10. Assignment of Proceeding

Michael R. Peevey is the assigned Commissioner, and Burton W. Mattson is the assigned ALJ in this proceeding.

1. Reid has satisfied all the procedural requirements necessary to claim compensation in this proceeding. Reid made a substantial contribution to D.09-06-018 as described herein.

2. Reid requested hourly rates which are reasonable when compared to the market rates for persons with similar training and experience.

3. The total of the reasonable compensation is $14,106.25.

4. The Appendix to this decision summarizes today's award.

1. Reid has fulfilled the requirements of §§ 1801-1812, which govern awards of intervenor compensation, and is entitled to intervenor compensation for his claimed expenses incurred in making substantial contributions to D.09-06-018.

2. Reid should be awarded $14,106.25 for his contribution to D.09-06-018.

3. This order should be effective today so that Reid may be compensated without delay.

4. This proceeding remains open to address other matters.

ORDER

IT IS ORDERED that:

1. L. Jan Reid is awarded $14,106.25 as compensation for his substantial contributions to Decision 09-06-018.

2. Within 30 days of the effective date of this decision, Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company shall pay L. Jan Reid their respective shares of the award. We direct Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company to allocate payment responsibility among themselves, based on their California-jurisdictional electric revenues for the 2009 calendar year, to reflect the year in which the proceeding was primarily litigated. Payment of the award shall include interest at the rate earned on prime, three-month commercial paper as reported in Federal Reserve Statistical Release H.15, beginning October 20, 2009, the 75th day after the filing date of Reid's request for compensation, and continuing until full payment is made.

3. Rulemaking 08-08-009 remains open to address other related matters.

This order is effective today.

Dated November 20, 2009, at San Francisco, California.

APPENDIX

Compensation Decision Summary Information

Compensation Decision:

D0911027

Modifies Decision? No

Contribution Decision(s):

D0906018

Proceeding(s):

R0808009

Author:

ALJ Mattson

Payer(s):

Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company

Intervenor Information

Intervenor

Claim Date

Amount Requested

Amount Awarded

Multiplier?

Reason Change/Disallowance

L. Jan Reid

08-06-2009

$17,149.50

$14,106.25

No

Lack of Substantial Contribution.

Advocate Information

First Name

Last Name

Type

Intervenor

Hourly Fee Requested

Year Hourly Fee Requested

Hourly Fee Adopted

L. Jan

Reid

Analyst/Policy Expert

Self

$185

2008

$185

L. Jan

Reid

Analyst/Policy Expert

Self

$185

2009

$185

(END OF APPENDIX)