| Word Document PDF Document |
JPO/avs 3/10/2003
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Joint Application of Southern California Edison Company and San Diego Gas and Electric Company for the 2002 Nuclear Decommissioning Cost Triennial Proceeding to Set Contribution Levels for the Companies' Nuclear Decommissioning Trust Funds and Address Other Related Decommissioning Issues.
Application 02-03-039
(Filed March 21, 2002)
ADMINISTRATIVE LAW JUDGE'S RULING CORRECTING TRANSCRIPT
By a letter dated October 9, 2002, Southern California Edison Company proposed several corrections to the transcript. All parties were sent copies of the letter. Since the corrections concern typographical errors without changing any material facts, and no party has expressed any objections to the corrections, I will adopt them.
THEREFORE, IT IS RULED that, Southern California Edison Company's proposed transcript corrections, attached hereto, are adopted.
Dated March 10, 2003, at San Francisco, California.
/s/ Jeffrey P. O'Donnell
Jeffrey P. O'Donnell
Administrative Law Judge
SOUTHERN CALIFORNIA EDISON COMPANY
A.02-03-039
TRANSCRIPT CORRECTION FORM
SCE Counsel: Carol Schmid-Frazee
Date: September 16, 2002
Volume: 1
Page No.
Line No.
Now Reads:
Should Read:
94
9
Page 319
Page 329
Date: September 17, 2002
Volume: 2
Page No.
Line No.
Now Reads:
Should Read:
122
14 & 15
decrease today 4.36 percent
decreases 4.36 percent
133
5
is going to accept case waste
is going to accept waste
187
4
appoint
acquaint
SOUTHERN CALIFORNIA EDISON COMPANY
A.02-03-039
TRANSCRIPT CORRECTION FORM
SCE Counsel: Paul Hunt
Date: September 17, 2002
Volume: 2
Page No.
Line No.
Now Reads:
Should Read:
133
21
In our C publication
In our NRC publication
CERTIFICATE OF SERVICE
I certify that I have by mail this day served a true copy of the original attached Administrative Law Judge's Ruling Correcting Error on all parties of record in this proceeding or their attorneys of record.
Dated March 10, 2003, at San Francisco, California.
/s/ Antonina V. Swansen
Antonina V. Swansen
NOTICE
Parties should notify the Process Office, Public Utilities Commission, 505 Van Ness Avenue, Room 2000, San Francisco, CA 94102, of any change of address to insure that they continue to receive documents. You must indicate the proceeding number on the service list on which your name appears.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
The Commission's policy is to schedule hearings (meetings, workshops, etc.) in locations that are accessible to people with disabilities. To verify that a particular location is accessible, call: Calendar Clerk (415) 703-1203.
If specialized accommodations for the disabled are needed, e.g., sign language interpreters, those making the arrangements must call the Public Advisor at (415) 703-2074,
TTY 1-866-836-7825 or (415) 703-5282 at least three working days in advance of the event.