Resolution E-4047. Pacific Gas & Electric (PG&E) Company requests approval of the amended Global Common renewable resource procurement contracts. These contracts are approved with modifications.

By Advice Letter 2865-E filed on July 28, 2006 and Supplemental Advice Letter 2865-EA filed on November 13, 2006.

__________________________________________________________

SUMMARY

PG&E's renewable contracts comply with the Renewable Portfolio Standard (RPS) procurement guidelines and are approved with modifications

PG&E's request for approval of the renewable resource procurement contracts is granted. The energy acquired from these contracts will count towards PG&E's Renewable Portfolio Standard (RPS) requirements. In addition, the price for the contracts has been deemed by the Commission to be reasonable and fully recoverable in rates over the life of the contracts, subject to Commission review of PG&E's administration of the contracts. However, the Commission does not grant PG&E's request for a non-bypassable charge.

Generating facility

Type

Term Years

MW Capacity

GWh Energy

Online

Date

Location

El Nido

Biomass

15

9 MW

72 GWh

9/30/07

Fresno, CA

Chowchilla

Biomass

15

9 MW

72 GWh

12/31/07

Fresno, CA

Confidential information about the contract should remain confidential

This resolution finds that certain material filed under seal pursuant to Public Utilities (Pub. Util.) Code Section 583, General Order (G.O.) 66-C and Decision (D.)06-06-066 should be kept confidential to ensure that market sensitive data does not influence the behavior of bidders in future RPS solicitations.