Communications Division

RESOLUTION T- 17239

Carrier Oversight and Programs Branch

January 21, 2010

Event

Payment Cycle 1

(Day/Month)

Payment Cycle 2

(Day/Month)

Invoices due from Broadband Associates Int., Inc. to CD

5th of Month 1

20th of Month 1

Payment letters from CD to Information and Management Services Division (IMSD) 3

On 19th of Month 1

On 4th of Month 2

Invoices submitted from IMSD to State Controller's Office (SCO) for payments

20th through 26th of Month 1

5th through 13th of Month 2

THEREFORE, IT IS ORDERED that:

9

Proposed Project Budget

 

 

TOTAL PROJECT COST

$180,129,635

 

a)

Total CASF Request

 

 

b)

CASF @ 10%

$18,012,964

 

c)

CIAC (contributions-in-aid of construction)

-

 

d)

Applicant's Funds

See below*

 

e)

ARRA Funds, contingent upon receiving waiver from 10% matching fund requirement*

$162,116,672*

 

1 SB 1193 (Chapter 393, Stats. of 2008) established the California Advanced Services Fund as a new public purpose program.

2 The American Recovery and Reinvestment Act (ARRA) appropriates $7.2 billion for grants and loans to support broadband deployment on a national level. ARRA offers a unique and ground breaking opportunity for California to partner with the federal government and other state agencies in advancing the goal of bridging the digital divide.

3 The above schedule is contingent on the CASF recipient submitting clear, complete, and error-free invoices to CD. Additional time to process payments may be necessary if CD finds problems with the submitted invoices.