7. Conclusion
We have resolved all issues identified in the Phase 2 Scoping Memo with the possible exception of the DBP. We have ruled on all outstanding petitions for modification, except one. We decline to devote additional resources of the Commission, parties and customers to consider late Category M applications.30 (D.01-09-020, mimeo., page 22.)
Thus, except for the one unresolved petition and the DBP, all matters are now resolved, moot, or need no further consideration. The proceeding is left open only for resolution of the two remaining items.