mike Florio, Attorney for TURN. TURN representatives discussed the proposed decision of ALJ O'Donnell and the alternate of Cmmr. Peevey. Freedman and Florio stated TURN¿s opposition to the alternate on the basis that it was poorly drafted, failed to incorporate any cost caps, was inconsistent with the Commission treatment for Diablo Canyon, and would place ratepayers at risk of unlimited cost overruns during the remaining life of the plant. Freedman urged to vote against the alternate.
|
Type:
COMMENTS
|
Filing Date:
December 13, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Reply; to comments of ORA, Aglet, TURN, WPTF and SDG&E.
|
Type:
COMMENTS ON ALTERNATE
|
Filing Date:
December 12, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Reply;
|
Type:
COMMENTS ON ALTERNATE
|
Filing Date:
December 12, 2005
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
Reply; Proposed Decision of Cmmr Peevey.
|
Type:
COMMENTS ON ALTERNATE
|
Filing Date:
December 8, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
WESTERN POWER TRADING FORUM
|
|
Description:
of Cmmr. Peevey.
|
Type:
COMMENTS ON ALTERNATE
|
Filing Date:
December 8, 2005
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
of Cmmr. Peevey.
|
Type:
COMMENTS ON ALTERNATE
|
Filing Date:
December 8, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Decision of Cmmr Peevey.
|
Type:
COMMENTS ON ALTERNATE
|
Filing Date:
December 8, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Opening; Decision of Cmmr Peevey.
|
Type:
COMMENTS ON ALTERNATE
|
Filing Date:
December 7, 2005
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
of Cmmr. Peevey.
|
Type:
ALTERNATE
|
Filing Date:
December 1, 2005
|
Filed By:
CMMR/PEEVEY/PUC
|
|
Description:
Comments are due by December 8, 2005; reply comments - December 12, 2005.
|
Type:
EXPARTE
|
Filing Date:
December 1, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
On November 28, 2005, Bruce Foster, Vice President of Regulatory Affairs of Southern California Edison Company (SCE), met with Stephen St. Marie, advisor to Cmmr. Bohn, in San Francisco. Foster discussed SCE¿s concerns regarding the ALJ¿s proposed decision, including the inequitable imposition of cost caps, and ignoring the value of deferring construction of major transmission lines. Foster also discussed the benefits San Onofre Nuclear generating Station Unit Numbers 2 and 3 operations provide to California ratepayers in an era of high natural gas prices.
|
Type:
COMMENTS
|
Filing Date:
November 29, 2005
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
Reply; on Proposed Decision of ALJ O'Donnell.
|
Type:
COMMENTS
|
Filing Date:
November 28, 2005
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
reply; on Proposed Decision of ALJ O'Donnell.
|
Type:
COMMENTS
|
Filing Date:
November 28, 2005
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
reply; on the proposed decision of ALJ O'Donnell.
|
Type:
COMMENTS
|
Filing Date:
November 28, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
reply; on the proposed decision.
|
Type:
COMMENTS
|
Filing Date:
November 28, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Reply; to Opening Comments of TURN, Aglet and SDG&E.
|
Type:
COMMENTS
|
Filing Date:
November 28, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Reply; on the proposed decision of ALJ O'Donnell.
|
Type:
COMMENTS
|
Filing Date:
November 21, 2005
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
on Proposed Decision of ALJ O'Donnell.
|
Type:
COMMENTS
|
Filing Date:
November 21, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
opening; on the proposed decision of ALJ O'Donnell.
|
Type:
COMMENTS
|
Filing Date:
November 21, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
(on the Proposed Decision of ALJ O'Donnell.)
|
Type:
COMMENTS
|
Filing Date:
November 21, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
on the Proposed Decision of ALJ O'Donnell.
|
Type:
PROPOSED DECISION
|
Filing Date:
October 31, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Opening Comments not to exceed 15 pages are due NLT 11/20/05; Reply Comments not to exceed 5 pages are due NLT 11/26/05.
|
Type:
RULING
|
Filing Date:
September 30, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Denies requests of June 28, 2005, of Edison and of July 13, 2005, of Cal. Earth Corps to reopen the record for the limited purpose of receiving specified documents into evidence, as set forth.
|
Type:
RESPONSE
|
Filing Date:
July 28, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to California Earth Corps' Motion to Reopen The Evidentiary Record.
|
Type:
RESPONSE
|
Filing Date:
July 21, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
to Motion (of Edison) to Re-Open the Evidentiary Record for the limited purpose of accepting the Gas Price Forecast set forth in Advice 1878-E submitted pursuant to D04-12-048
|
Type:
MOTION
|
Filing Date:
July 14, 2005
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
to Reopen The Evidentiary Record.
|
Type:
RESPONSE
|
Filing Date:
July 14, 2005
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
to [Edison's] Motion to Reopen the Evidentiary Record.
|
Type:
OPPOSITION
|
Filing Date:
July 13, 2005
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
to Edison's motion to reopen the evidentiary record.
|
Type:
RESPONSE
|
Filing Date:
July 13, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
to the motion of Edison to reopen the evidentiary record.
|
Type:
RESPONSE
|
Filing Date:
July 1, 2005
|
Filed By:
COGENERATION ASSOCIATION OF CALIFORNIA
ENERGY PRODUCERS AND USERS COALITION
|
|
Description:
to the motion of Edison to reopen the record.
|
Type:
MOTION
|
Filing Date:
June 28, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Re-Open the Evidentiary Record for the limited purpose of accepting the Gas Price Forecast set forth in Advice 1878-E submitted pursuant to D04-12-048.
|
Type:
RULING
|
Filing Date:
June 21, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Receiving Tube Degradation Results Exhibit Into Evidence.
|
Type:
EXPARTE
|
Filing Date:
June 14, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
On June 9, 2005, Carol A. Schmid-Frazee, Senior Attorney for Southern California Edison Company (SCE), sent a letter (attached to the notice) to the Administrative Law Judge O¿Donnell. The letter stated that response of San Diego Gas & Electric Company to SCE's May 26, 2005 compliance filing that included SCE's update of figures II-6 and II-7 was in error.
|
Type:
RESPONSE
|
Filing Date:
June 3, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
to Edison's Compliance Filing.
|
Type:
COMPLIANCE FILING
|
Filing Date:
May 26, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
per ALJ Ruling dated 04/29/05.
|
Type:
RULING
|
Filing Date:
April 29, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Requires provision of tube degradation results, as a compliance filing, by May 27, 2005; responses to the compliance filing may be filed within 10 days after the compliance filing.
|
Type:
OPPOSITION
|
Filing Date:
April 6, 2005
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
to Edison's Motion to Strike Portions of the Opening Brief.
|
Type:
RESPONSE
|
Filing Date:
April 6, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
to the motion to strike of Edison.
|
Type:
RESPONSE
|
Filing Date:
April 6, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
to SoCal Edison's Motion to Strike portions of the Opening Brief of SDG&E
|
Type:
BRIEF
|
Filing Date:
April 5, 2005
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
Reply;
|
Type:
BRIEF
|
Filing Date:
April 5, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
PUBLIC VERSION; reply; on the proposed steam generator replacement project. CONFIDENTIAL VERSION SUBMITTED UNDER SEAL PURSUANT TO THE PROTECTIVE ORDER.
|
Type:
BRIEF
|
Filing Date:
April 5, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Reply (PUBLIC AND CONFIDENTIAL VERSIONS).
|
Type:
BRIEF
|
Filing Date:
April 5, 2005
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
Reply;
|
Type:
BRIEF
|
Filing Date:
April 5, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Reply;
|
Type:
BRIEF
|
Filing Date:
April 5, 2005
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
reply.
|
Type:
MOTION
|
Filing Date:
March 25, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Strike portions of the Opening Brief of SDG&E concerning a new proposal to Warehouse Replacement Steam Generators; Requrest for Expedited Consideration.
|
Type:
MOTION
|
Filing Date:
March 25, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Strike portions of the Opening Brief of ORA concerning a new ratemaking proposa; Requrest for Expedited Consideration.
|
Type:
MOTION
|
Filing Date:
March 25, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Strike portions of the Opening Brief of TURN concerning a new proposal to have the Commission investigate Edison's maintenance of SONGS 2 & 3 Steam Generators; Requrest for Expedited Consideration.
|
Type:
BRIEF
|
Filing Date:
March 22, 2005
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
Opening;
|
Type:
EXPARTE
|
Filing Date:
March 21, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
On March 16, 2005, Carol A. Schmid-Frazee, Senior Attorney for Southern California Edison Company (SCE), sent an e-mail message (copy attached to the notice) to ALJ O'Donnell. The letter stated that San Diego Gas & Electric Company (SDG&E) had committed to providing access to the Arbitrator's Decision (AD) concerning the dispute between SCE and SDG&E. The letter attached the AD and stated that using the value of capacity chosen by the AD, SDG&E's share of San Onofre Nuclear Generating Station Unit Nos. 2 & 3 would be reduced to 0 percent.
|
Type:
BRIEF
|
Filing Date:
March 16, 2005
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
opening;
|
Type:
BRIEF
|
Filing Date:
March 16, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
[CONFIDENTIAL VERSION FILED UNDER SEAL] opening.
|
Type:
BRIEF
|
Filing Date:
March 16, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
PUBLIC VERSION; opening.
|
Type:
BRIEF
|
Filing Date:
March 16, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Opening (PUBLIC & CONFIDENTIAL VERSIONS).
|
Type:
BRIEF
|
Filing Date:
March 16, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Opening;
|
Type:
BRIEF
|
Filing Date:
March 16, 2005
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
Opening;
|
Type:
EXPARTE
|
Filing Date:
February 25, 2005
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On February 22, 2005, Brian Cherry, Director, Regulatory Relations, Pacific Gas and Electric Company (PG&E), participated in an all-party meeting with Cmmr. Brown in San Francisco. Also present were David Gamson, advisor to Cmmr. Brown, Greg Rueger, Senior Vice President and Chief Nuclear Officer, and Jennifer Post, counsel, for PG&E, and other attendees listed on a sign-in sheet, attached to the notice. Rueger addressed the construction delays that would result by a delayed vote on the interim decision. Rueger stated that any halt in construction contract progress would result in the project slipping at least one cycle, increasing the likelihood that three California nuclear generation units would be off-line at the same time in 2009. Post discussed the Westinghouse litigation, noting that PG&E had no valid cause of action for breach of warranty or fraud.
|
Type:
EXPARTE
|
Filing Date:
February 16, 2005
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On February 11, 2005, Brian Cherry, Director, Regulatory Relations, Pacific Gas and Electric Company (PG&E), had a telephone conversation with David Gamson, advisor to Cmmr. Brown. As a follow-up, a written material (attached to the notice) was provided. Cherry discussed the construction delays that would be caused by late vote on the interim decision. Cherry stated that any halt in construction contract progress would result in the project slipping at least one cycle, and the possibility that three California nuclear replacement projects would be done at the same time in 2009.
|
Type:
TRANSCRIPT
|
Filing Date:
February 15, 2005
|
Filed By:
REPORTING DIVISION
|
|
Description:
Submitted; Volume 10.
|
Type:
RULING
|
Filing Date:
January 25, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Denies a January 21, 2005 ORS's motion to delay hearing dates.
|
Type:
RESPONSE
|
Filing Date:
January 25, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to ORA's Motion to Continue Hearings.
|
Type:
MOTION
|
Filing Date:
January 21, 2005
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
to continue the hearing dates.
|
Type:
RULING
|
Filing Date:
January 20, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Denies the motion of Cal. Earth Corps for confidential treatment, as set forth.
|
Type:
RULING
|
Filing Date:
January 20, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Grants Edison's January 13, 2005 motion to apply the terms of the existing protective order to specified materials.
|
Type:
MOTION
|
Filing Date:
January 14, 2005
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
for ruling applying terms of existing protective order to materials relating to viability or non-viability of legal claims against manufacturer of steam generators, and to certain documents produced in discovery.
|
Type:
LAW & MOTION
|
Filing Date:
January 14, 2005
|
Filed By:
CALIFORNIA EARTH CORPS
|
|
Description:
for confidential treatment of written testimony of Dr. Joram Hopenfeld.
|
Type:
RULING
|
Filing Date:
January 7, 2005
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Denies motions to strike filed by Edison on December 28, 2004, as set forth.
|
Type:
RESPONSE
|
Filing Date:
January 7, 2005
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
in opposition to Edison's motion to strike the testimony of David Schlissel.
|
Type:
RESPONSE
|
Filing Date:
January 4, 2005
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
to [Edison's] Motion to Strike Testimony.
|
Type:
RESPONSE
|
Filing Date:
January 4, 2005
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
to [Edison's] Motion to Strike the Testimony of SDG&E witnesses.
|
Type:
MOTION
|
Filing Date:
December 28, 2004
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Strike the Testimony of SDG&E witnesses James Avery, Michael S. Schneider and Marina Vengrin; Request for Expedited Consideration.
|
Type:
MOTION
|
Filing Date:
December 28, 2004
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Strike the Testimony of David A. Schlissel relating to litigation over Westinghouse Steam Generators; Request for Expedited Consideration
|
Type:
RULING
|
Filing Date:
December 16, 2004
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Addresses TURN, et al.'s motion for permission to submit supplemental testimony.
|
Type:
OPPOSITION
|
Filing Date:
December 13, 2004
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Motion for Permission to Submit Supplemental Testimony.
|
Type:
MOTION
|
Filing Date:
December 7, 2004
|
Filed By:
AGLET CONSUMER ALLIANCE
CALIFORNIA EARTH CORPS
ORA/CPUC
THE UTILITY REFORM NETWORK
|
|
Description:
for permission to submit supplemental testimony.
|
Type:
RULING
|
Filing Date:
December 1, 2004
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Grants motion to find protective order applicable to additional materials, filed by Edison on November 24, 2004.
|
Type:
MOTION
|
Filing Date:
November 24, 2004
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
REVISED; to Find Protective Order applicable to additional confidential materials.
|
Type:
RULING
|
Filing Date:
November 23, 2004
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Denies the motion of SDG&E to revise the issues and schedule. Grants, to the extent set forth, the motion of TURN to revise the schedule; otherwise the motion is denied.
|
Type:
MOTION
|
Filing Date:
November 23, 2004
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Find Protective Order applicable to additional confidential materials, and for an Order Shortening Time for Response.
|
Type:
RESPONSE
|
Filing Date:
November 22, 2004
|
Filed By:
ORA/ANGELOPULO/PUC
|
|
Description:
in support of TURN's motion for revision of the procedural schedule.
|
Type:
OPPOSITION
|
Filing Date:
November 22, 2004
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to SDG&E's Motion and Proposed Modification to TURN's Motion for Revision of the Procedural Schedule.
|
Type:
RESPONSE
|
Filing Date:
November 22, 2004
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
to TURN's Motion for Revision of Procedural Schedule.
|
Type:
RULING
|
Filing Date:
November 19, 2004
|
Filed By:
ALJ/O'DONNELL/PUC
|
|
Description:
Grants motion to find protective order adopted by the May 21, 2004 ruling applicable to additional materials, filed November 12, 2004.
|
DECISIONS
Number of Decisions: 7
|
Decision Number:
D0811042
|
Rendered Date:
November 21, 2008
Effective Date:
November 21, 2008
|
|
Description:
Modifies Decision 05-12-040 to allow use of an alternative transportation route for replacement steam generators at San Onofre Nuclear Generating Station. Closes proceeding.
|
Decision Number:
D0611024
|
Rendered Date:
November 30, 2006
Effective Date:
November 30, 2006
|
|
Description:
Affirms the ordering paragraphs of D.05-12-040 as modified by D.06-06-040. This proceeding is closed.
|
Decision Number:
D0607018
|
Rendered Date:
July 20, 2006
Effective Date:
July 20, 2006
|
|
Description:
Grants intervenor compensation to The Utility Reform Network for substantial contributions to Decision 05-12-040. This proceeding is closed.
|
Decision Number:
D0607019
|
Rendered Date:
July 20, 2006
Effective Date:
July 20, 2006
|
|
Description:
Grants intervenor compensation to California Earth Corps for substantial contributions to Decision 05-12-040. This proceeding is closed.
|
Decision Number:
D0607020
|
Rendered Date:
July 20, 2006
Effective Date:
July 20, 2006
|
|
Description:
Grants intervenor compensation to Aglet Consumer Alliance for substantial contributions to Decision 05-12-040. This proceeding is closed.
|
Decision Number:
D0606040
|
Rendered Date:
June 15, 2006
Effective Date:
June 15, 2006
|
|
Description:
Modifies D05-12-040 in certain respects, grants limited rehearing, and denies rehearing in all other respects. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)
|
Decision Number:
D0512040
|
Rendered Date:
December 15, 2005
Effective Date:
December 15, 2005
|
|
Description:
The application of SCE for approval of its steam generator replacement program for San Onofre Nuclear Generating Station Units 2 & 3 is approved subject to the conditions as set forth. This proceeding is closed. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)
|