PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

ENERGY DIVISION RESOLUTION E-4513

August 2, 2012

RESOLUTION

Resolution E-4513. Southern California Edison Company requests approval of deviations in (1) its CREST Excess Sales Agreement (Form 14-785) for the United States Forest Service and (2) Interconnection Agreements (Forms 14-773 and 14-744) for Federal Agencies.

PROPOSED OUTCOME: This Resolution approves one-time modifications to Southern California Edison's CREST Excess Sales Agreement for the United States Forest Service and changes to Interconnection Agreements for Federal Agencies.

ESTIMATED COST: There are no expected costs associated with these modifications.

By Advice Letter 2716-E filed on April 13, 2012.

__________________________________________________________

SUMMARY

Southern California Edison Company's request for a one-time modification to its California Renewable Energy Small Tariff (CREST) Excess Sales Agreement (Form 14-785) for the United States Forest Service and for modifications to two interconnection agreements for Federal Agencies is approved.

Southern California Edison Company (SCE) is requesting approval of a one-time modification of its CREST power purchase agreement (PPA) for the U.S. Forest Service to interconnect a 300 kW solar photovoltaic (PV) system. SCE is also requesting modifications to two interconnection agreements-its Generating Facility Interconnection Agreement (GFIA) and its Customer Generation Agreement (CGA)-as offered to federal agencies.

The Commission approves both of these requested modifications on the basis of SCE's authority to deviate from its standard tariffs when providing service to federal agencies combined with the reasonableness of these deviations to ratepayers.