ATTACHMENT A

(CORRECTED)

ACTION PLAN AND WORK PLAN CONTENTS

The Action Plan and Work Plan are to be tailored to fit the needs of a given region's constituents and geography, incorporating core responsibilities, including goals, measurable deliverables, expected outcomes, and specific timeline milestones as they relate to broadband deployment, access, and adoption. Below are required core responsibilities that should be included and reflected in an Action Plan. Following the Action Plan is a list of activities that should be included in a Work Plan. The Work Plan should include all activities designed to implement the Action Plan goals. Sample forms illustrating the format of an Action Plan and Work Plan are included as Attachments B and C.

Action Plan Core Responsibilities that should be included:

ATTACHMENT B

Sample of Action Plan Format

[Name of Regional Consortium]

[Name of Project]

ACTION PLAN

---EXAMPLE SECTIONS---

(END OF ATTACHMENT B)

Sample of Work Plan Format

[Name of Regional Consortium]

[Name of Project]

WORK PLAN1 - [MONTH, YEAR]

Goals/
Objectives (as stated in the Action Plan)

Activity(ies)

Timeline

Responsible Party(ies)

Performance Measure(s)

Goal A

Identify, recruit, and train community-based organizations (CBOs) to conduct outreach

    · Identify CBOs and develop database

    · Secure commit-ments for CBO participa-tion

    · Train CBO officers

    · Convene meetings and facilitate planning

1/1/11 - 12/21/11

    · Identify CBOs and develop database: 1/1/11-1/8/11

    · Secure commit-ments: 1/9/11-2/9/11

    · Train CBO officers: 1/9/11-4/29/11

    · Convene meetings: 1/9/11-12/15/11

    · Joseph Lee, Communi-ty Relations Manager

    · Stephanie Singh, Marketing Director

    · Ashley Marino, CIO

    · Reach at least 80% of CBOs in region

    · Train CBO officers or designated representa-tives

    · Conduct two meetings per month

    · Conduct one conference call per week

(END OF ATTACHMENT C)

1 A Work Plan must be submitted for each funding year, e.g., Work Plan Year 1, Work Plan Year 2, Work Plan Year 3.