4. Proposed SGIP Modifications

4.1. Statement of Purpose and Program Principles

Staff proposes a Statement of Purpose for the SGIP program to assist the Commission and the parties with the program implementation. The Statement of Purpose proposes that the SGIP should contribute to:

In addition to the Statement of Purpose, Staff proposes the following eight guiding principles to help with evaluating new technologies and informing program design modifications:

1. The SGIP should only support DER technologies that are cost-effective, or represent the potential to achieve cost-effectiveness in the near future.

2. The SGIP should only support technologies that produce fewer GHG emissions than they avoid from the grid.

3. The SGIP incentives should provide sufficient payment to stimulate DER technology deployment without overpaying. The SGIP incentives should not be provided to technologies that do not need them to earn a reasonable return on investment.

4. The SGIP should support behind the meter "self-generation" DER technologies, which serve the primary purpose of offsetting some or all of a host-customer's on-site demand.

5. The SGIP should only support commercially available technologies.

6. The SGIP should target best of class DER by paying for performance.

7. The SGIP incentives should focus on projects that efficiently utilize the existing transmission and distribution system.

8. The SGIP should complement the structure of and be coordinated with existing ratepayer supported programs, especially the California Solar Initiative (CSI), which is aimed at transforming the market for renewable distributed generation by driving down prices and increasing performance of DER.

Parties generally support the proposed statement of purpose and the guiding principles, but several parties recommend including peak load reduction as one of the SGIP's guiding principles. These parties contend that peak load reduction was the original primary purpose of the program. They argue that "SB 412 did not reverse, or eliminate the importance of emphasis on peak load reduction that still remains in [Public Utilities Code Section] 379.6...."6

Discussion:

Clear program purpose and principles are essential to the successful implementation of any program. We agree that the proposed Statement of Purpose captures the key objectives of the SGIP and will help guide the PAs, the SGIP participants and the Commission staff through future program implementation process. Accordingly, we adopt Staff's proposed Statement of Purpose.

We agree with PG&E that given the limited budget and timeline required by SB 412, the Commission should strive to keep the SGIP program expansion as simple and straight forward as possible. Given that the proposed changes to the SGIP are to fulfill the statutory requirements of SB 412, and since SB 412 specifically requires that eligibility for receiving the SGIP incentives shall be based on GHG emissions reductions, requiring that SGIP systems funded under SGIP achieve GHG reductions emissions should be a priority. Accordingly, we adopt guiding principle 2, which requires that technologies must show GHG reductions. However, we agree that this requirement should be an additional guiding principle to the peak load management goals of the SGIP. As parties correctly point out, peak load reduction has been the original primary purpose of the program. We believe it should remain important in the SGIP and should be included in the list of the SGIP guiding principles. Accordingly, we add the following as a new guiding principle:

Encourage the deployment of DER in California to reduce the peak electric demand.

In addition, given that many of the initiatives supporting DG in California are fundamentally market transformation programs, we believe that market transformation should be added as a guiding principle of the SGIP. Accordingly, we add market transformation as a new guiding Principle .

With respect to the other proposed guiding principles, we adopt guiding principles 4 through 8 because we find that they are beneficial to California and consistent with stated policies towards DG.

We are, however, concerned that guiding principle 1 and 3 would impose unnecessary requirements that might result in slowing down development of DER in California. That outcome would not serve the public interest. We therefore, do not adopt guiding principles 1 and 3. A more detailed discussion of why we do not adopt guiding principles 1 and 3 is presented under the "technology eligibility test" section below.

4.2. SGIP Eligibility Requirements

4.2.1. Technology Eligibility Test

Originally, Staff recommended the Commission adopt three screens for SGIP eligibility:

1. GHG reductions: A product or a technology must produce fewer GHG emissions than it avoids from the grid;

2. Cost-effectiveness: A technology must be cost-effective or represent the potential to be cost-effective in the near future; and

3. Need for financial incentives: the SGIP incentives should provide sufficient payment to stimulate DER technology deployment without overpaying, and the SGIP incentives should not be provided to technologies that do not need them to earn a reasonable return on investment of 15%.

In the months following the issuance of the staff proposal, staff worked with the CARB to ensure that CARB concurs with staff analysis.

After reviewing the results of the Cost-Effectiveness Report, Staff altered its recommendation and proposed that the Commission only use cost-effectiveness and GHG emission reductions screens in determining the eligibility for incentives. The need for the financial incentives screen would be used only as an aid in setting incentive levels.

Staff also slightly modified the cost-effectiveness approach. The SGIP Cost-Effectiveness Report examined both current and future cost-effectiveness from the societal and participant perspective. Staff now recommends that only technologies which show cost-effectiveness on a total resource cost (TRC) basis in 2010 should be funded. Staff argues the future cost-effectiveness results are considerably more uncertain due to the projections that rely on assumed cost-reduction curves which may change due to external factors or unforeseen events. Therefore, to maximize the societal benefit of ratepayer funds, Staff recommends technologies which show a TRC value of >1.0 in the Statewide Average 2010 Commercial Results will be deemed "cost-effective" and pass the TRC screen.7 A technology must pass both the GHG screen and the TRC screen to be recommended for inclusion in the SGIP program.

Discussion:

Achieving GHG reductions through SGIP projects is a requirement, as stated in Public Utilities Code Section 379.6 (a) (2):

Eligibility for incentives under the [SGIP] program shall be limited to distributed energy resources that the commission, in consultation with the State Air Resources Board, determines will achieve reductions of greenhouse gas emissions pursuant to the California Global Warming Solutions Act of 2006 (Division 25.5 (commencing with Section 38500) of the Health and Safety Code).

As stated above, SB 412 authorizes the Commission to determine eligibility for the SGIP based on achieving GHG emissions reductions. Thus, it is appropriate to make the GHG emissions reduction requirement the primary screen for establishing technology eligibility for the SGIP. We do not believe it is necessary to impose the additional requirements that technologies pass the cost-effectiveness test or pass the need for financial incentives test as prerequisites to receiving SGIP incentives when SB 412 does not require such requirements. Although SB 412 provides that the Commission may consider other public policy interests in determining program eligibility, these suggested requirements do not contribute to the development of additional alternative energy technologies. In fact, they could slow investment in the SGIP and hamper market transformation for technologies that could contribute to reducing grid emissions.

The requirement that a technology passes the need for financial incentives test for SGIP eligibility can be complex and administratively difficult to implement, as financial performance of systems is tied to physical characteristics of the site and tax status of the customer. In addition, in some cases this requirement could increase the costs for customers to participate in the program, therefore discourage customer participation. As PG&E states, this would be counter to our stated purpose of facilitating development of DER.

The requirement that a technology passes the cost-effectiveness test could also be difficult to implement because of inadequate cost data to establish a reliable and accurate cost-effectiveness model. Currently, there are limited cost data available for most DER technologies. Furthermore, some input information is proprietary and may be difficult to obtain reliably. This is especially true of forecasted price information, which either does not exist at all or can only be derived through assumption-driven modeling. In addition, as stated by the parties, there are too many variables and assumptions that could lead to inconsistent results in calculating the cost-effectiveness of various technologies. For example, technology costs for DERs are frequently site-specific and vary significantly with capacity. Given all these uncertainties about the DER cost data, we find that a cost-effectiveness screen could not yield reliable results.

Furthermore, one of the purposes of the SGIP is to contribute to market transformation and facilitate DER development. Precluding technologies that are likely to have an impact on the GHG reduction emissions in California from participating in the program because they cannot meet the cost-effectiveness or the need for incentive tests would be contrary to the intent of SGIP and the state's goal of GHG reductions. On the other hand, eliminating the cost-effectiveness and the need for incentive tests would encourage customer participation and result in the development of additional projects. Furthermore, additional support from the SGIP incentives could help technologies achieve future cost-effectiveness. To that end, it is appropriate that SGIP provide support to technologies that are GHG reducing and may potentially be cost-effective in the future.

We now address Staff's proposal on how to use the GHG reduction screen and whether the GHG screen should be on a project-by-project or at the technology level.

4.2.1.1. Avoided GHG Emissions from the Grid

Staff Proposal, Part I proposes that a DER be considered to reduce GHG if the resource's avoided emissions is greater than the emissions the technology would produce. In addition, a given DER must show unequivocal GHG reductions in year one and continued performance without degradation above 1%/year. A DER which meets this standard will be deemed "GHG reducing".

While parties generally support this concept, some are opposed to the use of Staff's avoided GHG emission factor of 349 Kg CO2e/Megawatt-hours (MWh) as a baseline. These parties argue that the proposed GHG factor is too aggressive and would result in the exclusion of many technologies that meet the CEC's required efficiency for GHG reducing technologies. They suggest the use of the CARB factor of 437 Kg CO2e/MWh, which is the factor CARB developed to estimate the GHG reductions achieved by various renewable energy and energy efficiency measures adopted as part of the AB 32 Scoping Plan. Staff's proposed number is CARB's factor adjusted by 20% to account for renewable resources as required under the Renewables Portfolio Standard (RPS) program.8 California Clean DG coalition (CCDC) contends Staff's number is erroneous because it ignores several factors including the fact that some renewables were already accounted for in CARB's factor. CCDC also argues that DG could displace fossil fuel generation with higher GHG emissions or displace only some renewables. In CCDC's view, these factors could affect the Staff's proposed GHG factor.

Although adopting the adjustments to CARB's factor may have several shortcomings, we believe the adjusted factor represents a reasonable proxy for calculating the avoided GHG emissions at this time and adopt it here.

First, we believe that the GHG emissions factor should reflect the fact that DG displaces a mix of purchases including renewable resources as required by the RPS statute. CARB's factor is simply the weighted emission rate of all in-state gas-fired generation from 2002 through 2004.

Second, CARB's factor was adjusted by 20% while the State has adopted a 33% RPS mandate. It is likely that accounting for the 33% goal will require even further reduction to Staff's estimate.

Third, because the CARB Scoping Plan emission factor value is based on the emission rate of gas-fired power plants from 2002 to 2004, it does not reflect the lower emission rate of newer gas-fired units that SGIP projects may avoid going forward. Given these factors, we believe Staff's proposal to adjust CARB's factor by only 20% is reasonable.

We also agree that because technology performance degrades over time, in order to be deemed "GHG reducing", a given DER technology must show unequivocal GHG reductions in year one and continued performance without degradation above 1%/year. If SGIP projects are not held to this baseline in the first year, it is unlikely that they will continue to contribute toward the clean generation requirements of SB 412.

We also believe that to encourage long term investment in DER, the GHG screen should be applied on a technology level instead of project-by -project basis whenever possible. Having clear policies regarding which technologies are considered GHG reducing by the State and thus eligible for SGIP is essential in the development of distributed energy resources. Applying the GHG screen on a technology basis will provide a clear signal to market participants and developers in making investment decisions. However, because the GHG performance of fossil-fired CHP projects depends on site-specific factors, eligibility for these projects must be assessed on a project-by-project basis. The PAs shall propose in an advice letter, methods to determine the amount of waste heat capture for each project necessary to qualify the project as GHG reducing.

4.2.2. Eligible Technologies

Staff applied the GHG reductions and cost-effectiveness screens identified above to determine eligibility. A technology that passed both the GHG screen and the TRC screen was recommended as an eligible technology for inclusion in the SGIP. These technologies include wind, fuel cell CHPs, gas turbines CHPs greater than 3.5 MW, microturbine and IC engine CHPs with onsite biogas, organic Rankine cycle and pressure reduction turbines.

Table 2. Proposed SGIP Technologies

         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         
         

Because we reject Staff's recommendation to use a cost-effectiveness eligibility screen, we focus only on the GHG screen. Applying this screen as discussed above, we find wind, pressure reduction turbines, bottoming-cycle CHP, and projects using the RPS-required minimum of 75 percent biogas to be categorically eligible for SGIP.

All fossil-fuel consuming CHP technologies are conditionally eligible but must be evaluated on a project-specific basis to assure that they are GHG reducing. Electric-only technologies, such as electric-only fuel cells, seeking SGIP incentives for projects consuming fossil-based natural gas must receive certification from CARB that they achieve an emission rate below 379 kgCO2/MWh under realistic field conditions in the first five years of the operation. In cases where a DER changes fuel, the corresponding affect on emissions must be considered. Thus, if a generator uses renewable fuel but later switches to natural gas, that project's eligibility for SGIP could be affected unless the customer can demonstrate that the efficiency was high enough to demonstrate GHG reductions operating on natural gas.

We will require the SGIP PAs to propose modifications to the current waste heat emissions worksheet as necessary to reasonably ensure that an SGIP funded non-renewable CHP project will reduce GHG emissions compared to the adopted grid emission factor and the heating (or cooling) technology the SGIP project is displacing. The PAs shall work closely with parties to develop an assessment tool that is rigorous and transparent without being onerously complicated and submit an advice letter for Commission approval within 30 days of the effective date of this decision.

In addition to the above technologies, staff also considered AES technologies. Staff recommends AES coupled with intermittent distributed generation, which is currently eligible for the SGIP, continue to be included in the SGIP. Staff, however, does not support including stand-alone AES in the SGIP, because it did not show positive TRC results. The California Energy Storage Allinace (CESA) and Ice Energy argue that stand-alone AES should be eligible for SGIP incentives. The Division of Ratepayer Advocates (DRA) is against allowing AES in the SGIP. DRA argues that through the Commission's Demand Response programs, utilities have pilot programs for permanent load shifting (PLS) resources that provide incentives for resources that permanently shift load from on-peak to off-peak times, including energy storage resources. Therefore, DRA opposes allowing stand-alone storage to participate in SGIP before the results of the utilities PLS pilot program are available. CESA, however, urges us not to wait for the PLS pilot program results, since any expansion of scope or pace of implementation for these pilot programs is entirely unknown at the present.

We will allow stand-alone AES in the SGIP. Both the demand response and the storage proceedings are in preliminary stages of developing a program for storage. Stand-alone AES may reduce peak demand and GHGs. As such, even though it is not generation, it fulfills two important SGIP goals. Therefore, it is appropriate that AES receives interim support while the Commission considers various proposals related to this technology in other proceedings. As CCSE states "the SGIP is an excellent platform for technologies such as AES, which is relatively new to the marketplace, has significant positive benefits, and needs market support to increase deployment and become more fully commercial."9

We note, however, that if a future Commission decision in another proceeding provides any incentives to energy storage, the incentives provided to AES under the SGIP should be removed so as to prevent multiple incentives encouraging the same resource.

Staff recommends that PRTs or "in-conduit hydro" and organic-rankine cycle plants be included in the SGIP. Staff notes that these technologies are consistent with the goals of the program.10

We agree that PRTs - which do not require fuel - do reduce GHGs and can also address peak load. Because they require little or no additional fuel for generation of kilowatt-hour (kWh), bottoming-cycle CHP units are also considered renewable for purposes of determining the appropriate SGIP incentive levels. Including PRT and bottoming-cycle technologies in the SGIP will help promote these technologies as viable options for clean DG and achieve the market transformation goal articulated above. Because PRTs are likely to be limited by site-specific characteristics more than financial hurdles, their inclusion in the SGIP should enable further deployment at sites well suited for PRT.

Fuel cells are another emerging technology which show potential for significant cost reductions in the future. The Cost-Effectiveness Report found that of all technologies, residential fuel cells have the highest projected cost reductions between now and 2020.11 Because the SGIP provides support for commercially available yet emerging technologies, the Commission should continue to offer SGIP incentives to fuel cell applications.

Staff proposes that we allow OSB in the SGIP but raise the requirement for percentage of renewable fuel consumed from 75% for only the first five years of operation to 100% for the life of the project. Staff also recommends that we exclude DBGs from the SGIP. Staff is concerned about the potential for gaming associated with fuel use for these projects and the administrative challenges associated with verifying their fuel usage. Staff suggests that if we were to continue to allow DBG to qualify for incentives, we address issues related to the quantity, the timeline and verification of delivery of the renewable fuel. In particular, Staff recommends that DBG projects that have received incentive reservations but have not yet completed their projects be required to demonstrate a 10 year contract for 100% of fuel from biomass. In addition, Staff suggests that PAs audit these projects in order to enable them to litigate if these projects fail to prove continued DBG fuel purchase.

Given the concerns raised regarding the verifiability of out-of-state directed biogas, we will exclude it from SGIP eligibility. However, using renewable biogas and developing California's biogas industry remain important objectives as California transitions to a low-carbon future. For these reasons, we will retain a separate incentive for biogas utilization for SGIP projects that use biogas from in-state sources. This eligibility applies to both on-site biogas and directed biogas produced within California.

Many parties voice concerns about changing rules for DBG projects with existing reservations. We agree that projects that are already receiving SGIP incentives or have reservation requests underway should not be subject to new changes since these projects entered into contracts under the existing rules.12 Accordingly, the changes we adopt here will only apply to new projects with reservation requests as of the effective date of this decision.

4.2.3. System Size

The SGIP currently has a minimum size requirement of 30 kilowatt (kW) for wind turbines and renewable fuel cells. There is no minimum size for non-renewable fuel cell projects. In addition, all eligible projects are capped at a maximum size of 5 Megawatt (MW) and the program requires that projects be sized to meet onsite load.

Staff recommends that the minimum size requirement for wind and renewable fuel cells remain in place only as long as the Emerging Renewables Program (ERP) continues to provide incentives for these technologies. If the ERP program is discontinued or interrupted at any time, Staff recommends that wind and renewable- fueled fuel cells tecs under 30 kW should automatically receive SGIP incentives without additional Commission action. According to Staff, such incentives would be paid in exchange for, and not in addition to, ERP incentives. For all other technologies, Staff recommends that there be no minimum size requirement. Staff also recommends eliminating the maximum size restriction of 5 MW for all technologies participating in SGIP. Staff does not propose any changes to the program requirement that projects be sized to meet onsite load.

Discussion:

The 30 KW minimum size requirement was intended to ensure that there is minimal overlap between the SGIP and the CEC's ERP, which offers incentives for projects with the same technologies as the SGIP that are sized at less than 30kW. We agree that as long as ERP exists the minimum requirement for SGIP projects is appropriate to avoid any overlap. To the extent ERP program is interrupted or eliminated, we agree all wind and renewable fuel cells should automatically receive the SGIP incentives.

For other technologies, removing the minimum size requirement would ensure that customers with smaller load such as residential and small commercial customers also have access to incentives. This requirement would be consistent with SB 412, which requires the Commission to ensure that incentives under this program be available to all customers. We adopt it here.

Similarly, we eliminate the maximum size limit for SGIP systems. Eliminating the maximum size will be consistent with the requirement of SB 412 as it will open up the program to large energy users and as indicated by several parties, allow these customers to more effectively participate in SGIP. Additionally, removing the size cap will benefit the program by enabling systems greater than 5 MW, which may not be financially viable without the incentives available for the first 3 MW, to become eligible to participate in SGIP. Having large projects may also allow certain technologies to achieve wider adoption without any additional cost to the program. We believe the tiered incentive structure (see Section 4.4.4 below), which only provides incentives for the first 3 MW of a project's capacity, and the requirement that projects be sized to meet a customer's onsite-load, should provide sufficient limitations on the maximum size and cost of any single project, thereby obviating the need for the maximum size limitation.

4.3. Incentive Design and Payment Structure

The Commission must decide three areas with respect to incentive issues. First, we must decide whether we should continue the practice of providing technology-differentiated incentives to SGIP projects. Next, we must determine the structure of the incentive, i.e., whether the incentive should be upfront or based on actual system performance. Finally, we must determine the level of incentives for each technology.

4.3.1. Technology- Based Incentive

Originally, Staff recommended that we continue the practice of providing technology-specific SGIP incentives. Staff noted that although the development of some technologies have progressed more slowly than others, almost all the recommended SGIP technologies have demonstrated that they can be successfully developed at the current technology-based incentive levels. Moreover, Staff was concerned that a single incentive structure for all SGIP technologies would not accurately reflect differences in capital and operating costs, as well as performance.

After the Cost-Effectiveness Report was published, Staff changed its recommendation from a technology-based incentive to an incentive structure that provides $1.50/watt incentive rate to all technologies with renewable fuel and $0.50/watt to all technologies with non-renewable fuel. Staff's recommendation is based on the observation that the incentives vary widely from project to project depending on project specific characteristics and utility territory. In Staff's view, setting a single statewide incentive level per technology that could adequately take into account all the variations across technologies and installations would be difficult.

UTC Power Corporation (UTC) objects to incentives that are not based on technology. UTC argues differences in technology performance require different incentive across technologies. UTC further argues incentive levels based on fuel sources, rather than technology attributes, would create a very uneven playing field in which mature technologies would receive preferential treatment over newer technologies that have significant potential for cost reduction on the horizon. UTC therefore recommends that the higher incentive be offered to "less mature technologies with higher cost pr kW today and strong prospect for future cost reduction."13 In response, California Large Energy Consumers Association (CLECA) maintains it is unclear how the Commission would predict which technologies have the greatest prospect for future cost reduction or how it would choose winners and losers.14

Discussion:

One of the adopted statements of purpose is market transformation for DERs. Three emerging technologies, storage, biogas and fuel cells, have the potential to play an important role in California's energy future. The SGIP may play a similar role for these technologies as the SGIP and the CSI have played in promoting the maturity of the solar industry in California. Therefore, we will adopt higher incentives for these emerging technologies than we do for more mature technologies. In addition, because the program is intended to encourage development of clean DG, it is appropriate to adopt an incentive structure that reflects the nature of the fuel used rather than just the technology. Based on historically offering higher incentives for renewable technologies than for fossil-burning technologies, we will generally provide higher incentives for zero-and low-GHG technologies than for technologies consuming fossil fuels.

Structure of Incentive Payments - A Hybrid Performance-Based Incentive (PBI)

Staff proposes a hybrid performance based incentive, where a portion of the overall payment is provided up-front and the remainder is provided over time based on customer's system performance. The up-front payment is capacity-based and would constitute 25% of the incentive. The rest of the payments will be based on measured energy deliveries and will vary depending on actual system output during the year, the base incentive amount and the capacity factor for each technology. Payments would be made according to the following:

Staff notes that payment based on energy deliveries may create an incentive for energy storage technologies to discharge more than is necessary or beneficial. Therefore, Staff recommends that energy storage technologies receive annual payments based on availability during peak hours. Energy storage technologies must meet all operational requirements discussed above and must be available during peak weekday hours (or semi-peak hours during winter months), at least 80% of the time during the year and 90% of the time during the summer peak period. Availability shall be defined as days in which the energy storage device discharged at least partially during peak hours.

Discussion:

Staff's recommendation to implement a PBI approach is based on the concern arising from prior measurement and evaluation studies, which indicate that many projects that received incentives in the past have not been able to maintain performance at the minimum program efficiency requirements over the life of the project. In several cases, the capacity factor and or generator availability were lower than expected. Several parties have also expressed the same concern and question the performance of some systems. They endorse a hybrid PBI to prevent program abuse. Some parties who are generally supportive of a hybrid structure advocate for a different initial incentive. Tecogen Inc. (Tecogen) suggests increasing the initial incentive to 50% or 60% to make a bigger impact on owners' decision making. Capstone Turbine Corporation (Capstone) suggests 50% upfront incentive with two additional payments of 25%. Bloom Energy Corporation (Bloom) recommends even a higher increase of 80%.

Some parties argue against performance based incentives. SDG&E and SoCalGas believe such a mechanism is too complicated and could frustrate progress of the current SGIP. Rather than a hybrid PBI, Foundation Windpower LLC. (Foundation) suggests an incentive recovery clause which would require that the incentive recipient return 100% of the SGIP funding in the event the project falls below 75% of its operational availability.

We believe it is time to replace the current upfront, capacity -based incentive mechanism with a hybrid PBI mechanism to ensure long-term performance of projects that receive SGIP incentives. One of the criticisms of the current structure is that it lacks any discipline over projects' long-term performance after the projects receive upfront SGIP incentives. Recent results of some SGIP studies indicate that several SGIP projects have not performed as expected or have failed to maintain performance at the minimum efficiency requirements during the project life after receiving upfront incentive. A project that receives SGIP incentives must perform at the expected levels of production and operate over the expected project lifetime in order for the ratepayers to realize the benefits of their investment. Therefore, a PBI should be part of the overall incentive structure to ensure continued project operation during the life of the project.

We disagree with SDG&E's and SoCalGas' contention that a PBI mechanism is complicated and cannot be implemented without significant costs is not valid. Our past experience with implementing a PBI mechanism in CSI has been successful. Given that the SGIP PBI mechanism introduces a similar concept with a much smaller scale, we expect the expertise and knowledge obtained from the CSI program will be useful and can be applied in implementing a successful PBI mechanism for the SGIP.

At the same time, we recognize that upfront incentives play an important role in the owners' decisions to invest in projects. An upfront incentive will encourage development of new projects by reducing owners' initial capital costs, which many identify as one of the barriers to deploying SGIP technologies. Customers will be more motivated to invest in SGIP projects when the program offers upfront incentives.15 Therefore, an upfront incentive should also be a part of the incentive structure. Given our findings that the incentive structure should contain a combination of upfront incentives and PBI, we adopt a hybrid incentive structure. We believe a hybrid structure will be most effective in encouraging investments in clean DER and protect ratepayer-supported funds against non-performing or under performing projects.

4.3.2. Structure of PBI Incentive Payments

We now address the structure of the upfront and the PBI incentives and the different proposals regarding what portion of the incentive should be upfront. Several parties urge us to adopt a larger upfront capacity-based incentive coupled with a shorter period for annual performance payments. They recommend an upfront capacity payment of 50% or more. Some also argue that the proposed five-year period for annual performance payment is too long and may add risk and uncertainty to the finance of a project. They propose a shorter period. We believe 25% upfront capacity payment may not be sufficient to assist many technologies to overcome the first cost hurdle.

We decline to adopt Bloom's request to pay a larger portion of the overall incentive upfront. This approach would reduce the amount of incentive that would be subject to performance verification over time, thereby increasing the risk to ratepayers of overpayment to a system that has received upfront incentives but does not perform as expected. We agree with PG&E that a large portion of the overall payment should be performance-based. Therefore, we adopt 50% as upfront incentives.

We also decline to adopt Bloom's other suggestion that technologies with less than 10 years of commercial deployment be exempt from PBI. We agree with The Utility Reform Network (TURN) that being a less mature technology does not justify a differential payment. Indeed, it is these unproven technologieswhich necessitate a performance-based structure. However, SB 412 allows for differential incentives based on environmental performance and many parties support higher payments for renewable projects due to their environmental benefits. Because renewable projects generally have higher upfront capital costs, we believe it is reasonable to increase the upfront incentive portion for these systems from 25% to 50%. However, DBGs do not incur the same higher upfront costs of other systems with renewable fuels, despite their renewable fuel status. These projects will not be eligible for the increased incentive. They will receive the 25% upfront incentive instead.

With respect to the performance-based portion of the incentive, we find that it is appropriate to modify the PBI approach and require that each project be paid based on the actual performance of the system in a given 12-month period. Under this approach, customers who may encounter slower than expected business in one year will not be penalized if they produce less in that year. They will still receive a portion of their incentives based on the actual production of their system for that year. Similarly, customers whose systems perform better than expected could receive all of their performance-based payments in less than five years. In order to limit the amount of time that Program administrators are obligated to continue administering the SGIP, the maximum amount of time allowed for earning the performance portion of the SGIP payment would be set at five years. This approach will provide some flexibility to allow recovery of the performance- based portion of the incentive while it will ensure that systems that receive payments perform as expected.

This approach will also allow system that operate at maximum efficiency, but lower than target capacity factor to receive SGIP incentives rather than no incentives. Otherwise, as CCDG explains, these systems may install heat dump capability to allow them to operate even when the site thermal loads are satisfied. We agree with CCDG that such a practice will result in outcomes that are contrary to state policy, and the goals of SB 412. To prevent such a practice, we recommend a minimum percentage of waste heat capture based on technology.

4.3.3. Incentive Levels

Staff recommends incentives of $1.25/watt for renewable technologies and $0.50/watt for non-renewable technologies, including AES systems paired with eligible SGIP technologies. The following table indicates the proposed incentive rates for eligible SGIP technologies:

Table 3. Proposed SGIP Incentive Levels by Technology and Fuel Type

Technology

Fuel16

Total Resource Cost (TRC) Value17

Incentive ($/W)

Renewable Fuel (Plus Waste Heat Capture)

Wind

n/a

1.40

$1.25

Organic Rankine Cycle

n/a

1.54

$1.25

Pressure Reduction Turbine

n/a

n/a

$1.25

Fuel Cell - CHP

OSB

1.02

$1.25

Gas Turbine (>3.5MW) - CHP

OSB

1.18

$1.25

Microturbine - CHP

OSB

1.25

$1.25

IC Engine (0.5 MW) - CHP

OSB

1.51

$1.25

IC Engine (1.5 MW) - CHP

OSB

1.83

$1.25

Non-Renewable Fuel

Fuel Cell - CHP

NG

1.05

$0.50

Gas Turbine (>3.5MW) - CHP

NG

1.11

$0.50

Storage (paired with eligible DG technologies)

Advanced Energy Storage18

n/a

n/a

$0.50

Discussion:

Staff recommends incentives of $1.25/watt for renewable technologies and $0.50/watt for non-renewable technologies, including AES systems paired with eligible SGIP technologies. Staff acknowledges that these incentive levels are lower than the incentives historically offered by SGIP but given the limited budget, Staff believes that lowering the incentives would allow the program to support more capacity.

While, as discussed above, we declined to adopt the financial need and cost-effectiveness screens recommended by staff in the Staff Proposal, Part I, we agree with the general principle that the incentives should be high enough to stimulate the adoption of self-generation technologies without providing incentives far in excess of what is needed. With this idea in mind, we consider the appropriate incentives for those technologies we have identified as emerging technologies.

Since 2007 the incentive level for fuel cells has been $2.50 per watt. From 2007 to 2009, relatively few projects applied for SGIP funds. This is indicative that $2.50 per watt was insufficient to stimulate much demand for fuel cells. However, completed or currently active applications for fuel cell projects increased from 13 MW of capacity in 2009 to nearly 72 MW of capacity in 2010. Much of this investment was driven by the combination of the fuel cell and biogas incentives, but over one-third of the 2010 reservation requests were for projects using standard natural gas. Thus, it appears that fuel cell costs have fallen to a level at which fuel cells are economically viable in many applications with the SGIP incentives currently in effect.

In light of the rapid increase in fuel cell project applications in 2010, we will adopt a lower incentive than the $2.50 per watt currently in effect. Regarding the incentives for biogas, some parties opposed the reduction suggested by staff. The difference in incentive levels between projects using biogas and natural gas suggested by staff yields an implicit incentive for biogas of $0.75 per watt. While the number of SGIP applications seeking incentives for biogas increased sharply in 2010 (46 MW compared to 10 MW in 2009), the vast majority of the requested incentives were for directed biogas contracts of five years. A much smaller amount of capacity was reserved for on-site biogas projects. Because we adopt staff's recommendation to increase the minimum contract length for directed biogas to 10 years, a sizeable reduction in the incentive level now is likely to prove insufficient to promote further biogas development. SoCalGas encouraged the retention of the current incentive level for biogas, and we agree that with the more stringent requirements in place for directed biogas it would be prudent to maintain the incentive at $2.00 per watt.

Storage technologies have seen relatively little activity in the SGIP. In 2010, AES applications accounted for only eight MWs, or roughly eight percent of the total capacity reserved in 2010. As CESA noted, staff has previously determined that $2.00 per watt is necessary for AES to be financially attractive. The low participation of AES in the SGIP to date suggests that it would be premature to reduce the incentive level for these technologies at this time. Thus, we will maintain the current incentive level of $2.00 per watt for AES.

Aside from the emerging technologies for which we wish to encourage market transformation, we agree with the Staff that the SGIP should strive to incentivize the maximum amount of distributed generation possible at the lowest cost to ratepayers. Accordingly, for technologies other than the emerging technologies, it is reasonable to set the minimum incentive level necessary and allow the market to determine which technologies are installed based on their costs and the benefits they provide to participants. However, due to the state's strong interest in reducing GHGs, as well as local air pollutants, and promoting renewable energy, the SGIP should offer higher incentive levels for renewable and waste heat recovery technologies.

Pressure reduction turbines and bottoming-cycle CHP units have not been eligible for SGIP in the past. As a result, we do not have actual cost data available to inform our decision regarding incentives for these technologies. Because of this lack of program data, we will base our renewable and waste heat capture incentives on our experience with wind turbines.

Like fuel cells, wind turbines also saw a large increase in SGIP activity in 2010, with over 23 MW requesting reservations in 2010 compared to 1.6 MW in 2009. This uptick in wind applications in 2010 demonstrates that $1.50 per watt has proven sufficient to attract investment. We note that, based on reported total installed costs in SGIP, $1.50 per watt covers over one-third of installed costs in most cases and as much as half of installed costs for a couple of projects. Combined with the 30 percent ITC for which wind turbines are also eligible, the $1.50 per watt incentive may result in ratepayers overpaying to induce these investments. Therefore, we will adopt the reduced incentive for wind turbines of $1.25 per watt as recommended in the Staff Proposal, Part 2, and we will use this value for pressure reduction turbines and bottoming-cycle CHP technologies.

Conventional fuel-based CHP technologies have not been eligible for SGIP funds since 2006. At the time the program was revised to restrict eligibility to wind and fuel cells, the incentive levels for these technologies was $0.80 per watt for turbines/microturbines and $0.60 per watt for internal combustion engines. These incentive levels appear to have been adequate to incentivize several MW of installations of these technologies, particularly internal combustion engines. Moreover, the SGIP Cost-Effectiveness report shows the cost of these technologies falling generally in the $2 to $3 per watt range. Given the relatively low cost of these technologies and the 10 percent ITC available to them, we will adopt the staff's recommended incentive level of $0.50 per watt.

Table 4 - SGIP Incentive Levels Category

Technology Type

Incentive ($/W)

Renewable and Waste Heat Capture

Wind Turbine

$1.25

Bottoming-Cycle CHP

$1.25

Pressure Reduction Turbine

$1.25

Conventional Fuel-Based CHP

Internal Combustion Engine - CHP

$0.50

Microturbine - CHP

$0.50

Gas Turbine - CHP

$0.50

Emerging technologies

Advanced Energy Storage19

$2.00

Biogas

$2.00

Fuel Cell - CHP or Electric Only

$2.25

Staff recommends that the Commission maintain the current tiered incentive rates:

0-1 MW = 100 %

1-2 MW = 50 %

2-3 MW = 25 %

Discussion:

Except for Foundation Windpower, who advocates that we apply 100% to the first 1.5 megawatts of capacity, most parties support maintaining the tiered incentive rates. (FCE, ...) . It appears that Foundation's request for a higher percentage for large scale distributed wind generation is due to factors unique to a specific product. We see no reason to complicate the program by making a separate provision for a specific product. We reject Foundation's request.

The California Solar initiative (CSI) program has a declining incentive structure that is based on decreasing the incentives in steps as more solar projects are developed. Staff supports applying a declining incentive structure to the SGIP, but does not recommend that incentives for the SGIP decline in the same manner as CSI. Staff notes that a declining incentive structure like the one adopted for CSI would be difficult to implement for the range of SGIP technologies. Instead, staff recommends a 10% decline in the incentives for SGIP technologies, starting on January 1, 2013.

SoCal Gas supports a gradual "ramp down" of incentives over a period of years, using the CSI as a model. Fuel Cell Energy (FCE) supports this approach, with the caveat that the "step down" structure should be designed (as it was in the case of the CSI on a technology-specific assessment of current market maturity and the expected trajectory for market growth.20

Bloom recommends an annual 15 percent reduction in the incentive level, effective immediately upon re-opening the program. Fuel Cell Energy also recommends a reduction in the incentive level, but a less aggressive reduction schedule of 10 percent every two years. Similarly, UTC suggests a fixed annual percentage reduction of 5 percent to 10 percent per year.21

Discussion:

In D.04-12-045, the Commission stated that "a declining incentive structure will gradually reduce the market's reliance on a subsidy." (D.04-12-045 at 12) The Staff analysis also shows the CSI, which includes a declining incentive structure, has been successful in promoting development of solar projects and the CSI continues to receive record numbers of applications each month. Although a declining incentive structure was ultimately not adopted, with the exception of solar photovoltaic in the CSI program, we affirm the principle that SGIP incentives should gradually decline rather than end abruptly in order to ensure that the technologies supported by SGIP transition toward a self-sustaining level of maturity that is no longer dependent on ratepayer subsidies.

Given the past performance of the CSI, and that a declining structure similar to the CSI "would promote consistent incentive design structure among the Commission's DG programs and would follow a successfully implemented model" 22, we believe a declining incentive structure for the SGIP will facilitate self-sufficiency and promote cost reductions in the market for the SGIP technologies.

Although UTC proposes a 5% and DRA proposes a decline every two years, we are not convinced that these are better approaches than the Staff proposal. However, rather than the more aggressive decrease suggested by parties, we will begin with a 10 percent reduction to $2.25 per watt effective immediately upon recommencement of the program. Accordingly, starting on January 1, 2012, incentives for SGIP technologies will decline by 10% annually.

4.3.4. Calculation of SGIP Incentive

The SGIP Staff Proposal, Part I recommended a five year payment plan based on expected performance, with penalties for not achieving the planned generation. Each incentive level would be based on capacity and then converted into a cents per kWh payment (paid over 5 years) based on the capacity factor of the technology. The SGIP Staff Proposal Part II recommends an "energy bank" performance based payment targeting a four year expected payback.

Under this arrangement, each project would have a performance expectation established during the incentive claim phase of the project review. Kilowatt hour payments would be structured so that under forecasted operating conditions, a project would receive the entire stream of performance payments in four years. The full potential total payment would be "banked" and each year's performance would be measured and payments made that draw down on the balance of the account.

Each project would be paid a performance payment once a year based on the kWh of production for that 12 month period. If a customer had a business slowdown in a given year they would receive an amount based on actual performance of their project. However, in future years, the customer could make up those kWh and be paid for them. Similarly, customers with systems which perform better than expected could receive all of their performance based payments in less than four years. In order to limit the amount of time that Program administrators are obligated to continue administering the SGIP, the maximum amount of time allowed for earning the performance portion of the SGIP payment would be set at five years.

For example, a wind turbine eligible for a $1 million dollar incentive could receive $500,000 upfront with the remaining $500,000 paid based on expected kWh generation over four years, calculated as follows:

Capacity * Capacity Factor * hours per year * degradation

Table 5. Example of Generation and PBI of 800 kW wind turbine at 30% CF

Year

Capacity (kW)

Capacity factor (%)

Hrs/yr

kWh

Total kWh

PBI

Total PBI

1

800

30

8760

2,102,400

2,102,400

$102,041

$102,041

2

800

30

8760

2,081,376

4,183,776

$101,020

$203,061

3

800

30

8760

2,060,352

6,244,128

$100,000

$303,061

4

800

30

8760

2,039,328

8,283,456

$98,980

$402,041

       

2,018,304

10,301,760

$97,959

$500,000

*Note that this assumes a 1%/yr degradation, and upfront payment of 50% of the total incentive amount.

In the above example, the expected cumulative kWh generation by year five is 10,301,760 kWh. This amount of energy is then correlated to the $500,000 PBI to yield a payment which would result in a four year PBI stream:

($500,000 performance payment)

10,301,760 kWh = 4.9 cents/kWh PBI

Because the wind turbine in Table A operated as expected, it received the final PBI payment at the end of year five. If the turbine were to operate better than expected, it would receive the same $500,000 payment, albeit in a shorter time frame. Similarly, if it generated fewer kWh than predicted by year five, it would not receive the total payment.

Table 6. Example of Generation and PBI of 800 kW wind turbine at declining CF

Year

Capacity (kW)

Capacity factor (%)

Hrs/yr

kWh

Total kWh

PBI

Total PBI

1

800

30

8760

2,102,400

2,102,400

$102,041

$102,041

2

800

30

8760

2,081,376

4,183,776

$101,020

$203,061

3

800

25

8760

1,716,960

5,900,736

$83,333

$286,395

4

800

25

8760

1,699,440

7,600,176

$82,483

$368,878

5

800

25

8760

1,681,920

9,282,096

$81,633

$450,510

*Note that this assumes 1%/yr degradation, and upfront payment of 50% of the total incentive amount.

In the example shown in Table B above, we see an example of a declining capacity factor beginning in year three. This results in fewer kWh generated, and a correspondingly lower PBI for that year. Instead of receiving the entire payment in year five, this generator doesn't receive it. Also, note that in either scenario, the maximum PBI payment is $500,000.

Staff recommends that SGIP performance based incentive payments differ by technology, but be structured as a payment for kWh generation. Staff notes that CHP would also be paid by kWh, with a minimum operating efficiency standard being checked annually to ensure that overall system efficiency is within 2% points of the value cited by the developer.

Combined heat power (CHP) applications, though they have not historically performed well, do present an opportunity to reduce electrical and thermal load. The higher value of kWh compared with Btus of natural gas motivates project developers to focus on the electrical component of CHP, whereas the emissions savings come primarily from the avoided thermal demand. To appropriately value these savings and avoid `heat dumping,' we adopt a two-pronged approach: pre-screening and on-going monitoring that serves as a conditional basis for any ongoing performance payments.

Pre-screening of CHP efficiency could be accomplished by an improved Waste Heat Utilization Worksheet,23 one of the documents used in the SGIP application process. Developers would be required to demonstrate the base thermal load of a site, along with forecasted diurnal fluctuations and future changes due to changing business conditions. Additionally, they would be required to show the coincidence of thermal and electric load. This demonstration of base thermal load, fluctuations, and coincidence of demand would help ensure that only facilities with an appropriate heat demand are incentivized. Staff notes that for participation in the CHP feed-in-tariff per AB 1613, customer sites must demonstrate their thermal load. This load is then used to determine the maximum eligible generator size, so that CHP facilities are sized to the thermal and not electric load.

Monitoring will also be necessary to ensure the on-going performance of applications approved under the pre-screen. Natural gas input will be monitored by the utility, and kWh output monitored for PBI payment. Waste heat monitors would be the only additional piece of equipment, and generally cost less than $20,000 - a small percentage of a typical SGIP project cost. Reviewing project efficiency will enable Program administrators to verify that a project is utilizing waste heat as predicted in the waste heat utilization worksheet.

We adopt staff's recommendation that the SGIP PAs shall file an Advice Letter with the details of the performance -based payment structure, including any variations by technology and updates to the Waste Heat Utilization Worksheet, within 30 days of the final decision. Once approved, the Program administrators would incorporate all of the details into the SGIP Program Handbook.

4.3.5. Incentive Allocation per Technology Supplier and Installation Contractor

Staff suggests the SGIP annual budget on a statewide basis be capped at 50% for a single technology supplier or installation contractor. Staff notes that this will serve to diversify the ratepayer portfolio of DER and reduce over-exposure to any one product or developer. It will also facilitate a more equitable distribution of SGIP funds.

In addition, Staff recommends that the SGIP not pay incentives that represent more than 30% of upfront project costs because many SGIP projects are eligible for an investment tax credit of up to 30% that could offset project cost. Moreover, Staff believes that SGIP participants should pay a larger share of the project cost than either the ratepayers' share or the federal taxpayers' share. Therefore, Staff recommends that SGIP participants pay for at least 40% of the project costs after properly accounting for project costs and tax benefits.

Although most parties support the general concept of limiting the availability of the SGIP budget for a single technology or installation contractor in order to make limited program funds available to more technologies and participants, they differ on whether the limit should be a fixed dollar amount or a percentage of the budget. They also have different proposals regarding what the limit should be.

SDG&E and SoCalGas contend that a 50% limit is too high to ensure a diversified portfolio. SoCalGas recommends we lower the cap to 25%, and SDG&E recommends a $15 million statewide cap for each technology. CESA also recommends a $25 million cap. CESA contends any form of percentage-based cap will be too difficult to administer. CCSE counters CESA's argument and states that SGIP database could simply be modified to track total incentives in a calendar year to a single technology supplier and/or installation contractor.

Several parties are opposed to the adoption of the above requirement. SCE contends the requirements to cap upfront incentives would necessitate establishing and tracking both a project cost cap and threshold, which in SCE's view could not be implemented without significant time and administrative cost to the PAs. PG&E, CCSE and SoCal Gas also believe a project cost cap could become administratively burdensome. PG&E also notes that many customers (government and non-profit) cannot take advantage of the tax relief that was considered when setting the 30% cap.

SCE maintains that the requirement to have participants pay 40% of the project cost is also problematic because it requires the PAs to obtain tax information from participants.

Parties also argue that some projects, including publicly-owned projects, are not eligible or able to use the tax credit. Therefore, they recommend that the 30% cap limit should not be applied to these projects.

Discussion:

We adopt the Staff proposal. The cap would ensure that SGIP recipients are financially committed to projects' success. We are not convinced by SCE's claim that these requirements would be overly burdensome or require a significant administrative cost. The relatively small size of the SGIP program would make it unlikely that significant time or investments would be needed to support the implementation of these requirements for SGIP applications. Moreover, as TURN points out, since the SGIP currently requires that incentives not exceed project costs, the PAs could apply the same process and documentation to measure and enforce the limit on incentives as a portion of project costs.

While we adopt Staff's proposal, we decline to adopt the 30% cap for projects that are ineligible for a tax credit. In other words, publicly-owned projects or other projects that are ineligible to receive federal tax credit should not be subject to the 30% cap requirement. In addition, we recognize that there is a potential for gaming, such as creating different governance structures to allow participants to achieve more funding than the capped amount. Therefore, we direct the PAs to file an advice letter within 30 days of the effective date of this decision proposing guidelines on how to implement this requirement in order to avoid such outcomes.

We also adopt staff's proposal of a 50% supplier concentration limit, but not the proposal that a given developer can only supply 50% of SGIP projects using different products. Parties have stressed the importance of having a mechanism that will indicate if there is an imbalance in the supplier concentration. A supplier limit will serve as a program safety measure and provide checks and balances necessary to ensure that one supplier does not receive a disproportionate share of the program fund. For this purpose, there is little, if any, difference in adopting a percentage-based versus a fixed amount cap. Either approach would work relatively the same in informing us if a high concentration of one supplier exists. Given the above, we believe a percentage-based cap is an appropriate mechanism to ensure diversity of the portfolio and will equitably distribute SGIP funds. We find that Staff's proposed 50% cap is reasonable.

4.3.6. Additional Performance Warranties

4.4. Budget Allocation

When the SGIP was fist established, there were three incentive levels for eligible technology categories (Level 1, Level 2, and Level 3). D.01-03-073 allocated a percentage of the SGIP budget to each category and established rules for transferring funds between the three categories. Later, when Level 1 technologies were removed from the SGIP because solar photovoltaic (PV) was moved to the CSI program, the list of eligible technologies was limited to Level 2 and Level 3. Level 2 includes renewable technologies (wind, and fuel cells using renewable fuel) and non-renewable technologies (fuel cells using natural gas). PAs are authorized to move funds from the non-renewable category to the renewable category as needed. However, in order to move funds from the renewable category to the non-renewable category, PAs must file an Advice Letter seeking authorization from the Commission.

Staff recommends keeping this practice, but suggests eliminating the "Level 2" and "Level 3" designations and use "renewable" and "non-renewable" categories instead. In addition, staff suggests energy storage coupled with a renewable DG technology on-site, such as solar, wind or biogas, be funded out of the renewable budget allocation and all other energy storage technologies be funded out of the nonrenewable budget allocation.

Discussion:

We agree with staff that the Level 2 and 3 designations are outdated and should be changed. The renewable and non-renewable designations more appropriately represent the range of SGIP technologies.

Staff requested comments on whether the "renewable" category should be further designated between generation technologies which cause emissions "at the source" and those which do not (i.e. renewable fuel cells vs. wind turbines) We do not believe this designation in necessary.

4.5. Other SGIP Program Modifications

4.5.1. Measurement and Evaluation (M&E)

The SGIP Staff Proposal identifies several reports and activities that have been in place since the inception of the SGIP and are currently part of the SGIP M&E process. Staff recommends several additional M&E guidance to streamline the M&E process after implementing SGIP program changes pursuant to SB 412. Most significantly, Staff recommends a specific budget for the SGIP M&E program.

Ice Energy supports Staff's recommendation to obtain accurate measurement and monitoring of the performance of SGIP facilities, but contends that thermal energy storage for air conditioning has unique characteristics that need to be taken into account with regard to measurement and metering. For these types of systems, Ice Energy alleges that the discharge energy is not most important factor to measuring their performance on the grid. Rather, it is the electrical energy that they displace - the kW and kWh of electric demand that is avoided during peak hours as a result of the discharge of the stored thermal energy - that is the appropriate quantity to measure and monitor. According to Ice Energy, this is well suited to the Staff Proposal's approach to robust metering, measurement, monitoring and reporting.

Discussion:

Obtaining accurate and current performance data is critical in establishing historical performance of SGIP funded projects, particularly in a PBI environment. It also enables the Commission to make informed decisions regarding design and administration of SGIP program rules in the future. We adopt Staff's proposal.

4.5.2. Metering Requirements

Staff proposes that we expand the metering and reporting requirements adopted in D.10-02-017 to all SGIP applications and require metering and monitoring equipment to be installed on SGIP facilities as a condition of receiving incentives. Specifically Staff recommends the following:

_ Install metering equipment capable of measuring and recording 15-minute interval data on generation output, and (where applicable), fuel input, heat output (for CHP) and storage system charging and discharging.

_ Provide data by the system owner or its designee to the PA, directly to Energy Division staff and/or to relevant M&E contractors on a quarterly basis for the first five years of operation.

_ The program administrators along with Energy Division staff shall hold a public workshop to establish specific protocols to govern the metering and data reporting requirements for SGIP systems. The program administrators shall submit metering and monitoring protocols through a Tier 2 AL that modifies the SGIP Program Handbook within 60 days of the adoption of a final decision.

_ For M&E purposes, the investor-owned utilities shall be required to provide interval data on total energy consumption for project sites (which is different than the system production data described above that must be provided by the system owner) to the PAs, Energy Division staff and relevant M&E contractors. This should be done for a period of five years.

CESA and CCSE argue that the Commission should consider waiving metering requirements for small projects (e.g. < 10kW) due to the increased transaction and overhead cost associated with the metering requirements. However, for small projects, CESA recommends we require sampling and audits to ensure compliance with performance as predicted.

Bloom supports monitoring system performance to ensure SGIP projects that receive incentives perform as required, but has several concerns regarding privacy of the data and the additional cost of metering requirements for customers. Bloom suggests if we mandate additional metering requirements on SGIP customers, we continue the existing practice of requiring the PAs to pay the cost of any additional metering requirements that is not normally required by the utilities, but required as a condition of receiving incentives. Bloom also cautions us about confidentiality and competitive information of data for SGIP facilities and recommends we consider what data needs to be collected, who the data will be released to and what purpose the data will fulfill. Bloom also argues requiring quarterly reporting will increase costs and administrative burdens and recommends we delay requiring such reporting until additional funding is available.

Discussion:

Currently, metering and monitoring equipment for M&E purposes are installed only on a sample of SGIP systems. Additionally, the cost of this monitoring is paid from the SGIP administration budget of the SGIP Program administrators.

We agree with the Staff proposal that accurate metering and monitoring data will be necessary to calculate and verify performance of the SGIP systems for the purposes of PBI payments. Furthermore, quarterly reporting will provide important information and feedback on program performance and will contribute to improving the M&E studies of the program as a whole. We see no reason to delay this requirement and adopt Staff's proposal. We do, however, note that additional information will be needed to establish all the necessary details of the metering and reporting requirements. Furthermore, while some level of consistency among projects may be desirable, smaller projects may not require the same level of metering and reporting as larger projects. CESA's and CCSE's recommendation to waive the metering requirement for smaller projects should be further discussed. Parties should discuss the specific protocols to govern the metering and data reporting for all SGIP systems in a workshop, including the appropriateness of any size-differentiated metering requirements and who should pay for the additional metering expenses.

4.5.3. Marketing and Outreach

Staff suggests we adopt a specific budget for M&O activities, focused on informing and educating customers about DER opportunities and addressing market barriers to DER adoption. Staff recommends that we allocate 3% of the budget for program administration for marketing and outreach purposes.

Staff also recommends a number of activities to enhance more uniform statewide outreach efforts and to better coordinate M&O activities with the CEC, and industry groups. In particular, staff proposes the SGIP Working Group create a committee dedicated to M&O activities for SGIP.

Discussion:

Currently, 10% of the SGIP budget for each PA is set aside for administration, which includes general administration, M&E, and M&O. Staff reports that despite the fact that there has been funding incorporated into the administration budget for M&E, Program administrators have spent very little on these activities. Additionally, these activities do not show a correlation with increased SGIP activity.

We believe a more active and coordinated approach to M&O is warranted. A set budget will allow the PAs to focus on outreach and education to broaden the M&O activities. We adopt staff proposal to allocate 3% of the budget for program administration for marketing and outreach purposes.

4.5.4. Export to the Grid

Staff recommends SGIP projects that qualify for the Assembly Bill (AB) 1613 feed-in-tariff should be allowed to sell up to 25% of their self-generated electricity to the interconnected utility. Staff believes allowing SGIP projects a limited amount of export is consistent with the SGIP intent while it would be complementary with an export tariff program.

Parties generally support the export idea, but differ on the export limitation amount. FCE asserts the 25% limit imposes new and unnecessary restrictions on projects that are currently eligible under AB 1613 to export to the grid. According to FCE, the AB 1613 program is only available to projects that are sized to meet onsite load. Thus, FCE argues there will

Foundation supports the policy of customers having some ability to export power to the grid and believes the current project sizing rule has been effective in precluding projects that are net energy exporters from full SGIP eligibility. As long as the current limit on the SGIP self-generation project sizing (200% of a customers' peak 12 month demand) is maintained, Foundation believes there is no need to apply a specific cap on the amount of exported power.

Sustainable Conservation (Sustainable) is also against the 25% limit. Sustainable alleges the amount of fuel a generator may be able to produce in the case of biogas digesters on farms and food processing facilities, generally exceeds the 25% limit. Thus, Sustainable contends a 25% limit may result in unused fuel for electricity. Debenham supports the 25% limit on the amount of export to the grid.

Sustainable Conservation argues that projects should be sized to meet available fuel source, not limited to on-site load. SCE opposes the adoption of this proposal and urges us to reject it. SCE contends SGIP eligibility should be limited to distributed generation technologies on the customer's side of the utility meter that provide electricity for a portion or all of that customer's electric load. CLECA states that allowing unlimited (aka limited only to fuel availability) access to SGIP funding for a project that will sell power to the utility under the FiT requires a more thorough analysis than can be undertaken here.

Discussion:

We adopt the Staff proposal to allow customers to export 25% of their output to the grid on an annual basis. Allowing SGIP facilities to export to the grid will facilitate optimal and efficient sizing of SGIP systems and as TURN states, will allow customers some flexibility "to account for resource variability in the case of wind projects and to account for demand fluctuations due to business downturn." 24 However, we agree with DRA and TURN that there should be a limit on the amount of export. As DRA states, the intent of SGIP is to facilitate self-generation. Allowing customers to export to the grid without any caps would not benefit ratepayers.25 TURN does not support a blanket 25% provision for all SGIP customers and argues that such an allowance for five years is unnecessary. TURN's proposal is to limit the exports to a maximum of 25% in any given year but no more than 10% in five years.26 DRA does not oppose the proposed 25% export allowance.

While allowing export to the grid would provide flexibility in the program and motivate customers to invest in SGIP systems, we do not want this provision to provide incentives for technologies to export all or most of their output to the grid. This would result in increased costs to ratepayers. A 25% cap would correct this problem by providing a reasonable export limit. Accordingly, we adopt a 25% export allowance. We see no reason to restrict this to only one year as TURN proposes. Such a restriction would be counter to the optimal system sizing principle that we want to promote through this provision.

4.5.5. Energy Efficiency Requirements

Staff recommends customers receiving SGIP incentives obtain energy efficiency audits as a prerequisite and prior to receiving SGIP incentives. Staff recommends that after an energy audit is performed, SGIP customers submit a summary of the completed audit recommendations, and identify which, if any, energy efficiency or demand response measures identified in the audit will be undertaken, and describe how this influences sizing of the self-generation system.

Staff recommends that similar to the CSI, an energy efficiency audit be required.

Parties generally support the proposed energy efficiency requirements. However, to the extent that any new audit tools need to be developed to support the proposed requirement, some argue the Commission should authorize funding for this purpose.

Discussion:

Energy efficiency is the top priority in the State's loading order and any method that could educate the customer of its energy usage and identify energy efficiency measures that could potentially reduce the customer's demand and thereby reduce the size of SGIP system and corresponding incentives should be encouraged. An audit will also help the customer consider related energy efficiency measures that could be deployed at the time of SGIP system installation, thereby potentially lowering the total cost to the customer.

We disagree with the parties who are opposed to the energy efficiency audit requirement and argue it is unnecessary. While we believe that some project owners on their own might take into account energy efficiency measures when sizing their systems, we cannot be certain that such a practice is common among all potential owners.

However, as CCSE notes, "the appropriate energy efficiency measures will vary not only from technology to technology, but likely from project to project."27 We support Staff's recommendation that customers should submit a summary of the completed audit, identifying which, if any, energy efficiency measures will be taken and how these measures affect sizing of the SGIP Project, but do not require implementation of any of the specific energy efficiency requirements as a prerequisite to participation in the SGIP.

4.5.6. Application Fee and Maximum Reservation Hold Time

Staff recommends an application fee for all SGIP projects and solicits comments on whether the fee should be a fixed amount or a percentage of system cost. According to Staff, the PAs have experienced additional work and increased administrative costs due to SGIP projects re-submitting the same application right after their project was cancelled because the project did not meet the required project milestones. Staff argues re-submitting an application will re-set the timeline at no penalty to the developer and slows the processing time of processing SGIP applications.

Staff proposes that projects should pay an application fee at the point of initial reservation requests, but the fee should be refundable once projects are complete. Staff also proposes that public entities pay half the application fees that commercial customers pay. The proposed application fees for commercial customers are as follows:

0-25 kW = $0

25-50 kW = $1,000

50-100 kW = $2,500

100-250 kW = $5,000

250-500 kW = $10,000

500-1000 kW = $20,000

1000-3000 kW = $25,000

Staff also proposes that the current reservation hold time of 18 months for a project be limited to a maximum of two, six month extensions. Staff notes the SGIP currently allows a project to reserve and hold an incentive for up to 18 months from the time the application is submitted. In addition, projects can request for extension to this timeframe. According to staff, there is no formalized or consistent process for granting extensions. Staff reports a significant number of SGIP projects have held reservations for longer than 18 months. These projects are holding up SGIP funds that could be used for other projects.

A number of parties agree with requiring an application fee for SGIP applications, but differ on the structure of the fee or whether the fee should apply to all technologies.

Debenham agrees with re-instituting application fees, and proposes the following tired mechanism based on project size.

Debenham also proposes that we make an exception and waive the application fee for projects that usually invest in obtaining measurement or preliminary engineering work that are needed for securing a permit prior to submitting an SGIP application. In Debenham's view, these types of expenses could be considered as proof that the applicant intends to complete the project, thus no additional application fee should be required.

CESA is also supportive of an SGIP application fee but proposes the following structure

1) Residential applications (systems < 10kW) should be either free or capped at $100;

2) Project application fees should be a flat 1% of the proposed incentive amount; and

3) All Application fees should be forfeited if a project is either withdrawn, expired, or cancelled. Forfeited fees shall be used to off set program administration costs or be returned to fund projects. If a project is successfully completed and a claim is filed and paid the fee should be refunded at the time of claim payment.

CESA also recommends requiring application fees from all SGIP applicants that are currently on the PAs' waitlist to secure their spots on the waitlist. CESA argues that without an application fee, there is almost no downside to simply applying for an SGIP spot.

With respect to project hold time, parties seem to support establishing and particularly enforcing project development timelines. Some parties advocate an 18 month deadline with no extensions. FCC suggests extensions be limited in duration and granted only if circumstances arise that are beyond the developer's control. In addition, FCC advocates that extensions should not be granted to projects that have not made satisfactory progress toward completion in compliance with established milestones and requirements.

Discussion:

We adopt a capacity-based application fee for SGIP projects. Previously, an application fee was required of all SGIP applications, but it was eliminated to encourage more participation in SGIP. We agree that an application fee serves to support program administration and create a disincentive for a perpetual application process. Moreover, we agree with CCSE that scaling the fee appropriately to the project size will help deter applicants who may not intend to complete projects. Accordingly, we require an application fee of all projects.

In addition, we require that all projects be limited to a maximum of two, six- month extensions after which the reservation shall be cancelled automatically. We do so to clarify because it appears that previous SGIP decisions did not specify how the PAss were to handle requests for extensions and this has resulted in inconsistent treatment of extension requests among the PAs and a general concern over the number of extensions granted. We agree with CESA that given the recent increased demand for SGIP, there is a need to ensure that the Program administrators manage the SGIP budget in such a way that only the highest quality applications with greatest certainty of completion remain in the queue. Moreover, it is important that the deadlines for completing applications are being enforced to ensure that projects are not holding up funds that could be used for other projects. At the same time, we agree that there may be circumstances beyond the developer's control that warrant an extension. To that end, extensions should be limited in duration and granted only for special circumstances. In addition, extensions should not be granted to projects that have not made satisfactory progress toward completion in compliance with established milestones and requirements.

Currently, PAs do not collect any information on the number of projects that request extensions or the number of projects that do not meet the extension deadlines. This information would be useful in determining the appropriate number of extensions and the appropriate length of an extension. The PAs should collect this data and submit a report annually to Energy Division. In the meantime, we allow two-six month extensions and direct the Program administrators to cancel projects that do not meet the required deadline.

4.5.7. Warranty Requirement

Staff recommends all technologies except wind turbines to have a 10-year service warranty. For wind turbines, staff recommends a 20-year warranty.

Currently, SGIP only requires projects to have a five-year warranty on parts. There is no requirement for a service warranty. We agree with Staff that requiring only a parts warranty is insufficient to protect ratepayers' investment. A service warranty for a reasonable expected useful life of a project ensures proper maintenance and continued project performance. We find that requiring a service warranty is reasonable. At the same time, we agree with UTC that suggests the need for further stakeholder input on specific warranty requirements. Therefore, we will direct the Energy Division staff to hold a workshop on the subject of the warranty.

6 See e.g., Opening Comments of Ice Energy, Inc. on Administrative Law Judge's Ruling Requesting Comments on Staff Proposal regarding Modifications to the Self-Generation Incentive Program (Ice Energy Comments), November 15, 2010, at 4.

7 SGIP Cost-Effectiveness of Distributed Generation Technologies Final Report, at 5-3.

8 The RPS program requires investor-owned utilities, electric service providers, and community choice aggregators to increase procurement from eligible renewable energy resources by at least 1% of their retail sales annually, until they reach 20% by 2010.

9 CCSE Reply Comments, May 9, 2011 at 3.

10 The Staff Proposals refer to Organic Rankine Cycle technologies, but as suggested in comments, any bottoming-cycle technology is likely to be GHG-reducing, not just ORCs. Thus, we clarify that all bottoming-cycle technologies are eligible for SGIP.

11 See the Cost-Effectiveness Report, Figure A-2.

12 ???????

13 Opening comments of UTC Power at 5.

14 Reply Comments of CLECA at 3.

15 SDG&E Comments to Staff proposal, November 15, 2010.

16 Fuel types referred to are OSB = onsite biogas, or NG = natural gas. Staff recommends that, in addition to OSB, any onsite renewable fuel, which meets RPS guidelines should be considered an eligible onsite renewable fuel and be eligible for the OSB based incentive levels. This recommendation allows for onsite biodiesel or waste vegetable oil to qualify.

17 Results shown are same as Table 1.

18 Paired with any otherwise eligible SGIP technology.

19 Stand-alone or paired with solar PV or any otherwise eligible SGIP technology.

20 Reply Comments of FCE at 4.

21 Reply Comments of UTC on Staff Proposal, Part II at 3)

22 DRA comments November 15, 2010, at 4.

23 See for example:

http://www.pge.com/includes/docs/word_xls/shared/selfgenerationincentive/waste_heat_emission_worksheet.xls

24 TURN Comments on Staff Proposal Regarding Modifications to the SGIP, November 15, 2010 at 7.

25 DRA Comments on Staff Proposal Regarding Modifications to the SGIP, November 15, 2010 at 4.

26 TURN Comments on Staff Proposal Regarding Modifications to the SGIP, November 15, 2010 at 7.

27 CCSE November 15, 2010 comments at 16.

Previous PageTop Of PageNext PageGo To First Page