ALJ/DUG/hkr Date of Issuance 12/18/2009
Decision 09-12-043 December 17, 2009
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of San Diego Gas & Electric Company (U902M) for Authority to update its Gas and Electric Revenue Requirement and Base Rates effective on January 1, 2008. |
Application 06-12-009 (Filed December 8, 2006) |
And Related Matters. |
Application 06-12-010 Investigation 07-02-013 |
DECISION PARTIALLY GRANTING AND OTHERWISE DENYING
INTERVENOR COMPENSATION TO THE GREENLINING INSTITUTE
FOR SUBSTANTIAL CONTRIBUTION TO DECISION 08-07-046
TABLE OF CONTENTS
Title Page
DECISION PARTIALLY GRANTING AND OTHERWISE DENYING INTERVENOR COMPENSATION TO THE GREENLINING INSTITUTE
FOR SUBSTANTIAL CONTRIBUTION TO DECISION 08-07-046 22
2. Requirements for Awards of Compensation 33
2.1. Preliminary Procedural Issues 44
3. Greenlining's Assertion of a Substantial Contribution 66
4. Greenlining's Actual Contributions 99
5. Contributions of Other Parties 1717
6. Reasonableness of Requested Compensation 1818
6.1. Reasonable Hourly Rates 2020
6.2. The Hours and Costs Necessary for a Substantial Contribution 2222
DECISION PARTIALLY GRANTING AND OTHERWISE DENYING INTERVENOR COMPENSATION TO THE GREENLINING INSTITUTE
FOR SUBSTANTIAL CONTRIBUTION TO DECISION 08-07-046
This decision awards The Greenlining Institute $12,186.01 in compensation for its substantial contributions, on the issue of business office closures, to Decision 08-07-046, which is a decrease of $417,027 (97% reduction) because the majority of the requested compensation was for activities which the Commission found to be beyond the scope of the proceeding and no order was necessary by the Commission. Today's award payment will be split equally between San Diego Gas & Electric Company and Southern California Gas Company. These proceedings are closed.
San Diego Gas & Electric Company (SDG&E) filed Application (A.) 06-12-009, a general rate case (GRC) application, and Southern California Gas Company (SoCalGas) filed A.06-12-010, also a GRC application. They are related companies with some shared services. Decision (D.) 08-07-046 adopted a Test Year 2008 revenue requirement for each company, a mechanism for attrition adjustments until the next GRC, and performance and safety incentive mechanisms, which are reasonable and necessary to provide safe and reliable service to ratepayers.
The Test Year 2008 settlements adopted in D.08-07-046 provide a gas and electric revenue requirement of $1.361 billion for SDG&E and a gas revenue requirement of $1.685 billion for SoCalGas.