Word Document PDF Document

PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Item #19

ID #9732

ENERGY DIVISION RESOLUTION E-4359

RESOLUTION

Resolution E-4359. Southern California Edison Resolution E-4359. Southern California Edison (SCE) requests approval of thirteen renewable power purchase agreements and four related amendments to two existing power purchase and sale agreements with WM Energy Solutions, Inc.

PROPOSED OUTCOME: This Resolution approves cost recovery for twelve renewable power purchase agreements resulting from SCE's 2009 Renewables Standard Contracts Program and four related amendments to two existing purchase and sale agreements with WM Energy Solutions, Inc. These power purchase agreements and amendments are approved without modification.

ESTIMATED COST: The estimated total cost of the thirteen power purchase agreements is $548,000,000.

By Advice Letter 2457-E filed on March 29, 2010 and Advice Letter 2457-E-A filed on June 15, 2010.

__________________________________________________________

SUMMARY

Southern California Edison's renewable power purchase agreements (PPA) and amendments comply with the Renewables Portfolio Standard (RPS) procurement guidelines and are approved

Southern California Edison (SCE) filed advice letter (AL) 2357-E requesting Commission review and approval of thirteen renewable power purchase agreements resulting from SCE's 2009 Renewables Standard Contracts (RSC) Program and four related amendments to two existing power purchase and sale agreements with WM Energy Solutions, Inc (WMES), the seller under two of the RSC PPAs. The WMES amendments transition the existing RPS PPAs into RSC PPAs. SCE filed AL 2357-E-A to modify certain information contained in the confidential Appendix C of AL 2357-E. On August 23, 2010, SCE wrote a letter to Commission staff that one of the RSC PPAs (The Aeromen LLC) was cancelled; thus, this Resolution approves only twelve RSC PPAs.

The following table provides a summary of the twelve approved RSC contracts:

Generating Facility

Technology Type

Term

(Years)

Capacity

(MW)

Energy

(GWh/year)

Contract Delivery

Start

Date

Location

Relevant 2008 MPR ($/MWh)

WM Energy Solutions, Inc (Simi Valley)

Biomass (landfill gas)

10

2.49-5

11-22

2009

Simi Valley, CA

100.43

WM Energy Solutions Inc. (El Sobrante)

Biomass (landfill gas)

10

3.77-5

17-22

2009

Simi Valley, CA

100.43

Sustainable Energy Capital Partners, LLC

Solar Photovoltaic (PV)

20

20

56

2010

29 Palms, CA

113.90

TA - High Desert, LLC

Solar PV

20

20

42

2011

Lancaster, CA

117.30

RE Rio Grande, LLC

Solar PV

20

5

11

2012

Mojave, CA

121.26

RE Victor Phelan Solar One, LLC

Solar PV

20

20

49

2013

Adelanto, CA

125.27

RE Rosamond Two LLC

Solar PV

20

20

47

2013

Rosamond, CA

125.27

Boron Solar, LLC

Solar PV

20

15

30

2014

San Bernardino County, CA

128.97

North Edwards Solar, LLC

Solar PV

20

20

39

2014

San Bernardino County, CA

128.97

LSR Kramer South, LLC

Solar PV

20

20

40

2014

San Bernardino County, CA

128.97

Clear Vista Ranch, LLC

Wind

20

20

55

2011

Tehachapi, CA

117.30

Sand Canyon of Tehachapi LLC

Wind

20

20

55

2011

Tehachapi, CA

117.30

SCE initiated the RSC Program for renewable energy projects under 20 megawatts (MW) to provide a streamlined procurement process for smaller RPS-eligible projects. The RSC Program is a bilateral standard contracting program and will encourage contracts with small renewable generators by reducing barriers smaller projects may face when participating in the annual RPS solicitations. Projects with smaller capacities face difficulties competing in renewable solicitations with larger projects because of economies of scale and the cost of submitting bids and negotiating contracts. Each contract executed as part of its 2009 RSC Program is priced at the applicable 2008 Market Price Referent (MPR).

Deliveries from the PPAs are reasonably priced and fully recoverable in rates over the life of the contracts, subject to Commission review of SCE's administration of the contracts.

AL 2457-E and AL 2457-E-A are approved without modification.

Top Of Page