7. Comments on Proposed Decision

To ensure consistency in the estimation of overall and net benefits derived from all project awarded grants, DOE will apply a cost-benefit analysis (CBA) methodology. ... While the details of benefits estimation for each project might vary, the CBA methodology will be applied uniformly, and to the extent possible, DOE will use the same method, from project to project, to estimate each given type of benefit.82

Deployment of a smart grid will facilitate the following four mechanisms that contribute to reduced greenhouse gas (GHG) emissions.

· Increased use of renewable energy;

· Energy conservation;

· Load shifting; and

· Enabling electric transportation.88

Based on conservative estimates, SCE expects Edison SmartConnectTM to create an annual reduction of 365,000 metric tons of carbon dioxide or about 1,000 metric tons per day within our service territory. 89

The increased use of Plug-in Electric Vehicles (PEVs) supports greenhouse gas reduction goals by displacing fossil fuel emissions with electricity from an increasingly renewable utility generation portfolio. 90

(2) A tariff change in compliance with a statute or Commission order where the wording of the change does not follow directly from the statute or Commission order. ...

(9) A change to a rate or charge pursuant to a methodology approved by the Commission for use in an advice letter, such as an annual performance review for performance-based ratemaking as approved by the Commission for the Utility submitting the advice letter.101

Thus, the proposed use of Advice Letter is perfectly consistent with General Order 96B.

... the Commission must be willing to employ extraordinary and expedited decision-making procedures in order to meet the DOE's deadlines for approval of ARRA projects, because DOE is likely to significantly discount the merits of proposed projects for which required regulatory approvals and non-federal matching funding have not been timely secured.104

... the Commission should make clear that the requirement that utilities file a formal application for their projects under this process does not mean that the application should require evidentiary hearings, prepared testimony, or should require extensive discovery or even any discovery, if the application contains extensive information and factual support on its face. In addition, although limiting the protest period for such applications is helpful, it is equally important that the Commission direct the Assigned Commissioner and Administrative Law Judge presiding over the application to hold a prehearing conference and issue a scoping memo on an expedited basis, i.e. within a few days of the deadline for protests.105

... it is essential that the Commission acknowledge DOE's 90 day deadline for deciding Smart Grid applications, and direct the Assigned Commissioner and ALJ to issue a proposed decision on a "fast track" schedule, e.g. no later than 60 days following the Prehearing Conference. In addition to the comments and revisions that we have discussed herein, we have made other changes and revisions as we deemed appropriate.106

79 TURN Comments on PD at 4.

80 Id. at 7.

81 See ALJ Ruling, July 8, 2009, Attachment B at 51ff.

82 See ALJ Ruling, July 8, 2009, Attachment A.

83 TURN Comments on PD at 11.

84 Id. at 11.

85 Id. at 11.

86 See for example the June 6, 2002 Joint ACR and ALJ Ruling in R.02-06-001 at 5, which provides guidance to utilities on the costs that IOUs should submit for the "Base Case AMI Scenario."

87 Id. at 12.

88 SCE Comments, February 9, 2009 at 70.

89 Id.

90 Id. at 71.

91 See also PG&E Comments, February 9, 2009 at 33 and SDG&E Comments, February 9, 2009, at 27, which also provide information on this issue, albeit with less detail.

92 DRA Comments on PD at 11.

93 Id. at 12.

94 Id. at 11.

95 Id. at 12.

96 Id.

97 CFC Comments on Proposed Decision at 3.

98 Id. at 4.

99 Id. at 6.

100 Id.

101 General Order 99B, Energy Industry Rule 5, Section 5.3.

102 CFC Comments on Proposed Decision at 7.

103 Id. at 9.

104 PG&E Comments of Proposed Decision at 1.

105 Id. at 2-3.

106 Id. at 3.

Previous PageTop Of PageNext PageGo To First Page