Scope of Work for SB 1038 Renewables
Transmission Study

Per my January 29, 2003 ruling, the utilities have been working with Energy Division to develop a proposed scope of work for the Commission's SB 1038 study. Based on those discussions, Energy Division has developed a description of the scope of work, which is appended as Attachment 2. Utilities and interested parties may submit comments on this description within 10 days from the date of this ruling. Reply comments are due five days thereafter. After further consultation with Energy Division, I will issue a ruling setting forth the scope of the SB 1038 transmission study.