STATE OF CALIFORNIA
PUBLIC UTILITIES COMMISSION

Southern California Edison's
Tehachapi Renewable Transmission Project
(Application A.07-06-031, filed June 29,2007)

Project
Location
Maps

Scoping
Report

Notice of
Availability
of the Final
EIR

Final EIR

Address
Look-Up

Fact Sheets

Schedule

 

 

Welcome to the California Public Utilities Commission (CPUC) website for the environmental review of the Tehachapi Renewable Transmission Project in Kern, Los Angeles, and San Bernardino counties. Southern California Edison (SCE) submitted an application for a Certificate of Public Convenience and Necessity (CPCN) for this project to the CPUC on June 29, 2007. SCE also submitted an application for a Special Use authorization to the USDA Forest Service. The project is subject to review under both the California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA). This site provides access to public documents and information relevant to the CEQA and NEPA review processes.

The CPUC issued a Proposed Decision for this project on November 3, 2009. The CPUC certified the Final EIR and issued Decision 09-12-044 approving the project December 17, 2009. Read the press release here . The Notice of Determination was submitted to the State Clearinghouse on December 17, 2009 (received December 21,2009).

As the NEPA Lead Agency for the project, the USDA Forest Service is currently conducting a detailed review of the impacts of the Station Fire, which burned approximately 251 square miles of National Forest System (NFS) lands in the Angeles National Forest, including portions of Segments 6 and 11, between August 26, 2009, and October 16, 2009 when 100 percent containment was achieved. The Forest Service will prepare a Supplemental Draft Environmental Impact Statement (EIS) to assess the impacts of the Station Fire and other project changes affecting NFS lands. After the public review period for the Supplemental Draft EIS, the Forest Service will issue its Final EIS. Following release of the Final EIS, the Forest Service will issue a Record of Decision (ROD) to document the decision to either approve or deny the requested Special Use authorization for the Project.

Public documents related to the Tehachapi Renewable Transmission Project CEQA and NEPA review process are available on this website and can also be viewed at several repository sites throughout the Project area. A list of these repository sites is available in the Notice of Availability for the Draft EIR/EIS.

Final EIR

The Final EIR was released to the public on October 30, 2009. The Final EIR is available by clicking the link above and is also available at numerous repository sites. Copies of the Final EIR on DVD may be requested by emailing TRTP@AspenEG.com

The Final EIR includes responses to all comments received on the Draft EIR/EIS during the public review period (February 13 through April 6, 2009). The Final EIR also includes an analysis of a modified version of Alternative 4C proposed by the City of Chino Hills, which incorporates a slightly different switching station location, and incorporation of new information issued by the California Independent System Operator regarding the need for Segment 8B (for all alternatives). In addition, the Final EIR includes a Mitigation Monitoring Program.

Draft EIR/EIS

The CPUC and the USDA Forest Service released the Draft EIR/EIS for the proposed Tehachapi Renewable Transmission Project on February 13, 2009. The public comment period ended on April 6, 2009.Revisions to the Draft EIR/EIS are reflected in the Final EIR (see link above).

Project Background and Description

SCE filed applications with the CPUC and the Forest Service to construct a series of transmission system improvements to deliver electricity from new wind energy projects in eastern Kern County to the Los Angeles Basin. The proposed Project would provide the electrical facilities necessary to integrate levels of new wind generation in excess of 700 megawatts (MW) and up to approximately 4,500 MW in the Tehachapi Wind Resource Area (TWRA).

For descriptive purposes, the proposed Project is separated into eight distinct segments, referred to as Segments 4 through 11. Segments 4 through 8, as well as Segments 10 and 11 of the proposed Project are transmission facilities, while Segment 9 addresses the addition and upgrade of substation facilities. The Project's major components include:

  • Two new single-circuit 220-kilovolt (kV) transmission lines traveling in parallel approximately 4 miles over new right-of-way (ROW) from the Cottonwind Substation to the proposed new Whirlwind Substation (Segment 4 - 220 kV).
  • A new single-circuit 500-kV transmission line, initially energized to 220 kV, traveling approximately 15.6 miles over new ROW from the proposed new Whirlwind Substation to the existing Antelope Substation (Segment 4 - 500 kV).
  • Replace approximately 17.4 miles of the existing Antelope-Vincent 220-kV transmission line and the existing Antelope-Mesa 220-kV transmission line with only one new transmission line built to 500-kV standards in existing ROW between the existing Antelope Substation and the existing Vincent Substation (Segment 5).
  • Rebuild approximately 31.9 miles of existing 220-kV transmission line to 500-kV standards from existing Vincent Substation to the southern boundary of the Angeles National Forest (ANF). This segment includes the rebuild of approximately 26.9 miles of the existing Antelope-Mesa 220-kV transmission line and approximately 5 miles of the existing Rio Hondo–Vincent 220-kV No. 2 transmission line (Segment 6).
  • Rebuild approximately 15.8 miles of existing 220-kV transmission line to 500-kV standards from the southern boundary of the ANF to the existing Mesa Substation. This segment would replace the existing Antelope-Mesa 220-kV transmission line (Segment 7).
  • Rebuild approximately 33 miles of existing 220-kV transmission line to 500-kV standards from a point approximately 2 miles east of the existing Mesa Substation (the "San Gabriel Junction") to the existing Mira Loma Substation (Segment 8A). This segment would also include the rebuild of approximately 7 miles of the existing Chino–Mira Loma No. 1 line from single-circuit to double-circuit 220-kV structures (Segment 8B).A new circuit between Chino Substation and approximately 0.8 mile west of the Mira Loma Substation (6.4 miles) would also be installed on the new double-circuit 500-kV structures built as part of Segment 8A (Segment 8C).
  • Whirlwind Substation, a new 500/220-kV substation located approximately 4 to 5 miles south of the Cottonwind Substation near the intersection of 170th Street and Holiday Avenue in Kern County near the TWRA (Segment 9).
  • Upgrade of the existing Antelope, Vincent, Mesa, Gould, and Mira Loma Substations to accommodate new transmission line construction and system compensation elements (Segment 9).
  • Build a new 500-kV transmission line traveling approximately 16.8 miles over new ROW between the approved Windhub Substation (not part of this project) and the proposed new Whirlwind Substation (Segment 10).
  • Rebuild approximately 18.7 miles of existing 220-kV transmission line to 500-kV standards between the existing Vincent and Gould Substations. This segment would also include the addition of a new 220-kV circuit on the vacant side of the existing double-circuit structures of the Eagle Rock–Mesa 220-kV transmission line, between the existing Gould Substation and the existing Mesa Substation (Segment 11).
  • Installation of associated telecommunications infrastructure.

Project Location

Maps of the proposed transmission routes can be viewed by clicking on the link below
     Project Location Maps.

To find the location of your property in relation to the proposed transmission routes, click on the link below and enter your property address.
     Address Look-up

Additional Project Documents

Comment Summary Report

The Comment Summary Report and its appendices, which document and summarize the public meeting that was held on January 17, 2008, in Brea, CA, are available here.

Scoping Report

The Scoping Report and its appendices, which document and summarize the public scoping process, including comments received on the proposed Project, are available here.

Policy Consistency and Plan Amendments Report

The Policy Consistency and Plan Amendments Report, which provides a review of relevant federal, State, regional, and local agency plans and planning documents, is available here.

Fact Sheets

Several Fact Sheets are available that provide information on aspects of electrical transmission that frequently interest the public. These Fact Sheets were provided at all of the public scoping meetings and are also available here.

Notice of Preparation

The CPUC and Forest Service are jointly preparing an Environmental Impact Report (EIR) and Environmental Impact Statement (EIS) for the proposed Tehachapi Renewable Transmission Project. To initiate the EIR process, a Notice of Preparation was distributed by the CPUC on August 31, 2007.

The Notice of Preparation (English) can be viewed here. Translated versions of the NOP can be viewed here. [Chinese], [Spanish], and [Korean].

Notice of Intent

To initiate the EIS process, the USDA Forest Service published its Notice of Intent to prepare an Environmental Impact Statement in the Federal Register (Volume 72, No. 173, page 51404) on September 7, 2007.

Proponent's Environmental Assessment (PEA)

As part of its application to the CPUC, SCE prepared and submitted a Proponent's Environmental Assessment (PEA), which describes the proposed project, existing environmental conditions in the project area, and potential environmental impacts. The PEA may be viewed here.

Notice of Availability of the Draft EIR/EIS

When the CPUC and the Forest Service published the Draft EIR/EIS, a Notice of Availability (NOA) was distributed to the public on February 13, 2009. The NOA (English) can be viewed here. Translated versions of the NOA can be viewed here [Chinese], [Spanish], and [Korean].

For Additional Information

The CPUC and the Forest Service are conducting an environmental review of this project. To request additional information or to be added to the mailing list, please contact us by email, fax, or phone, as follows:

Project Mailing Address:

CPUC/Angeles National Forest
c/o Aspen Environmental Group
30423 Canwood Street, Suite 215
Agoura Hills, CA 91301

Project Email: TRTP@AspenEG.com

   

This page contains tables and is best viewed with Internet Explorer or Mozilla Firefox. Please report any problems to the Energy Division web coordinator.

   
 
Project Home Page - CPUC Environmental Information - CPUC Home