7. Factors Considered in Review of Proposals

7.1. Usefulness and Limitations of Cost Effectiveness Analysis

· The utilities are calculating the Avoided Cost of Capacity using combustion turbine costs which are too low.15

· PG&E's gross margins are too high.16

· The utilities used three different discount rates, 17 time horizons and lifecycles to compute the net present value of the benefits and costs.

· The three utilities used different input assumptions to compute avoided costs so that it is difficult to compare the cost effectiveness of the same programs across different utilities.18

· The avoided Transmission and Distribution (T&D) cost for PG&E is calculated incorrectly.19

· No party has provided a convincing argument for the inclusion of avoided T&D costs.20

· The Avoided T&D cost is applied incorrectly.21

· PG&E did not provide an appropriate Avoided T&D cost analysis.22

· The utilities' assumption that participant benefits are equal to participant costs skews the cost effectiveness results, since participant benefits are actually greater than, not equal to, participant costs for voluntary programs.23

· The utility's adjustments to the Avoided Capacity Cost based on LOLE/P calculations are inaccurate and inconsistent.24

· The utility's method exaggerates the benefits and does not include all the costs.25

· The cost effectiveness of statewide programs should not differ that much across the state.26

13 Guidance Ruling, February 27, 2008, p. 24.

14 The California Standard Practice Manual identifies the cost and benefit components and cost effectiveness calculation procedures from four major perspectives: Participant, Ratepayer Impact Measure (RIM), Program Administrator Cost (PAC) and Total Resource Cost (TRC). See the Standard Practice Manual at http://www.energy.ca.gov/greenbuilding/documents/background/07-J_CPUC_STANDARD_PRACTICE_MANUAL.PDF

15 CDRC Opening Brief, pp. 5; 6-8.

16 CDRC Opening Brief, pp. 5; 9-10.

17 CLECA March 2, 2009 comments.

18 DRA Opening Brief, p. 33.

19 TURN Opening Brief, p. 15.

20 DRA Opening Brief, p. 18; CAISO Opening Brief, p. 11.

21 CLECA March 2, 2009 comments.

22 TURN Opening Brief, p. 15; CLECA, CLECA March 2, 2009 Comments.

23 CDRC Opening Brief, pp. 6 and 11-13.

24 CDRC Opening Brief, pp. 6; 13-16.

25 TURN Opening Brief, pp. 18-25.

26 CLECA, p. 2 and Exhibit 601.

27 SCE Reply to CLECA Comments, March 5, 2009, p. 2.

28 PG&E Reply Brief, p. 8.

Previous PageTop Of PageNext PageGo To First Page