VIII. Allocation of Aggregate DWR Revenue Requirement Among the Utility Service Areas

1. Overview

2. Parties Supporting the Pro Rata Allocation Approach

3. Parties Supporting Geographically Differentiated Cost Allocations

4. ORA's Proposal

1. Statutory Basis for Allocation Methodology

2. Cost-Based Principles as a Basis for DWR Allocation Methodology

3. Allocation of Administrative and Financing Costs

4. Allocation of Power Procurement Commodity Costs

c. Distinctions in the Allocation of Fixed Price Versus Short Term Purchases

20 Kuga Direct Testimony (Ex 163) p. 1-3, quoting DWR memorandum to CPUC dated August 9, 2001. 21 In a memorandum from Peter Garris, DWR's Acting Deputy Director, to Commissioner Geoffrey Brown, dated November 28, 2001, DWR committed to providing the hourly cost information to the Commission on a timely basis. 22 See Ex. 163, p. 1-3; quoting DWR memorandum to the CPUC, August 8, 2001; Response to Comments on DWR Revenue Requirements, P. 3. 23 See 43 RT 6371-6372/Marcus. 24 See Ex. 163, pp. 1-2; footnote 2. 25 Ex. 159, Barkovich Testimony; pg. 8. 26 See, 41 RT 6126, lines 2-9 (and earlier comments on 6125.)

27 See, Exh. 157, 41 RT 6105, lines 5-15.

28 See excerpt from DWR's response to SCE's Data Request SCE-01, as cited in Exhs. 155 and 157.) 29 SCE, Stern, 39 RT 5902. 30 See DWR's Response to PG&E Data Request 34, as referenced in Ex. 163, footnote 2. 31 See DWR's Response to Data Requests dated August 1, 2001, as cited on page 10 of CLECA Ex. 159. 32 See Ex. 159 (Barkovich) pg. 4 footnote. 33 See Ex. 160, Weil Testimony, page 4. 34 Ex. 157, p. 4. 35 D.01-05-064, mimeo, pg. 18 36 See Ex 163, p. 2-3. 37 See Exhibit 151-A, Stern; the exhibit is confidential, but the cited fact is not. (See Stern, 40 RT 5966:7-10.) 38 SDG&E, Croyle, Tr. Vol. 40, p. 6003. 39 40 RT 6070, SDG&E/Croyle