ALJ/VSK/tcg Date of Issuance 9/28/2009
Decision 09-09-033 September 24, 2009
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
In the Matter of the Application of Southern California Edison Company (U338E) for a Certificate of Public Convenience and Necessity Concerning the Antelope-Pardee 500 kV (Segment 1) Transmission Project as Required by Decision 04-06-010 and as Modified by Subsequent Assigned Commissioner Ruling. |
Application 04-12-007 (Filed December 9, 2004) |
And Related Matter. |
Application 04-12-008 (Filed December 9, 2004) |
DECISION MODIFYING DECISION (D.) 07-03-012 AND D.07-03-045
TABLE OF CONTENTS
Title Page
DECISION MODIFYING DECISION (D.) 07-03-012 AND D.07-03-045 22
2. Procedural Requirements under Rule 16.4 44
3. Requested Relief in Petition for Modification of D.07-03-012 55
4. Requested Relief in Petition for Modification of D.07-03-045 66
5. Construction Costs for the Antelope Transmission Project 88
8. Comments on Proposed Decision 1414
Attachment 1 - Redline of Modifications to Affected Portions of D.07-03-012
Attachment 2 - Redline of Modifications to Affected Portions of D.07-03-045
DECISION MODIFYING DECISION (D.) 07-03-012 AND D.07-03-045
On July 18, 2008, Southern California Edison Company (SCE) filed separate petitions for modification of Decision (D.) 07-03-012 in Application (A.) 04-12-007 and of D.07-03-045 in A.04-12-008 (collectively, the Decisions). The most significant change to the Decisions requested by SCE is to consolidate the maximum reasonable and prudent costs (maximum cost) set in the two Decisions, and to increase the total maximum cost for the transmission projects approved in the Decisions from $257.60 million to $746.00 million.
This decision grants the requested relief, as adjusted herein, and modifies D.07-03-012 as set forth in Attachment 1 and modifies D.07-03-045 as set forth in Attachment 2.