Type: EXPARTE

Filing Date: November 16, 2007
Filed By:
San Diego Gas & Electric Company
Description: SUMMARY: On November 13, 2007 Billy Blattner, Manager of Regulatory Relations for San Diego Gas & Electric Company (SDG&E) had a telephone conversation with Jack Stoddard, advisor to Pres. Peevey. Mike McClenahan, Director of Procurement and Portfolio Design for SDG&E; Abby Snyder, Counsel for SDG&E; and Steve Case, Counsel for SDG&E also participated in the phone call. Blattner expressed concern that language pertaining to the Assignment term proposed in the Proposed Decision (PD) could impede consents that resolve concerns about risk. McClenahan explained that language pertaining to the Eligibility term would hinder project financing and could impermissibly subject the utilities to hindsight reasonableness reviews. Contact Person: Trish Rickard; telephone: (415) 202-9986; e-mail: TRickard@SempraUtilities.com.

Type: EXPARTE

Filing Date: November 14, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: On November 8, 2007 Meredith Allen, Director, Regulatory Relations for Pacific Gas and Electric Company (PG&E) had a telephone conversation with Jackson Stoddard, advisor to Pres. Peevey in San Francisco. Allen explained PG&E's concern that the revised Draft Decision's discussion of the Assignment standard term could limit consents to assignment that a utility would be able to provide creating obstacles for sellers to obtain necessary financing. As a result, such language could harm customers by limiting opportunities for RPS contracting needed to meet the RPS goals and increasing customer costs.

Type: EXPARTE

Filing Date: November 8, 2007
Filed By:
Southern California Edison Company
Description: SUMMARY: On November 7, 2007 Michael Hoover, Director of Regulatory Affairs of Southern California Edison Company (SCE) had a telephone call with Jack Stoddard, advisor to Pres. Peevey; J Eric Isken, Senior Attorney of SCE; Dawn Anaiscourt, Attorney for SCE; William Walsh, Attorney of SCE; Ellen LeVine, Legal Division of the CPUC; Paul Douglas, Energy Division of the CPUC; and Adam Umanoff of Chadbourne and Park also participated in the phone call. Written material (attached to this notice) was used. Walsh discussed the need to make the Commission's standard Assignment term in the investor owned utilities' ("IOUs") renewables portfolio standard ("RPS") contracts modifiable. SCE explained that the Commission's November 1, 2007 Proposed Decision (the "PD") incorrectly assumes that the standard language ensures that a lender assignee will be required to be bound by the power purchase agreement, including the assumptions of payment and performance obligations thereunder, in the event of a default. SCE stated tha

Type: EXPARTE

Filing Date: November 7, 2007
Filed By:
Independent Energy Producers Association
Description: SUMMARY: On November 2, 2007 Steven Kelly, Policy Director of Independent Energy Producers Association (IEP) met with Nancy Ryan, advisor to Pres. Peevey in San Francisco. Also present were Andrew Schwartz, advisor to Pres. Peevey; and Brian Cragg, outside counsel for IEP. Kelly raised a concern that one of the proposed, non-modifiable standard contract terms mentioned in the Proposed Decision in this proceeding would create an unacceptable risk to project developers for changes in law that are outside the developers' control. Contact Person: Melinda LaJaunie; telephone: (415) 392-7900.

Type: EXPARTE

Filing Date: November 5, 2007
Filed By:
Center for Energy Efficiency and Renewable Technologies
Description: SUMMARY: On October 31, 2007 Sara Steck Myers, attorney for the Energy Efficiency and Renewable Technologies (CEERT) had a telephone conversation with F. Jackson Stoddard, advisor to Pres. Peevey. Myers stated that CEERT had filed comments on the Proposed Decision of ALJ Mattson on Amended Petition for Modification of Decision 04-06-014 Regarding Standard Terms and Conditions (Proposed Decision) and had asked that the Proposed Decision be modified to limit the non-modifiable Renewable Portfolio Standard (RPS) standard terms and conditions (STCs) to the three identified in the Amended Petition. Myers indicated that CEERT had supported the original petition filed by Pacific Gas and Electric Company (PG&E) and Southern California Edison Company (SCE). Myers also stated that while CEERT continued to believe that all RPS STCs terms should be modifiable, as an alternative, CEERT did support the amended petition and asked that the Proposed Decision be modified to limit the non-modifiable STCs to just the three term

Type: EXPARTE

Filing Date: November 2, 2007
Filed By:
San Diego Gas & Electric Company
Description: SUMMARY: On October 30, 2007 Billy Blattner, Manager of Regulatory Relations for San Diego Gas & Electric Company (SDG&E) had a telephone conversation with Jack Stoddard, advisor to Pres. Peevey. Blattner expressed concern regarding the Eligibility term proposed in the Proposed Decision (PD). Blatner noted that a consensus is forming around "commercially reasonable" language offered by SDG&E in its comments on the PD, which would address parties' concerns about the potential impact of the provision on the ability to finance and develop renewable energy projects. Contact Person: Trish Rickard; telephone: (415) 202-9986; e-mail: TRickard@SempraUtilities.com.

Type: EXPARTE

Filing Date: November 2, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: On October 30, 2007 Meredith Allen, Director, Regulatory Relations for Pacific Gas and Electric Company (PG&E) met with Jaclyn Marks, advisor to Cmmr. Simon in San Francisco. Also present were Robert Mason, advisor to Cmmr. Simon; and Gary Jeung, Director, Structured Transactions of PG&E. Written materials (attached to the notice) were used. Jeung explained PG&E's concern that the draft decision's proposed change to the Eligibility standard term and its analysis of the Assignment standard term would harm customers by limiting opportunities for RPS contracting needed to meet the RPS goals and increasing customer costs. Allen stated that the draft decision's verification requirement would only create delays in the preparation of filings for contract approval.

Type: EXPARTE

Filing Date: October 31, 2007
Filed By:
Southern California Edison Company
Description: SUMMARY: On October 29, 2007 Michael Hoover, Director of Regulatory Affairs, of Southern California Edison Company (SCE) had a telephone conversation with Jack Stoddard, advisor to Cmmr. Peevey. Hoover discussed the need to approve SCE's and Pacific Gas and Electric Company's ("PG&E") petition for modification of the standard terms and conditions decision (D.04-060-14) (the "Petition") based on the reasons outlined in SCE's comments to the Proposed Decision ("PD"). Hoover indicated that the standard non-modifiable Eligibility term, as drafted in the PD, could potentially make it impossible for renewables portfolio standard developers to receive financing for their projects. Contact Person: Henry Romero; telephone: (626) 302-4124; e-mail: Henry.Romero@sce.com.

Type: EXPARTE

Filing Date: October 30, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: On October 25, 2007 Meredith Allen, Director, Regulatory Relations for Pacific Gas and Electric Company (PG&E) had a telephone conversation with Jackson Stoddard, advisor to Pres. Peevey in San Francisco. Allen explained PG&E's concern that the Draft Decision's proposed change to the Eligibility standard term and its analysis of the Assignment standard term would harm customers by limiting opportunities for RPS contracting needed to meet the RPS goals and increasing customer costs. Allen further stated that the Draft Decision's verification requirement would only create delays in the preparation of filings for contract approval.

Type: EXPARTE

Filing Date: October 29, 2007
Filed By:
Independent Energy Producers Association
Description: SUMMARY: On October 24, 2007 Douglas K. Kerner, attorney for the Independent Energy Producers Association ("IEP"), had two separate telephone conversations with Jackson Stoddard, advisor to Pres. Peevey. Kerner expressed IEP's concern with the Proposed Decision of ALJ Mattson, particularly with respect to its proposed, non-modifiable standard contract term. Kerner stated that the proposed provision creates untenable project risk to developers and lenders, and increased customer cost, due to changes in law. Contact Person: Eric Janssen; telephone: (916) 447-2166; e-mail: ericj@eslawfirm.com.

Type: COMMENTS

Filing Date: October 29, 2007
Filed By:
Southern California Edison Company
Description: Reply; on Proposed Decision.

Type: COMMENTS

Filing Date: October 29, 2007
Filed By:
Pacific Gas and Electric Company
Description: Reply; On the Proposed Decision on Amended Petition for Modification of D.04-06-014 (Standard Terms and Conditions).

Type: COMMENTS

Filing Date: October 23, 2007
Filed By:
San Diego Gas & Electric Company
Description: On Proposed Decision Regarding Amended Petition for Modification of Decision 04-06-014.

Type: COMMENTS

Filing Date: October 22, 2007
Filed By:
Southern California Edison Company
Description: On Proposed Decision.

Type: COMMENTS

Filing Date: October 22, 2007
Filed By:
Independent Energy Producers Association
Description: On Draft Opinion on Amended Petition for Modification of Decision 04-06-014 Regarding Standard Terms and Conditions.

Type: COMMENTS

Filing Date: October 22, 2007
Filed By:
Center for Energy Efficiency and Renewable Technologies
Description: On the Proposed Decision of ALJ Mattson On Amended Petition for Modification of Decision 04-06-014.

Type: COMMENTS

Filing Date: October 22, 2007
Filed By:
Pacific Gas and Electric Company
Description: On the Proposed Decision on Amended Petition for Modification of D.04-06-014.

Type: COMMENTS

Filing Date: October 19, 2007
Filed By:
DRA/OBIORA/CPUC
Description: On the Opinion on Amended Petition for Modification of Decision 04-06-014 Regarding Standard Terms and Conditions.

Type: PROPOSED DECISION

Filing Date: October 1, 2007
Filed By:
ALJ/MATTSON/CPUC
Description: Opinion on Amended Petition for Modification of Decision 04-06-014 Regarding Standard Terms and Conditions. Opening Comments, which shall not exceed 15 pages, are due no later than October 21, 2007. Reply Comments are due 5 days after Opening Comments are filed.

Type: COMMENTS

Filing Date: September 14, 2007
Filed By:
OBIORA/DRA/CPUC
Description: Reply; On the Proposed Decision on Petition for Modification of D.05-12-042.

Type: COMMENTS

Filing Date: September 10, 2007
Filed By:
Southern California Edison Company
Description: On Proposed Decision.

Type: COMMENTS

Filing Date: September 10, 2007
Filed By:
California Wind Energy Association
Concentrated Solar Power Alliance
The Green Power Institute
Description: on the Proposed Decision of ALJ Simon on the California Wind Energy Association's and The Green Power Institute's Petition for Modification of Decision 05-12-042.

Type: PROPOSED DECISION

Filing Date: August 21, 2007
Filed By:
ALJ/SIMON/CPUC
Description: Opinion on Petition for Modification of Decision 05-12-042. Opening Comments, which shall not exceed 15 pages, are due no later than September 10, 2007. Reply Comments are due 5 days after Opening Comments are filed.

Type: RULING

Filing Date: July 30, 2007
Filed By:
ALJ/SIMON/CPUC
Description: ALJ's Ruling on Motion for Party Status.

Type: REPLY

Filing Date: July 24, 2007
Filed By:
California Wind Energy Association
The Green Power Institute
Description: to the Petition for Modification of Decision 05-12-042.

Type: RESPONSE

Filing Date: July 17, 2007
Filed By:
CALIFORNIA COGENERATION COUNCIL
Description: to the Petition of the California Wind Energy Association and Green Power Institute for Modification of Decision 05-12-042.

Type: RESPONSE

Filing Date: July 17, 2007
Filed By:
Pacific Gas and Electric Company
Description: to Petition of the California Wind Energy Association and the Green Power Institute for Modification of Decision 05-12-042: Interim Opinion Adopting Methodology for the 2005 Marketing Price Referent.

Type: RESPONSE

Filing Date: July 17, 2007
Filed By:
San Diego Gas & Electric Company
Description: to Petition for Modification of D.05-12-042.

Type: RESPONSE

Filing Date: July 17, 2007
Filed By:
Union of Concerned Scientists
Description: to the Petition of the California Wind Energy Association and the Green Power Institute for Modification of Decision 05-12-042: Interim Opinion Adopting Methodology for the 2005 Market Price Referent.

Type: RESPONSE

Filing Date: July 17, 2007
Filed By:
Center for Energy Efficiency and Renewable Technologies
Description: to Petition of the California Wind Energy Association and Green Power Institute for Modification of Decision 05-12-042.

Type: COMMENTS

Filing Date: July 17, 2007
Filed By:
DRA/OBIORA/CPUC
Description: on Petition of California Wind Energy Association and the Green Power Institute for Modification of Decision 05-12-042.

Type: RESPONSE

Filing Date: July 17, 2007
Filed By:
Southern California Edison Company
Description: Opposition to the CALWEA and the Green Power Institute Petition for Modification of Decision 05-12-042.

Type: RESPONSE

Filing Date: July 17, 2007
Filed By:
Concentrated Solar Power Alliance
Description: to the Petition of the California Wind Energy Association and Green Power Institute for Modification of Decision 05-12-042.

Type: EXPARTE

Filing Date: July 17, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: On July 12, 2007, Meredith Allen, Regulatory Relations of Pacific Gas and Electric Company (PG&E) met with Andrew Schwartz, advisor to Pres. Peevey in San Francisco. Also present were Jim Shandalov, Principal, Energy Procurement of PG&E; and Michael Hoover, Director, Regulatory Affairs of Southern California Edison (SCE). Written materials (attached to the notice) were used. Allen stated that the Commission should adopt the modifications to the RPS Standard Terms and Conditions decision (D.04-06-014) proposed in the Joint Amended petition of PG&E and SCE. These proposed modifications promote the RPS and incorporate the lessons learned through experience with the program.

Type: MOTION

Filing Date: July 17, 2007
Filed By:
Concentrated Solar Power Alliance
Description: for Party Status by the Concentrated Solar Power Alliance.

Type: REPLY

Filing Date: July 9, 2007
Filed By:
Pacific Gas and Electric Company
Southern California Edison Company
Description: to Responses on Amended Petition for Modification of D.04-06-014 regarding standard terms and conditions required for renewables portfolio standard contracts (filing authorized by ALJ Mattson per email ruling dated June 19, 2007).

Type: RESPONSE

Filing Date: July 2, 2007
Filed By:
Independent Energy Producers Association
Description: to the Amended Petition for Modification.

Type: RESPONSE

Filing Date: July 2, 2007
Filed By:
San Diego Gas & Electric Company
Description: to Amended Petition for Modification of Decision 04-06-014.

Type: RESPONSE

Filing Date: June 29, 2007
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
Description: to Amended Petititon for Modification of D.04-06-014.

Type: RULING

Filing Date: June 28, 2007
Filed By:
ALJ/SIMON/CPUC
Description: on Motion to Expedite. The time for filing and service of responses to the petition of the California Wind Energy Association (CalWEA) and the Green Power Institute (GPI), for Modification of Decision 05-12-042, is shortened to July 17, 2007. CalWEA and GPI may file and serve a reply to the responses not later than July 24, 2007.

Type: PETITION FOR MODIFICATION

Filing Date: June 25, 2007
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
THE GREEN POWER INSTITUTE
Description: of Decision 05-12-042: Interim Opinion Adopting Methodology for the 2005 Market Price Referent.

Type: MOTION

Filing Date: June 25, 2007
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
THE GREEN POWER INSTITUTE
Description: for expedited decision and order shortening time related to its concurrently filed Petition for Modification of Decision 05-12-042: Interim Opinion Adopting Methodology for the 2005 Market Price Referent.

Type: EXPARTE

Filing Date: June 22, 2007
Filed By:
Southern California Edison Company
Description: SUMMARY: On June 19, 2007, Michael Hoover, Director, Regulatory Affairs, Southern California Edison Company (SCE) had a telephone conversation with Andy Schwartz, advisor to Pres. Peevey. Hoover discussed the need to approve SCE's and Pacific Gas and Electric Company's (PG&E) petition for modification of D.04-06-014 (Petition) based on the reasons outlined in the Petition and the recently filed amended petition for modification. Hoover explained that the recent scoping memo for the 2008 renewables portfolio standard procurement plan reinforces the need to grant SCE's and PG&E's Petition. Contact person: Henry Romero, telephone: (626) 302-4124; e-mail: henry.Romero@sce.com

Type: COMMENTS

Filing Date: June 19, 2007
Filed By:
Southern California Edison Company
Description: Supplemental; in support of Amended Petition for Modification of Decision 04-06-014 of PG&E and SCE regarding Standard Terms and Conditions Required for Renewables Portfolio Standard Contracts.

Type: COMMENTS

Filing Date: June 18, 2007
Filed By:
Independent Energy Producers Association
Description: Reply; on the Proposed Decision.

Type: COMMENTS

Filing Date: June 18, 2007
Filed By:
Pacific Gas and Electric Company
Southern California Edison
Description: Reply; on ALJ Mattson's Proposed Decision entitled "Opinion on Petition for Modification of Decision 04-06-014 regarding process for changing, and lifting restrictions on, designated standard terms and conditions"

Type: PETITION FOR MODIFICATION

Filing Date: June 15, 2007
Filed By:
Pacific Gas and Electric Company
Southern California Edison Company
Description: Amended; of Decison 04-06-014 regarding Standard Terms and Conditions Required for Renewables Portfolio Standard Contracts.

Type: COMMENTS

Filing Date: June 11, 2007
Filed By:
Pacific Gas and Electric Company
Description: on ALJ Mattson's Proposed Decision entitled Opinion on Petition for Modification of D0406014 Regarding Process for Changing, and Lifting Restrictions on, Designated Standard Terms and Conditions.

Type: COMMENTS

Filing Date: June 11, 2007
Filed By:
San Diego Gas & Electric Company
Description: on Proposed Decision regarding Petition for Modification of Decision 04-06-014.

Type: COMMENTS

Filing Date: June 8, 2007
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
Description: of the Center for Energy Efficiency and Renewable Technologies on the Proposed Decision of ALJ Mattson.

Type: COMPLIANCE FILING

Filing Date: May 29, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: pursuant to ALJ Ruling dated April 30, 2007.

Type: MOTION

Filing Date: May 29, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: for Reconsideration of ALJ Ruling dated April 30, 2007 and Request for Continued Confidential Treatment of Documents provided under seal.

Type: MOTION

Filing Date: May 29, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: Supplemental Motion for Confidential Protection pursuant to ALJ Ruling dated April 30, 2007.

Type: NOTICE

Filing Date: May 29, 2007
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: of Availability pursuant to ALJ Ruling dated April 30, 2007.

Type: PROPOSED DECISION

Filing Date: May 22, 2007
Filed By:
ALJ/MATTSON/CPUC
Description: Opinion on Petition for Modification of Decision 04-06-014 Regarding Process for Changing, and Lifting Restrictions on, Designated Standard Terms and Conditions. Opening Comments, which shall not exceed 15 pages, are due no later than June 11, 2007. Reply Comments are due 5 days after Reply Comments are filed.

Type: RESPONSE

Filing Date: May 22, 2007
Filed By:
San Diego Gas & Electric Company
Description: Compliance Filing: Unredacted Version of 2006 Renewable Portfolio Standard Procurement Plan.

Type: REPORT

Filing Date: May 22, 2007
Filed By:
Southern California Edison Company
Description: (PUBLIC VERSION) 2006 Renewables Portfolio Standard Procurement Plan.

Type: RULING

Filing Date: April 30, 2007
Filed By:
ALJ/MATTSON/CPUC
Description: on Southern California Edison Company motions to file data under seal.

Type: RULING

Filing Date: April 30, 2007
Filed By:
ALJ/MATTSON/CPUC
Description: on PG&E' Company's Motions to File Data Under Seal (related to the Commission's Renewables Portfolio Standard Program).

Type: RULING

Filing Date: April 30, 2007
Filed By:
ALJ/MATTSON/CPUC
Description: on SDG&E Company's Motions to File Data Under Seal (related to the Commission's Renewables Portfolio Standard Program).

Type: COMMENTS

Filing Date: February 28, 2007
Filed By:
Independent Energy Producers Association
Description: on Petition for Modification of Decision 04-06-014 of PG&E and SCE regarding standard terms and conditions required for Renewables Portfolio Standard Contracts.

Type: RESPONSE

Filing Date: February 28, 2007
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
Description: to Petition for Modification of Decision 04-06-014 of Pacific Gas and Electric Company and Southern California Edison Company.

Type: PETITION FOR MODIFICATION

Filing Date: February 1, 2007
Filed By:
Pacific Gas and Electric Company
Southern California Edison Company
Description: of D04-06-014 regarding standard terms and conditions required for Renewables Portfolio Standard contracts.

Type: PETITION FOR MODIFICATION

Filing Date: November 20, 2006
Filed By:
AGLET CONSUMER ALLIANCE
Description: of D06-10-012.

Type: EXPARTE

Filing Date: August 15, 2006
Filed By:
ALLIANCE FOR RETAIL ENERGY MARKETS
Description: On August 10, 2006, Stacy Aguayo of APS Energy Services, representing the Alliance for Retail Energy Markets (AReM), met with Andrew Campbell, advisor to Cmmr. Chong, Belinda Gatti, advisor to Cmmr. Brown, Robert Lane and Lindsay Brown, advisors to Cmmr. Bohn, Nancy Ryan, advisor to Pres. Peevey, Julie Fitch, Director of Strategic Planning Division, Andrew Schwartz of the Division of Strategic Planning, and Bill Chen of Constellation NewEnergy, and Gregory Klatt of Douglass & Liddell, representing AReM. AReM representatives voiced concern about the timing of the Commission's implementation of the Renewables Portfolio Standard (RPS) for electric service providers (ESPs). AReM representatives expressed the need for interim guidance from the Commission regarding the manner in which ESPs are to participate in the RPS program, particularly for 2006, in the event that formal decisions resolving pending matters relating to ESP compliance are not adopted very soon. AReM representatives reiterated the need for the Co

Type: REQUEST

Filing Date: July 25, 2006
Filed By:
AGLET CONSUMER ALLIANCE
Description: for Award of Compensation.

Type: REQUEST

Filing Date: July 25, 2006
Filed By:
THE GREEN POWER INSTITUTE
Description: for Award of Compensation for Substantial Contribution to D.06-05-039.

Type: REQUEST

Filing Date: July 25, 2006
Filed By:
UNION OF CONCERNED SCIENTISTS
Description: for an award of compensation for substantial contributions to D05-07-039, D05-10-014, D05-11-025, D05-12-42, and D06-05-039 and for participation in utility procurement preview groups.

Type: RULING

Filing Date: July 12, 2006
Filed By:
ALJ/MATTSON/CPUC
Description: REGARDING FILING OF INTERVENOR COMPENSATION REQUESTS. The requests, if filed, should be filed by July 25, 2006.

Type: COMPLIANCE FILING

Filing Date: June 9, 2006
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
Description: Amended 2006 RFP Protocol.

Type: COMPLIANCE FILING

Filing Date: June 9, 2006
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
Description: (PUBLIC & CONFIDENTIAL VERSIONS) Amended 2006 Short-Term Renewable Procurement Plan.

Type: RULING

Filing Date: May 23, 2006
Filed By:
ALJ/MATTSON/PUC
Description: Grants PG&E's motions of May 15, 2006 for leave to supplement its comments on reporting and compliance issues and for leave to file an appendix to its Supplement under seal.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
AGLET CONSUMER ALLIANCE
Description: Reply; on Proposed Decision of ALJ Mattson.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
GREEN POWER INSTITUTE
Description: Reply; on the Draft Decision of ALJ Mattson.

Type: LAW & MOTION

Filing Date: May 22, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: motion for leave to file confidential material under seal; confidential materials attached and filed under seal, namely, PG&E's RPS compliance strategy.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
Description: reply; on the proposed decision of ALJ Mattson on 2006 RPS Procurement Plans.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
Description: reply; on the proposed decision of ALJ Mattson.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
INDEPENDENT ENERGY PRODUCERS ASSOCIATION
Description: reply; on the draft decision of ALJ Mattson.

Type: EXPARTE

Filing Date: May 22, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: On May 17, 2006, Frank De Rosa, Director, Power Contract, Pacific Gas and Electric Company (PG&E), met with Andrew Campbell, advisor to Cmmr. Chong, in San Francisco. Also present were Meredith Allen, Chief, Regulatory Relations, and Charles Post, Senior Power Contract Specialist, for PG&E. Confidential written materials, submitted under seal along with a motion for leave to file under seal, were used. A redacted version of the written material is attached to the notice. Allen explained that the Commission should adopt the full earmarking proposal. De Rosa stated that the full earmarking accommodates the lead times for developing new renewables projects.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
Description: Reply; on Draft Decision of ALJ Mattson.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
Description: Reply; on Draft Decision (of ALJ Mattson) adopting 2006 RPS Procurement Plans.

Type: COMMENTS

Filing Date: May 22, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: reply; on the proposed decision conditionally approving procurement plans for 2006 RPS solicitations.

Type: RULING

Filing Date: May 18, 2006
Filed By:
ALJ/MATTSON/PUC
Description: Denies the May 15, 2006 motion of PG&E to shorten time for response, as set forth.

Type: LAW & MOTION

Filing Date: May 18, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: motion for leave to file confidential material under seal; confidential material attached and filed under seal, namely, PG&E's RPS compliance strategy.

Type: EXPARTE

Filing Date: May 18, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: On May 15, 2006, Meredith Allen, Chief, Regulatory Relations, Pacific Gas and Electric Company, met with Peter Hanson, advisor to Cmmr. Brown, in San Francisco. Also present was Belinda Gatti, advisor to Cmmr. Brown. Confidential written materials, submitted under seal along with a motion for leave to file under seal, were used. A redacted version of the written material is attached to the notice. Allen explained that the Commission should adopt the full earmarking proposal.

Type: RULING

Filing Date: May 17, 2006
Filed By:
CMMR/PEEVEY/PUC
Description: Adopting 2006 Transmision Ranking Cost Reports.

Type: LAW & MOTION

Filing Date: May 16, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: motion for leave to file confidential material under seal; confidential material attached and filed under seal, namely, PG&E's RPS Compliance Strategy.

Type: EXPARTE

Filing Date: May 16, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: On May 11, 2006, Meredith Allen, Chief, Regulatory Relations, Pacific Gas and Electric Company, met with Stephen St. Marie, advisor to Cmmr. Bohn, in San Francisco. Confidential written materials, submitted under seal along with a motion for leave to file under seal, were used. A redacted version of the written material is attached to the notice. Allen explained that the Commission should adopt the full earmarking proposal.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
COALITION OF CALIFORNIA UTILITY EMPLOYEES
Description: on the draft decision of ALJ Mattson.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
UNION OF CONCERNED SCIENTISTS
Description: on the proposed decision adopting 2006 RPS procurement plans.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
AGLET CONSUMER ALLIANCE
Description: on Proposed Decision of ALJ Mattson.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
DRA/OBIORA/PUC
Description: opening; on the draft decision conditionally approving procurement plans for 2006 renewable procurement standards solicitations.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
Description: on the draft decision of ALJ Mattson.

Type: MOTION

Filing Date: May 15, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: for leave to supplement comments on reporting and compliance issues; supplement attached.

Type: MOTION

Filing Date: May 15, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: for Order Shortening Time for Reply to Seven Days.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
Description: on Draft Decision (of ALJ Mattson).

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
Description: opening; on the draft decision conditionally approving procurement plans for 2006 renewable procurement standards solicitations. ALJ Mattson conditionally approving procurement plans for 2006 RPS Solicitations, addressing TOD Benchmarking Methodology, and closing proceeding.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
INDEPENDENT ENERGY PRODUCERS ASSOCIATION
Description: on the draft decision of ALJ Mattson on 2006 RPS procurement plans.

Type: LAW & MOTION

Filing Date: May 15, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: motion for leave to file confidential material under seal; confidential materials attached and filed under seal; namely, confidential appendix to Supplement to Comments.

Type: COMMENTS

Filing Date: May 15, 2006
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
Description: opening; on the proposed decision conditionally approving procurement plans, etc.

DECISIONS
Number of Decisions: 22

Decision Number: D0801008

Rendered Date: January 10, 2008
Effective Date: January 10, 2008
Description: Grants intervenor compensation to Union of Concerned Scientists for substantial contributions to Decision (D) 06-05-039, D05-07-039, D05-10-014, D05-11-025, D05-12-042, and related procurement review groups in this proceeding. This proceeding is closed.

Decision Number: D0801019

Rendered Date: January 10, 2008
Effective Date: January 10, 2008
Description: Clarifies Decision 06-10-012 and denies the petition for modification of Aglet Consumer Alliance.

Decision Number: D0711025

Rendered Date: November 16, 2007
Effective Date: November 16, 2007
Description: Grants amended petition for modification of Decision 04-06-014 regarding standard terms and conditions, as set forth, and denies in all other respects.

Decision Number: D0709024

Rendered Date: September 20, 2007
Effective Date: September 20, 2007
Description: Grants the request of the California Wind Energy Association and the Green Power Institute that the 2007 market price referent (MPR) developed for the renewables portfolio standard program include an additional element in the MPR to account for the costs of the emission of greenhouse gases (GHG adder). The Commission denies at this time their request to modify the MPR methodology set forth in D05-12-042 to include a GHG adder for 2008 and later years using the specific approach adopted here.

Decision Number: D0705051

Rendered Date: May 24, 2007
Effective Date: May 24, 2007
Description: Grants Intervenor compensation to Aglet Consumer Alliance and Green Power Institute for their substantial contributions to Decision 06-05-039.

Decision Number: D0610012

Rendered Date: October 5, 2006
Effective Date: October 5, 2006
Description: Grants intervenor compensation to Green Power Institute and The Utility Reform Network for substantial contributions to Decision 04-06-014, Decision 04-06-015, Decision 04-07-029, Decision 05-05-011, Decision 05-07-039, Decision 05-10-014, Decision 05-11-025, Decision 05-12-042, and Decision 06-01-046; and denies compensation to Aglet Consumer Alliance. This proceeding is closed.

Decision Number: D0605023

Rendered Date: May 25, 2006
Effective Date: May 25, 2006
Description: Southern California Edison Company's petition for modification of D05-07-039 is denied.

Decision Number: D0605039

Rendered Date: May 25, 2006
Effective Date: May 25, 2006
Description: Conditionally approves for the next procurement cycle, each proposed renewables portfolio standard procurement plan and draft request for offer filed by Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company. This proceeding is closed. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0604022

Rendered Date: April 13, 2006
Effective Date: April 13, 2006
Description: Awards the Green Power Institute $23,531.00, and the Union of Concerned Scientists $4,531.88, in compensation for their substantial contributions to D05-05-011. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0603016

Rendered Date: March 2, 2006
Effective Date: March 2, 2006
Description: Modifies D05-11-025 and denies rehearing of the Decision, as modified. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0601046

Rendered Date: January 26, 2006
Effective Date: January 26, 2006
Description: Denies Rehearing of D05-07-039 filed by the Center for Energy Efficiency and Renewable Technologies and Southern California Edison Company.

Decision Number: D0601029

Rendered Date: January 19, 2006
Effective Date: January 19, 2006
Description: Corrects errors in D05-12-042.

Decision Number: D0512042

Rendered Date: December 15, 2005
Effective Date: December 15, 2005
Description: Interim Opinion. Adopts the methodology for calculating the 2005 market price referent to be used for solicitations in the Renewables Portfolio Standard program. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0511025

Rendered Date: November 18, 2005
Effective Date: November 18, 2005
Description: Sets forth the basic parameters for the participation of Energy Service Providers, Community Choice Aggregators, and small and multi-jurisdictional utilities in the Renewables Portfolio Standards program. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0510014

Rendered Date: October 6, 2005
Effective Date: October 6, 2005
Description: Interim Opinion. Conditionally approves the long-term procurement plans for the Renewables Portfolio Standard Plans. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration. Comr. Bohn, being necessarily absent, did not participate.)

Decision Number: D0507039

Rendered Date: July 21, 2005
Effective Date: July 21, 2005
Description: Approves procurement plans and requests for offers for 2005 RPS solicitations. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0505011

Rendered Date: May 5, 2005
Effective Date: May 5, 2005
Description: Clarifies participation of renewable distributed generation in the renewable portfolio standards program. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration. Comr. Bohn recused himself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0501053

Rendered Date: January 27, 2005
Effective Date: January 27, 2005
Description: Grants intervenor compensation to Green Power Institute for substantial contributions to D04-06-014, D04-06-015, and D04-07-029. (Comr. Grueneich recused herself from this agenda item and was not part of the quorum in its consideration.)

Decision Number: D0409036

Rendered Date: September 20, 2004
Effective Date: September 20, 2004
Description: Corrects errror in D04-07-029.

Decision Number: D0407029

Rendered Date: July 8, 2004
Effective Date: July 8, 2004
Description: Adopts criteria for the selection least-cost and best-fit renewable resources.

Decision Number: D0406015

Rendered Date: June 9, 2004
Effective Date: June 9, 2004
Description: Adopts market price referent methodology. (Comr. Lynch and Comr. Wood reserve the right to file a dissent).

Decision Number: D0406014

Rendered Date: June 9, 2004
Effective Date: June 9, 2004
Description: Adopts standard contract terms and conditions. (Comr. Wood and Comr. Lynch reserve the right to file a dissent).

Top of Page    Documents    Decisions    Main Index