Number of Documents: 708
|
|
|
Type:
EXPARTE
|
Filing Date:
November 16, 2007
|
Filed By:
San Diego Gas & Electric Company
|
|
Description:
SUMMARY: On November 13, 2007 Billy Blattner, Manager of Regulatory Relations
for San Diego Gas & Electric Company (SDG&E) had a telephone conversation with
Jack Stoddard, advisor to Pres. Peevey. Mike McClenahan, Director of
Procurement and Portfolio Design for SDG&E; Abby Snyder, Counsel for SDG&E; and
Steve Case, Counsel for SDG&E also participated in the phone call. Blattner
expressed concern that language pertaining to the Assignment term proposed in
the Proposed Decision (PD) could impede consents that resolve concerns about
risk. McClenahan explained that language pertaining to the Eligibility term
would hinder project financing and could impermissibly subject the utilities to
hindsight reasonableness reviews. Contact Person: Trish Rickard; telephone:
(415) 202-9986; e-mail: TRickard@SempraUtilities.com.
|
|
|
Type:
EXPARTE
|
Filing Date:
November 14, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On November 8, 2007 Meredith Allen, Director, Regulatory Relations for Pacific
Gas and Electric Company (PG&E) had a telephone conversation with Jackson
Stoddard, advisor to Pres. Peevey in San Francisco. Allen explained PG&E's
concern that the revised Draft Decision's discussion of the Assignment standard
term could limit consents to assignment that a utility would be able to provide
creating obstacles for sellers to obtain necessary financing. As a result, such
language could harm customers by limiting opportunities for RPS contracting
needed to meet the RPS goals and increasing customer costs.
|
|
|
Type:
EXPARTE
|
Filing Date:
November 8, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
SUMMARY: On November 7, 2007 Michael Hoover, Director of Regulatory Affairs of
Southern California Edison Company (SCE) had a telephone call with Jack
Stoddard, advisor to Pres. Peevey; J Eric Isken, Senior Attorney of SCE; Dawn
Anaiscourt, Attorney for SCE; William Walsh, Attorney of SCE; Ellen LeVine,
Legal Division of the CPUC; Paul Douglas, Energy Division of the CPUC; and Adam
Umanoff of Chadbourne and Park also participated in the phone call. Written
material (attached to this notice) was used. Walsh discussed the need to make
the Commission's standard Assignment term in the investor owned utilities'
("IOUs") renewables portfolio standard ("RPS") contracts modifiable. SCE
explained that the Commission's November 1, 2007 Proposed Decision (the "PD")
incorrectly assumes that the standard language ensures that a lender assignee
will be required to be bound by the power purchase agreement, including the
assumptions of payment and performance obligations thereunder, in the event of
a default. SCE stated that allowing the term to be modifiable provides greater
opportunity for the IOUs to be able to negotiate consent to collateral
assignment agreements with the renewable developers' lenders that ensure that
power purchase agreements remain in place in the event of a foreclosure. SCE
also indicated that it was satisfied with the standard Eligibility term
identified in the PD, except that SCE would recommend allowing the parties to
define "commercially reasonable efforts" elsewhere in the agreement. Contact
Person: Henry Romero; telephone: (626) 302-4124; e-mail address:
Henry.Romero@sce.com.
|
|
|
Type:
EXPARTE
|
Filing Date:
November 7, 2007
|
Filed By:
Independent Energy Producers Association
|
|
Description:
SUMMARY: On November 2, 2007 Steven Kelly, Policy Director of Independent
Energy Producers Association (IEP) met with Nancy Ryan, advisor to Pres. Peevey
in San Francisco. Also present were Andrew Schwartz, advisor to Pres. Peevey;
and Brian Cragg, outside counsel for IEP. Kelly raised a concern that one of
the proposed, non-modifiable standard contract terms mentioned in the Proposed
Decision in this proceeding would create an unacceptable risk to project
developers for changes in law that are outside the developers' control. Contact
Person: Melinda LaJaunie; telephone: (415) 392-7900.
|
|
|
Type:
EXPARTE
|
Filing Date:
November 5, 2007
|
Filed By:
Center for Energy Efficiency and Renewable Technologies
|
|
Description:
SUMMARY: On October 31, 2007 Sara Steck Myers, attorney for the Energy
Efficiency and Renewable Technologies (CEERT) had a telephone conversation with
F. Jackson Stoddard, advisor to Pres. Peevey. Myers stated that CEERT had filed
comments on the Proposed Decision of ALJ Mattson on Amended Petition for
Modification of Decision 04-06-014 Regarding Standard Terms and Conditions
(Proposed Decision) and had asked that the Proposed Decision be modified to
limit the non-modifiable Renewable Portfolio Standard (RPS) standard terms and
conditions (STCs) to the three identified in the Amended Petition. Myers
indicated that CEERT had supported the original petition filed by Pacific Gas
and Electric Company (PG&E) and Southern California Edison Company (SCE). Myers
also stated that while CEERT continued to believe that all RPS STCs terms
should be modifiable, as an alternative, CEERT did support the amended petition
and asked that the Proposed Decision be modified to limit the non-modifiable
STCs to just the three terms identified by PG&E and SCE in the Amended
Petition. Contact Person: Sara Steck Myers; telephone: (415) 387-1904; e-mail:
ssmyers@att.net.
|
|
|
Type:
EXPARTE
|
Filing Date:
November 2, 2007
|
Filed By:
San Diego Gas & Electric Company
|
|
Description:
SUMMARY: On October 30, 2007 Billy Blattner, Manager of Regulatory Relations
for San Diego Gas & Electric Company (SDG&E) had a telephone conversation with
Jack Stoddard, advisor to Pres. Peevey. Blattner expressed concern regarding
the Eligibility term proposed in the Proposed Decision (PD). Blatner noted that
a consensus is forming around "commercially reasonable" language offered by
SDG&E in its comments on the PD, which would address parties' concerns about
the potential impact of the provision on the ability to finance and develop
renewable energy projects. Contact Person: Trish Rickard; telephone: (415)
202-9986; e-mail: TRickard@SempraUtilities.com.
|
|
|
Type:
EXPARTE
|
Filing Date:
November 2, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On October 30, 2007 Meredith Allen, Director, Regulatory Relations for Pacific
Gas and Electric Company (PG&E) met with Jaclyn Marks, advisor to Cmmr. Simon
in San Francisco. Also present were Robert Mason, advisor to Cmmr. Simon; and
Gary Jeung, Director, Structured Transactions of PG&E. Written materials
(attached to the notice) were used. Jeung explained PG&E's concern that the
draft decision's proposed change to the Eligibility standard term and its
analysis of the Assignment standard term would harm customers by limiting
opportunities for RPS contracting needed to meet the RPS goals and increasing
customer costs. Allen stated that the draft decision's verification requirement
would only create delays in the preparation of filings for contract approval.
|
|
|
Type:
EXPARTE
|
Filing Date:
October 31, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
SUMMARY: On October 29, 2007 Michael Hoover, Director of Regulatory Affairs, of
Southern California Edison Company (SCE) had a telephone conversation with Jack
Stoddard, advisor to Cmmr. Peevey. Hoover discussed the need to approve SCE's
and Pacific Gas and Electric Company's ("PG&E") petition for modification of
the standard terms and conditions decision (D.04-060-14) (the "Petition") based
on the reasons outlined in SCE's comments to the Proposed Decision ("PD").
Hoover indicated that the standard non-modifiable Eligibility term, as drafted
in the PD, could potentially make it impossible for renewables portfolio
standard developers to receive financing for their projects. Contact Person:
Henry Romero; telephone: (626) 302-4124; e-mail: Henry.Romero@sce.com.
|
|
|
Type:
EXPARTE
|
Filing Date:
October 30, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On October 25, 2007 Meredith Allen, Director, Regulatory Relations for Pacific
Gas and Electric Company (PG&E) had a telephone conversation with Jackson
Stoddard, advisor to Pres. Peevey in San Francisco. Allen explained PG&E's
concern that the Draft Decision's proposed change to the Eligibility standard
term and its analysis of the Assignment standard term would harm customers by
limiting opportunities for RPS contracting needed to meet the RPS goals and
increasing customer costs. Allen further stated that the Draft Decision's
verification requirement would only create delays in the preparation of filings
for contract approval.
|
|
|
Type:
EXPARTE
|
Filing Date:
October 29, 2007
|
Filed By:
Independent Energy Producers Association
|
|
Description:
SUMMARY: On October 24, 2007 Douglas K. Kerner, attorney for the Independent
Energy Producers Association ("IEP"), had two separate telephone conversations
with Jackson Stoddard, advisor to Pres. Peevey. Kerner expressed IEP's concern
with the Proposed Decision of ALJ Mattson, particularly with respect to its
proposed, non-modifiable standard contract term. Kerner stated that the
proposed provision creates untenable project risk to developers and lenders,
and increased customer cost, due to changes in law. Contact Person: Eric
Janssen; telephone: (916) 447-2166; e-mail: ericj@eslawfirm.com.
|
|
|
Type:
COMMENTS
|
Filing Date:
October 29, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
Reply; on Proposed Decision.
|
|
|
Type:
COMMENTS
|
Filing Date:
October 29, 2007
|
Filed By:
Pacific Gas and Electric Company
|
|
Description:
Reply; On the Proposed Decision on Amended Petition for Modification of
D.04-06-014 (Standard Terms and Conditions).
|
|
|
Type:
COMMENTS
|
Filing Date:
October 23, 2007
|
Filed By:
San Diego Gas & Electric Company
|
|
Description:
On Proposed Decision Regarding Amended Petition for Modification of Decision
04-06-014.
|
|
|
Type:
COMMENTS
|
Filing Date:
October 22, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
On Proposed Decision.
|
|
|
Type:
COMMENTS
|
Filing Date:
October 22, 2007
|
Filed By:
Independent Energy Producers Association
|
|
Description:
On Draft Opinion on Amended Petition for Modification of Decision 04-06-014
Regarding Standard Terms and Conditions.
|
|
|
Type:
COMMENTS
|
Filing Date:
October 22, 2007
|
Filed By:
Center for Energy Efficiency and Renewable Technologies
|
|
Description:
On the Proposed Decision of ALJ Mattson On Amended Petition for Modification of
Decision 04-06-014.
|
|
|
Type:
COMMENTS
|
Filing Date:
October 22, 2007
|
Filed By:
Pacific Gas and Electric Company
|
|
Description:
On the Proposed Decision on Amended Petition for Modification of D.04-06-014.
|
|
|
Type:
COMMENTS
|
Filing Date:
October 19, 2007
|
Filed By:
DRA/OBIORA/CPUC
|
|
Description:
On the Opinion on Amended Petition for Modification of Decision 04-06-014
Regarding Standard Terms and Conditions.
|
|
|
Type:
PROPOSED DECISION
|
Filing Date:
October 1, 2007
|
Filed By:
ALJ/MATTSON/CPUC
|
|
Description:
Opinion on Amended Petition for Modification of Decision 04-06-014 Regarding
Standard Terms and Conditions. Opening Comments, which shall not exceed 15
pages, are due no later than October 21, 2007. Reply Comments are due 5 days
after Opening Comments are filed.
|
|
|
Type:
COMMENTS
|
Filing Date:
September 14, 2007
|
Filed By:
OBIORA/DRA/CPUC
|
|
Description:
Reply; On the Proposed Decision on Petition for Modification of D.05-12-042.
|
|
|
Type:
COMMENTS
|
Filing Date:
September 10, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
On Proposed Decision.
|
|
|
Type:
COMMENTS
|
Filing Date:
September 10, 2007
|
Filed By:
California Wind Energy Association
Concentrated Solar Power Alliance
The Green Power Institute
|
|
Description:
on the Proposed Decision of ALJ Simon on the California Wind Energy
Association's and The Green Power Institute's Petition for Modification of
Decision 05-12-042.
|
|
|
Type:
PROPOSED DECISION
|
Filing Date:
August 21, 2007
|
Filed By:
ALJ/SIMON/CPUC
|
|
Description:
Opinion on Petition for Modification of Decision 05-12-042. Opening Comments,
which shall not exceed 15 pages, are due no later than September 10, 2007.
Reply Comments are due 5 days after Opening Comments are filed.
|
|
|
Type:
RULING
|
Filing Date:
July 30, 2007
|
Filed By:
ALJ/SIMON/CPUC
|
|
Description:
ALJ's Ruling on Motion for Party Status.
|
|
|
Type:
REPLY
|
Filing Date:
July 24, 2007
|
Filed By:
California Wind Energy Association
The Green Power Institute
|
|
Description:
to the Petition for Modification of Decision 05-12-042.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 17, 2007
|
Filed By:
CALIFORNIA COGENERATION COUNCIL
|
|
Description:
to the Petition of the California Wind Energy Association and Green Power
Institute for Modification of Decision 05-12-042.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 17, 2007
|
Filed By:
Pacific Gas and Electric Company
|
|
Description:
to Petition of the California Wind Energy Association and the Green Power
Institute for Modification of Decision 05-12-042: Interim Opinion Adopting
Methodology for the 2005 Marketing Price Referent.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 17, 2007
|
Filed By:
San Diego Gas & Electric Company
|
|
Description:
to Petition for Modification of D.05-12-042.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 17, 2007
|
Filed By:
Union of Concerned Scientists
|
|
Description:
to the Petition of the California Wind Energy Association and the Green Power
Institute for Modification of Decision 05-12-042: Interim Opinion Adopting
Methodology for the 2005 Market Price Referent.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 17, 2007
|
Filed By:
Center for Energy Efficiency and Renewable Technologies
|
|
Description:
to Petition of the California Wind Energy Association and Green Power Institute
for Modification of Decision 05-12-042.
|
|
|
Type:
COMMENTS
|
Filing Date:
July 17, 2007
|
Filed By:
DRA/OBIORA/CPUC
|
|
Description:
on Petition of California Wind Energy Association and the Green Power Institute
for Modification of Decision 05-12-042.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 17, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
Opposition to the CALWEA and the Green Power Institute Petition for
Modification of Decision 05-12-042.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 17, 2007
|
Filed By:
Concentrated Solar Power Alliance
|
|
Description:
to the Petition of the California Wind Energy Association and Green Power
Institute for Modification of Decision 05-12-042.
|
|
|
Type:
EXPARTE
|
Filing Date:
July 17, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On July 12, 2007, Meredith Allen, Regulatory Relations of Pacific Gas and
Electric Company (PG&E) met with Andrew Schwartz, advisor to Pres. Peevey in
San Francisco. Also present were Jim Shandalov, Principal, Energy Procurement
of PG&E; and Michael Hoover, Director, Regulatory Affairs of Southern
California Edison (SCE). Written materials (attached to the notice) were used.
Allen stated that the Commission should adopt the modifications to the RPS
Standard Terms and Conditions decision (D.04-06-014) proposed in the Joint
Amended petition of PG&E and SCE. These proposed modifications promote the RPS
and incorporate the lessons learned through experience with the program.
|
|
|
Type:
MOTION
|
Filing Date:
July 17, 2007
|
Filed By:
Concentrated Solar Power Alliance
|
|
Description:
for Party Status by the Concentrated Solar Power Alliance.
|
|
|
Type:
REPLY
|
Filing Date:
July 9, 2007
|
Filed By:
Pacific Gas and Electric Company
Southern California Edison Company
|
|
Description:
to Responses on Amended Petition for Modification of D.04-06-014 regarding
standard terms and conditions required for renewables portfolio standard
contracts (filing authorized by ALJ Mattson per email ruling dated June 19,
2007).
|
|
|
Type:
RESPONSE
|
Filing Date:
July 2, 2007
|
Filed By:
Independent Energy Producers Association
|
|
Description:
to the Amended Petition for Modification.
|
|
|
Type:
RESPONSE
|
Filing Date:
July 2, 2007
|
Filed By:
San Diego Gas & Electric Company
|
|
Description:
to Amended Petition for Modification of Decision 04-06-014.
|
|
|
Type:
RESPONSE
|
Filing Date:
June 29, 2007
|
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
|
|
Description:
to Amended Petititon for Modification of D.04-06-014.
|
|
|
Type:
RULING
|
Filing Date:
June 28, 2007
|
Filed By:
ALJ/SIMON/CPUC
|
|
Description:
on Motion to Expedite. The time for filing and service of responses to the
petition of the California Wind Energy Association (CalWEA) and the Green Power
Institute (GPI), for Modification of Decision 05-12-042, is shortened to July
17, 2007. CalWEA and GPI may file and serve a reply to the responses not later
than July 24, 2007.
|
|
|
Type:
PETITION FOR MODIFICATION
|
Filing Date:
June 25, 2007
|
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
THE GREEN POWER INSTITUTE
|
|
Description:
of Decision 05-12-042: Interim Opinion Adopting Methodology for the 2005 Market
Price Referent.
|
|
|
Type:
MOTION
|
Filing Date:
June 25, 2007
|
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
THE GREEN POWER INSTITUTE
|
|
Description:
for expedited decision and order shortening time related to its concurrently
filed Petition for Modification of Decision 05-12-042: Interim Opinion Adopting
Methodology for the 2005 Market Price Referent.
|
|
|
Type:
EXPARTE
|
Filing Date:
June 22, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
SUMMARY: On June 19, 2007, Michael Hoover, Director, Regulatory Affairs,
Southern California Edison Company (SCE) had a telephone conversation with Andy
Schwartz, advisor to Pres. Peevey. Hoover discussed the need to approve SCE's
and Pacific Gas and Electric Company's (PG&E) petition for modification of
D.04-06-014 (Petition) based on the reasons outlined in the Petition and the
recently filed amended petition for modification. Hoover explained that the
recent scoping memo for the 2008 renewables portfolio standard procurement plan
reinforces the need to grant SCE's and PG&E's Petition. Contact person: Henry
Romero, telephone: (626) 302-4124; e-mail: henry.Romero@sce.com
|
|
|
Type:
COMMENTS
|
Filing Date:
June 19, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
Supplemental; in support of Amended Petition for Modification of Decision
04-06-014 of PG&E and SCE regarding Standard Terms and Conditions Required for
Renewables Portfolio Standard Contracts.
|
|
|
Type:
COMMENTS
|
Filing Date:
June 18, 2007
|
Filed By:
Independent Energy Producers Association
|
|
Description:
Reply; on the Proposed Decision.
|
|
|
Type:
COMMENTS
|
Filing Date:
June 18, 2007
|
Filed By:
Pacific Gas and Electric Company
Southern California Edison
|
|
Description:
Reply; on ALJ Mattson's Proposed Decision entitled "Opinion on Petition for
Modification of Decision 04-06-014 regarding process for changing, and lifting
restrictions on, designated standard terms and conditions"
|
|
|
Type:
PETITION FOR MODIFICATION
|
Filing Date:
June 15, 2007
|
Filed By:
Pacific Gas and Electric Company
Southern California Edison Company
|
|
Description:
Amended; of Decison 04-06-014 regarding Standard Terms and Conditions Required
for Renewables Portfolio Standard Contracts.
|
|
|
Type:
COMMENTS
|
Filing Date:
June 11, 2007
|
Filed By:
Pacific Gas and Electric Company
|
|
Description:
on ALJ Mattson's Proposed Decision entitled Opinion on Petition for
Modification of D0406014 Regarding Process for Changing, and
Lifting
Restrictions on, Designated Standard Terms and Conditions.
|
|
|
Type:
COMMENTS
|
Filing Date:
June 11, 2007
|
Filed By:
San Diego Gas & Electric Company
|
|
Description:
on Proposed Decision regarding Petition for Modification of Decision 04-06-014.
|
|
|
Type:
COMMENTS
|
Filing Date:
June 8, 2007
|
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
|
|
Description:
of the Center for Energy Efficiency and Renewable Technologies on the Proposed
Decision of ALJ Mattson.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
May 29, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
pursuant to ALJ Ruling dated April 30, 2007.
|
|
|
Type:
MOTION
|
Filing Date:
May 29, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
for Reconsideration of ALJ Ruling dated April 30, 2007 and Request for
Continued Confidential Treatment of Documents provided under seal.
|
|
|
Type:
MOTION
|
Filing Date:
May 29, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
Supplemental Motion for Confidential Protection pursuant to ALJ Ruling dated
April 30, 2007.
|
|
|
Type:
NOTICE
|
Filing Date:
May 29, 2007
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
of Availability pursuant to ALJ Ruling dated April 30, 2007.
|
|
|
Type:
PROPOSED DECISION
|
Filing Date:
May 22, 2007
|
Filed By:
ALJ/MATTSON/CPUC
|
|
Description:
Opinion on Petition for Modification of Decision 04-06-014 Regarding Process
for Changing, and Lifting Restrictions on, Designated Standard Terms and
Conditions. Opening Comments, which shall not exceed 15 pages, are due no
later than June 11, 2007. Reply Comments are due 5 days after Reply Comments
are filed.
|
|
|
Type:
RESPONSE
|
Filing Date:
May 22, 2007
|
Filed By:
San Diego Gas & Electric Company
|
|
Description:
Compliance Filing: Unredacted Version of 2006 Renewable Portfolio Standard
Procurement Plan.
|
|
|
Type:
REPORT
|
Filing Date:
May 22, 2007
|
Filed By:
Southern California Edison Company
|
|
Description:
(PUBLIC VERSION) 2006 Renewables Portfolio Standard Procurement Plan.
|
|
|
Type:
RULING
|
Filing Date:
April 30, 2007
|
Filed By:
ALJ/MATTSON/CPUC
|
|
Description:
on Southern California Edison Company motions to file data under seal.
|
|
|
Type:
RULING
|
Filing Date:
April 30, 2007
|
Filed By:
ALJ/MATTSON/CPUC
|
|
Description:
on PG&E' Company's Motions to File Data Under Seal (related to the Commission's
Renewables Portfolio Standard Program).
|
|
|
Type:
RULING
|
Filing Date:
April 30, 2007
|
Filed By:
ALJ/MATTSON/CPUC
|
|
Description:
on SDG&E Company's Motions to File Data Under Seal (related to the Commission's
Renewables Portfolio Standard Program).
|
|
|
Type:
COMMENTS
|
Filing Date:
February 28, 2007
|
Filed By:
Independent Energy Producers Association
|
|
Description:
on Petition for Modification of Decision 04-06-014 of PG&E and SCE regarding
standard terms and conditions required for Renewables Portfolio Standard
Contracts.
|
|
|
Type:
RESPONSE
|
Filing Date:
February 28, 2007
|
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
|
|
Description:
to Petition for Modification of Decision 04-06-014 of Pacific Gas and Electric
Company and Southern California Edison Company.
|
|
|
Type:
PETITION FOR MODIFICATION
|
Filing Date:
February 1, 2007
|
Filed By:
Pacific Gas and Electric Company
Southern California Edison Company
|
|
Description:
of D04-06-014 regarding standard terms and conditions required for Renewables
Portfolio Standard contracts.
|
|
|
Type:
PETITION FOR MODIFICATION
|
Filing Date:
November 20, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
of D06-10-012.
|
|
|
Type:
EXPARTE
|
Filing Date:
August 15, 2006
|
Filed By:
ALLIANCE FOR RETAIL ENERGY MARKETS
|
|
Description:
On August 10, 2006, Stacy Aguayo of APS Energy Services, representing the
Alliance for Retail Energy Markets (AReM), met with Andrew Campbell, advisor to
Cmmr. Chong, Belinda Gatti, advisor to Cmmr. Brown, Robert Lane and Lindsay
Brown, advisors to Cmmr. Bohn, Nancy Ryan, advisor to Pres. Peevey, Julie
Fitch, Director of Strategic Planning Division, Andrew Schwartz of the Division
of Strategic Planning, and Bill Chen of Constellation NewEnergy, and Gregory
Klatt of Douglass & Liddell, representing AReM. AReM representatives voiced
concern about the timing of the Commission's implementation of the Renewables
Portfolio Standard (RPS) for electric service providers (ESPs). AReM
representatives expressed the need for interim guidance from the Commission
regarding the manner in which ESPs are to participate in the RPS program,
particularly for 2006, in the event that formal decisions resolving pending
matters relating to ESP compliance are not adopted very soon. AReM
representatives reiterated the need for the Commission to address issues
relating to the use of unbundled Renewable Energy Credits.
|
|
|
Type:
REQUEST
|
Filing Date:
July 25, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
for Award of Compensation.
|
|
|
Type:
REQUEST
|
Filing Date:
July 25, 2006
|
Filed By:
THE GREEN POWER INSTITUTE
|
|
Description:
for Award of Compensation for Substantial Contribution to D.06-05-039.
|
|
|
Type:
REQUEST
|
Filing Date:
July 25, 2006
|
Filed By:
UNION OF CONCERNED SCIENTISTS
|
|
Description:
for an award of compensation for substantial contributions to D05-07-039,
D05-10-014, D05-11-025, D05-12-42, and D06-05-039 and for participation in
utility procurement preview groups.
|
|
|
Type:
RULING
|
Filing Date:
July 12, 2006
|
Filed By:
ALJ/MATTSON/CPUC
|
|
Description:
REGARDING FILING OF INTERVENOR COMPENSATION REQUESTS. The requests, if filed,
should be filed by July 25, 2006.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
June 9, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Amended 2006 RFP Protocol.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
June 9, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
(PUBLIC & CONFIDENTIAL VERSIONS) Amended 2006 Short-Term Renewable Procurement
Plan.
|
|
|
Type:
RULING
|
Filing Date:
May 23, 2006
|
Filed By:
ALJ/MATTSON/PUC
|
|
Description:
Grants PG&E's motions of May 15, 2006 for leave to supplement its comments on
reporting and compliance issues and for leave to file an appendix to its
Supplement under seal.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
Reply; on Proposed Decision of ALJ Mattson.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
Reply; on the Draft Decision of ALJ Mattson.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
May 22, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
motion for leave to file confidential material under seal; confidential
materials attached and filed under seal, namely, PG&E's RPS compliance strategy.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
|
|
Description:
reply; on the proposed decision of ALJ Mattson on 2006 RPS Procurement Plans.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
|
|
Description:
reply; on the proposed decision of ALJ Mattson.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
INDEPENDENT ENERGY PRODUCERS ASSOCIATION
|
|
Description:
reply; on the draft decision of ALJ Mattson.
|
|
|
Type:
EXPARTE
|
Filing Date:
May 22, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On May 17, 2006, Frank De Rosa, Director, Power Contract, Pacific Gas and
Electric Company (PG&E), met with Andrew Campbell, advisor to Cmmr. Chong, in
San Francisco. Also present were Meredith Allen, Chief, Regulatory Relations,
and Charles Post, Senior Power Contract Specialist, for PG&E. Confidential
written materials, submitted under seal along with a motion for leave to file
under seal, were used. A redacted version of the written material is attached
to the notice. Allen explained that the Commission should adopt the full
earmarking proposal. De Rosa stated that the full earmarking accommodates the
lead times for developing new renewables projects.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Reply; on Draft Decision of ALJ Mattson.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Reply; on Draft Decision (of ALJ Mattson) adopting 2006 RPS Procurement Plans.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 22, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
reply; on the proposed decision conditionally approving procurement plans for
2006 RPS solicitations.
|
|
|
Type:
RULING
|
Filing Date:
May 18, 2006
|
Filed By:
ALJ/MATTSON/PUC
|
|
Description:
Denies the May 15, 2006 motion of PG&E to shorten time for response, as set
forth.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
May 18, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
motion for leave to file confidential material under seal; confidential
material attached and filed under seal, namely, PG&E's RPS compliance strategy.
|
|
|
Type:
EXPARTE
|
Filing Date:
May 18, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On May 15, 2006, Meredith Allen, Chief, Regulatory Relations, Pacific Gas and
Electric Company, met with Peter Hanson, advisor to Cmmr. Brown, in San
Francisco. Also present was Belinda Gatti, advisor to Cmmr. Brown. Confidential
written materials, submitted under seal along with a motion for leave to file
under seal, were used. A redacted version of the written material is attached
to the notice. Allen explained that the Commission should adopt the full
earmarking proposal.
|
|
|
Type:
RULING
|
Filing Date:
May 17, 2006
|
Filed By:
CMMR/PEEVEY/PUC
|
|
Description:
Adopting 2006 Transmision Ranking Cost Reports.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
May 16, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
motion for leave to file confidential material under seal; confidential
material attached and filed under seal, namely, PG&E's RPS Compliance Strategy.
|
|
|
Type:
EXPARTE
|
Filing Date:
May 16, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
On May 11, 2006, Meredith Allen, Chief, Regulatory Relations, Pacific Gas and
Electric Company, met with Stephen St. Marie, advisor to Cmmr. Bohn, in San
Francisco. Confidential written materials, submitted under seal along with a
motion for leave to file under seal, were used. A redacted version of the
written material is attached to the notice. Allen explained that the Commission
should adopt the full earmarking proposal.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
COALITION OF CALIFORNIA UTILITY EMPLOYEES
|
|
Description:
on the draft decision of ALJ Mattson.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
UNION OF CONCERNED SCIENTISTS
|
|
Description:
on the proposed decision adopting 2006 RPS procurement plans.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
on Proposed Decision of ALJ Mattson.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
DRA/OBIORA/PUC
|
|
Description:
opening; on the draft decision conditionally approving procurement plans for
2006 renewable procurement standards solicitations.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
CALIFORNIA WIND ENERGY ASSOCIATION
|
|
Description:
on the draft decision of ALJ Mattson.
|
|
|
Type:
MOTION
|
Filing Date:
May 15, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
for leave to supplement comments on reporting and compliance issues; supplement
attached.
|
|
|
Type:
MOTION
|
Filing Date:
May 15, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
for Order Shortening Time for Reply to Seven Days.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
on Draft Decision (of ALJ Mattson).
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
opening; on the draft decision conditionally approving procurement plans for
2006 renewable procurement standards solicitations. ALJ Mattson conditionally
approving procurement plans for 2006 RPS Solicitations, addressing TOD
Benchmarking Methodology, and closing proceeding.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
INDEPENDENT ENERGY PRODUCERS ASSOCIATION
|
|
Description:
on the draft decision of ALJ Mattson on 2006 RPS procurement plans.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
May 15, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
motion for leave to file confidential material under seal; confidential
materials attached and filed under seal; namely, confidential appendix to
Supplement to Comments.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
opening; on the proposed decision conditionally approving procurement plans,
etc.
|
|
|
Type:
COMMENTS
|
Filing Date:
May 15, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
on the draft decision of ALJ Mattson: Opinion Conditionally Approving
Procurement Plans, etc.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
May 10, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
Motion for leave to file under seal confdidential material under seal;
confidential materials attached and filed under seal, namely, PG&E's RPS
Compliance Strategy.
|
|
|
Type:
EXPARTE
|
Filing Date:
May 10, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
LATE FILED. On May 3, 2006, Fong Wan, Vice President, Energy Procurement,
Pacific Gas and Electric Company (PG&E), met with Nancy Ryan, advisor to Pres.
Peevey, in San Francisco. Also present were Frank De Rosa, Director, Power
Contracts, and Meredith Allen, Chief, Regulatory Relations, for PG&E.
Confidential written materials, submitted under seal with a motion for leave to
file under seal, were used. A redacted version of the written material is
attached to the notice. Wan and De Rosa explained that the Commission should
adopt the full earmarking proposal. Wan indicated that full earmarking would
allow PG&E to sign contracts in the best interests of its customers. De Rosa
stated that full earmarking accommodates the lead times for developing new
renewables projects, a key policy objective of the RPS.
|
|
|
Type:
SUPPLEMENT
|
Filing Date:
May 4, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
to Request for an Award of Compensation for Substantial Contributions to
D.05-07-039, D.05-10-014, D.05-11-025 and D.05-12-042
|
|
|
Type:
REQUEST
|
Filing Date:
May 2, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
for award of compensation.
|
|
|
Type:
DRAFT DECISION
|
Filing Date:
April 25, 2006
|
Filed By:
ALJ/MATTSON/PUC
|
|
Description:
Opinion Conditionally Approving Procurement Plans for 2006 RPS Solicitations,
Addressing TOD Benchmarking Methodology, and Closing Proceeding. Comments are
due May 15, 2006; reply comments - 5 days after comments are filed.
|
|
|
Type:
DRAFT DECISION
|
Filing Date:
April 20, 2006
|
Filed By:
ALJ/SIMON/PUC
|
|
Description:
Opinion Denying Petition for Modification of D05-07-039.Comments are due May
10, 2006; reply comments - 5 days after comments are filed.
|
|
|
Type:
REPORT
|
Filing Date:
April 6, 2006
|
Filed By:
GOLDEN STATE WATER COMPANY
|
|
Description:
Preliminary Renewable Portfolio Report for Bear Valley Electric Service.
|
|
|
Type:
REQUEST
|
Filing Date:
April 3, 2006
|
Filed By:
THE UTILITY REFORM NETWORK
|
|
Description:
for an award of compensation for substantial contributions to decisions
D04-06-014, D04-06-015, D04-07-029, D05-05-011, D05-07-039, D05-10-014,
D05-11-025, D05-12-042 and D06-01-046, and for participation in Utility
Procurement Review Groups.
|
|
|
Type:
RULING
|
Filing Date:
March 30, 2006
|
Filed By:
ALJ/SIMON/PUC
|
|
Description:
Finds Aglet Consumer Alliance eligible to claim intervenor compensation.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
March 27, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Transmission Ranking Cost Report for Renewable Portfolio Standard Procurement.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
Reply; on RPS Reporting and Compliance Issues.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
THE UTILITY REFORM NETWORK
UNION OF CONCERNED SCIENTISTS
|
|
Description:
joint, reply; on Renewables Portfolio Standard reporting and compliance issues.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
reply; on reporting and compliance issues.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
DRA/OBIORA/PUC
|
|
Description:
reply; on the Renewable Portfolio Standards program annual procurement targets
reporting and compliance staff White Paper.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
ALLIANCE FOR RETAIL ENERGY MARKETS
|
|
Description:
Reply; on Staff White Paper on Annual Procurement Targets and related Reporting
and Compliance issues.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Reply; on Staff White Paper titled 'RPS Annual Procurement Targets: Reporting
and Compliance.'
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Reply; regarding Reporting and Compliance Staff White Paper.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 22, 2006
|
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
|
|
Description:
reply; on Energy Division White Paper on RPS reporting and compliance.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
March 15, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Transmission Ranking Cost Report for Renewable Portfolio Standard Procurement.
|
|
|
Type:
REPORT
|
Filing Date:
March 15, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
2006 Transmission Ranking Cost Report in compliance with the Ruling of November
9, 2005.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
THE UTILITY REFORM NETWORK
UNION OF CONCERNED SCIENTISTS
|
|
Description:
joint; on renewables portfolio standard reporting and compliance issues.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
CENTER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES
|
|
Description:
on Energy Division White Paper on RPS Reporting and Compliance.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
on reporting and compliance issues.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
on Staff White Paper titled 'RPS Annual Procurement Targets: Reporting and
Compliance.'
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
CITY AND COUNTY OF SAN FRANCISCO
CITY OF CHULA VISTA
|
|
Description:
regarding reporting and compliance for the renewable portfolio standard.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
DRA/OBIORA/PUC
|
|
Description:
opening; on the renewable portfolio standards program annual procurement
targets reporting and compliance staff white paper.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
re: Reporting and Compliance Staff White Paper.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 13, 2006
|
Filed By:
ALLIANCE FOR RETAIL ENERGY MARKETS
|
|
Description:
on the Staff White Paper on Annual Procurement Targets and related Reporting
and Compliance issues.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 10, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
on RPS reporting and compliance issues [pursuant to the February 23, 2006
ruling].
|
|
|
Type:
SUPPLEMENT
|
Filing Date:
March 6, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
to Compliance Filing of 03/01/06 re: Achievement of 2005 Renewable Portfolio
Standard Annual Procurement Target.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 1, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
reply; to comments on Time of Delivery Factors and Benchmarking Proposal.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
March 1, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
[in compliance with D03-06-071 and D05-07-039, Ordering Paragraph 17]Reporting
Achievement of Annual Procurement Target for Renewable Generation Pursuant to
Renewable Portfolio Standard.
|
|
|
Type:
SUPPLEMENT
|
Filing Date:
March 1, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
to June 13, 2005 Request for Intervenor Compensation.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
March 1, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
March 1, 2006 Renewables Portfolio Standard.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 1, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Reply; on [its] Time of Delivery Profile Benchmarking and Evaluation Proposal.
|
|
|
Type:
COMMENTS
|
Filing Date:
March 1, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Reply; on [its] proposal for Benchmarking and evaluating Time of Delivery
Profiles.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
March 1, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
re: Achievement of 2005 Renewable Poretfolio Standard Annual Procurement Target.
|
|
|
Type:
RULING
|
Filing Date:
February 23, 2006
|
Filed By:
ALJ/MATTSON/SIMON/PUC
|
|
Description:
Directs parties to file comments on the staff white paper titled "RPS Annual
Procurement Targets: Reporting and Compliance", by March 10, 2006, and reply
comments by March 17, 2006.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
February 21, 2006
|
Filed By:
SIERRA PACIFIC POWER COMPANY
|
|
Description:
Proposals for Compliance with California's Renewables Portfolio Standards
Program.
|
|
|
Type:
MISCELLANEOUS FILING
|
Filing Date:
February 17, 2006
|
Filed By:
PACIFICORP
|
|
Description:
Proposal for RPS Participation; pursuant to ALJ Simon's Ruling of February 3,
2006.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
February 17, 2006
|
Filed By:
MOUNTAIN UTILITIES
|
|
Description:
Proposal.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
February 17, 2006
|
Filed By:
ALLIANCE FOR RETAIL ENERGY MARKETS
|
|
Description:
Proposal for the Participation of Electric Service Providers in the Renewable
Portfolio Standard Program under the framework established in Decision
05-11-025.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
February 17, 2006
|
Filed By:
CITY AND COUNTY OF SAN FRANCISCO
CITY OF CHULA VISTA
|
|
Description:
Proposal for Renewable Portfolio Standards Program Participation for Community
Choice Aggregators.
|
|
|
Type:
REQUEST
|
Filing Date:
February 16, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
for an Award of Compensation for Substantial Contributions to D.05-07-039,
D.05-10-014, D.05-11-025 and D.05-12-042.
|
|
|
Type:
COMMENTS
|
Filing Date:
February 15, 2006
|
Filed By:
GREEN POWER INSTITUTE
|
|
Description:
on the TOD benchmark proposals of PG&E, SCE and SDG&E.
|
|
|
Type:
COMMENTS
|
Filing Date:
February 15, 2006
|
Filed By:
SOLEL INC.
|
|
Description:
on the large utility proposals for benchamarking and evaluating Time of
Delivery profiles.
|
|
|
Type:
COMMENTS
|
Filing Date:
February 15, 2006
|
Filed By:
DRA/OBIORA/PUC
|
|
Description:
on the large utility proposals for benchamarking and evaluating Time of
Delivery profiles.
|
|
|
Type:
COMMENTS
|
Filing Date:
February 15, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
on IOU Proposals for Benchmarking TOD Profiles.
|
|
|
Type:
REPORT
|
Filing Date:
February 14, 2006
|
Filed By:
PILOT POWER GROUP, INC.
|
|
Description:
(REDACTED VERSION) Preliminary Renewable Portfolio.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 14, 2006
|
Filed By:
PILOT POWER GROUP, INC.
|
|
Description:
for Leave to File Confidential Material Under Seal and for Protective Order;
Confidential Materials Attached and Filed Under Seal, namely, Unredacted
Version of Preliminary Renewable Portfolio Report.
|
|
|
Type:
SUPPLEMENT
|
Filing Date:
February 8, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
to the Draft 2006 Renewables Portfolio Standard Solicitation Protocol filed
December 22, 2005, and TOD Factors Benchmarking Study.
|
|
|
Type:
SUPPLEMENT
|
Filing Date:
February 8, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
to Proposal for Benchmarking and Evaluating Time-of-Delivery Profiles.
|
|
|
Type:
RULING
|
Filing Date:
February 3, 2006
|
Filed By:
ALJ/SIMON/PUC
|
|
Description:
Extends time to file proposals for RPS participation, to February 17, 2006.
Comments on such proposals are due by March 7, 2006; reply comments - March 15,
2006.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 1, 2006
|
Filed By:
CONSTELLATION NEWENERGY, INC.
|
|
Description:
motion for leave to file confidential material under seal and for protective
order.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 1, 2006
|
Filed By:
PRAXAIR PLAINFIELD, INC.
|
|
Description:
motion for leave to file confidential material under seal and for protective
order.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 1, 2006
|
Filed By:
COMMERCE ENERGY, INC.
|
|
Description:
for leave file unredacted version of Preliminary Renewable Portfolio Report
under seal.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 1, 2006
|
Filed By:
STRATEGIC ENERGY, LLC
|
|
Description:
for leave to file unredacted version of Preliminary Renewable Portfolio Report
under seal.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 1, 2006
|
Filed By:
CALPINEPOWERAMERICA-CA, LLC
|
|
Description:
for leave to file Exhibit A to Preliminary Renewable Portfolio Report under
seal.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 1, 2006
|
Filed By:
APS ENERGY SERVICES
|
|
Description:
for leave to file unredacted version of Preliminary Renewable Portfolio Report
under seal.
|
|
|
Type:
LAW & MOTION
|
Filing Date:
February 1, 2006
|
Filed By:
SEMPRA ENERGY SOLUTIONS
|
|
Description:
Motion for Leave to File Confidential Information Under Seal and for Adoption
of Protective Order, namely, Preliminary Report in compliance with the
Renewable Portfolio Standards.
|
|
|
Type:
COMMENTS
|
Filing Date:
January 31, 2006
|
Filed By:
PACIFIC GAS AND ELECTRIC COMPANY
|
|
Description:
reply; to comments on 2006 RPS Plan.
|
|
|
Type:
COMMENTS
|
Filing Date:
January 31, 2006
|
Filed By:
UNION OF CONCERNED SCIENTISTS
|
|
Description:
reply; on 2006 RPS procurement plans and draft requests for offers.
|
|
|
Type:
COMMENTS
|
Filing Date:
January 31, 2006
|
Filed By:
ALLIANCE FOR RETAIL ENERGY MARKETS
|
|
Description:
Reply; on 2006 RPS Procurement Plans of PG&E, SDG&E and SCE.
|
|
|
Type:
COMMENTS
|
Filing Date:
January 31, 2006
|
Filed By:
SAN DIEGO GAS & ELECTRIC COMPANY
|
|
Description:
Reply; concerning 2006 Short-Term Renewable Procurement Plan and Draft RFO.
|
|
|
Type:
COMMENTS
|
Filing Date:
January 31, 2006
|
Filed By:
SOUTHERN CALIFORNIA EDISON COMPANY
|
|
Description:
Reply; on 2006 RPS Procurement Plan.
|
|
|
Type:
COMMENTS
|
Filing Date:
January 31, 2006
|
Filed By:
DRA/OBIORA/PUC
|
|
Description:
reply; on the 2006 renewable energy procurement plans of Edison, PG&E, and
SDG&E.
|
|
|
Type:
COMMENTS
|
Filing Date:
January 30, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
Reply; to Comments of Green Power Institute.
|
|
|
Type:
RESPONSE
|
Filing Date:
January 27, 2006
|
Filed By:
AGLET CONSUMER ALLIANCE
|
|
Description:
in Opposition to Motion of CCSF and City of Chula Vista.
|
|
|
Type:
COMPLIANCE FILING
|
Filing Date:
January 26, 2006
|
Filed By:
CORAL POWER, LLC
|
|
Description:
Preliminary Renewable Portfolio Report.
|
|
|
Type:
REPORT
|
Filing Date:
January 26, 2006
|
Filed By:
CONSTELLATION NEWENERGY, INC.
|
|
Description:
PUBLIC VERSION; preliminary renewable portfolio report.
|
|
|
Type:
REPORT
|
Filing Date:
January 26, 2006
|
Filed By:
CALP |