Industry Rule 5. Tier Classifications for Advice Letters

A Utility submitting an advice letter shall designate the appropriate tier, based on the content of the advice letter. A Tier 1 or Tier 2 advice letter is subject to disposition under General Rule 7.6.1; a Tier 3 advice letter is subject to disposition under General Rule 7.6.2.

5.1 Matters Appropriate to Tier 1 (Effective Pending Disposition)

A matter appropriate to Tier 1 may be designated by a Utility in its advice letter as effective pending disposition. (For advice letters pursuant to General Rule 8.2.3, see Industry Rule 5.3.) Matters appropriate to Tier 1 are:

5.2 Matters Appropriate to Tier 2 (Effective After Staff Approval)

Matters appropriate to Tier 2 are:

5.3 Matters Appropriate to Tier 3 (Effective After Commission Approval)

An advice letter submitted under (8) of this Industry Rule may be designated by the Utility as effective pending disposition; all other matters appropriate to Tier 3 may become effective only after Commission approval. Matters appropriate to Tier 3 are: