Word Document PDF Document

ALJ/DUG/jt2 Date of Issuance 9/16/2009

Decision 09-09-006 September 10, 2009

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Application of San Diego Gas & Electric Company (U902M) for Authority to Update its Gas and Electric Revenue Requirement and Base Rates Effective on January 1, 2008.

Application 06-12-009

(Filed December 8, 2006)

And Related Matters.

Application 06-12-010

(Filed December 8, 2006)

Investigation 07-02-013

(Filed February 15, 2007)

(See Appendix for List of Appearances.)

DECISION DENYING THE PETITION TO MODIFY
DECISION 08-07-046 FILED BY THE GREENLINING INSTITUTE

1. Summary

This decision denies the petition to modify Decision 08-07-046 filed by the Greenlining Institute in light of the Commission's denial of the Greenlining Institute's application for rehearing, which raised identical issues. Therefore, the petition to modify is moot and hereby denied. There is no cost impact to ratepayers.