ALJ/BWM/jt2 Date of Issuance 12/28/2009

Decision 09-12-039 December 17, 2009

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Order Instituting Rulemaking to Continue Implementation and Administration of California Renewables Portfolio Standard Program.

Rulemaking 08-08-009

(Filed August 21, 2008)

DECISION GRANTING INTERVENOR COMPENSATION
TO SUSTAINABLE CONSERVATION FOR SUBSTANTIAL CONTRIBUTIONS TO RESOLUTION E-4137 AND DECISION 08-02-010

Table of Contents

Title Page

DECISION GRANTING INTERVENOR COMPENSATION TO
SUSTAINABLE CONSERVATION FOR SUBSTANTIAL
CONTRIBUTIONS TO RESOLUTION E-4137 AND DECISION 08-02-010
22

1. Summary 22

2. Background 22

3. Requirements for Awards of Compensation 33

4. Substantial Contribution 77

5. Contributions of Other Parties 1414

6. Reasonableness of Requested Compensation 1616

7. Productivity 1919

8. Award 2020

9. Waiver of Comment Period 2222

10. Assignment of Proceeding 2222

Findings of Fact 2323

Conclusions of Law 2323

ORDER 2424

Appendix

DECISION GRANTING INTERVENOR COMPENSATION TO SUSTAINABLE CONSERVATION FOR SUBSTANTIAL CONTRIBUTIONS TO
RESOLUTION E-4137 AND DECISION 08-02-010

1. Summary

This decision awards Sustainable Conservation $11,680.56 in compensation for substantial contributions to Resolution E-4137 and Decision 08-02-010. The award is a decrease of 28% from the amount requested due to reductions for duplication of efforts with other parties, failure to make a substantial contribution on some issues and a miscalculation. Today's award payment is allocated to Pacific Gas and Electric Company, San Diego Gas & Electric Company, and Southern California Edison Company for payment. This proceeding remains open.