Word Document PDF Document

ALJ/JHE/hkr Date of Issuance 4/12/2010

Decision 10-04-026 April 8, 2010

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Application of Southern California Edison Company

(U 338-E) for Approval of Demand Response Programs, Goals and Budgets for 2009-2011.

Application 08-06-001

(Filed June 2, 2008)

And Related Matters.

Application 08-06-002

Application 08-06-003

DECISION AWARDING INTERVENOR COMPENSATION TO THE UTILITY REFORM NETWORK FOR SUBSTANTIAL CONTRIBUTION TO
DECISION 09-08-027 AS MODIFIED BY DECISION 09-10-006

Claimant: The Utility Reform Network

For contribution to D.09-08-027 as modified

by D.09-10-006

Claimed ($): $153,735.98

Awarded ($): $123,240.03 (20% reduction)

Assigned Commissioner: Grueneich

Assigned ALJ: Hecht

PART I: PROCEDURAL ISSUES

A. Brief Description of Decision:

The utilities requested approximately $429.2 million for various demand response programs and aggregator contracts. The Commission approved budgets totaling $349,509,463 for demand response programs for PG&E, SCE and SDG&E for 2009-2011. The Commission reduced aggregator contract budgets by approximately $28 million and reduced the budgets for utility programs by about $52 million.

B. Claimant must satisfy intervenor compensation requirements set forth in Public Utilities Code §§ 1801-1812:

 

Claimant

CPUC Verified

Timely filing of notice of intent to claim compensation (§ 1804(a)):

1. Date of Prehearing Conference:

October 1, 2008

Yes

2. Other Specified Date for NOI:

   

3. Date NOI Filed:

October 31, 2008

Yes

4. Was the notice of intent timely filed?

Yes

Showing of customer or customer-related status (§ 1802(b)):

5. Based on ALJ ruling issued in proceeding number:

A.08-06-001 et al.

Yes

6. Date of ALJ ruling:

December 5, 2008

Yes

7. Based on another CPUC determination (specify):

   

8. Has the claimant demonstrated customer or customer-related status?

Yes

Showing of "significant financial hardship" (§ 1802(g)):

9. Based on ALJ ruling issued in proceeding number:

A.08-06-001 et al.

Yes

10. Date of ALJ ruling:

December 5, 2008

Yes

11. Based on another CPUC determination (specify):

   

12. 12. Has the claimant demonstrated significant financial hardship?

Yes

Timely request for compensation (§ 1804(c)):

13. Identify Final Decision

D.09-08-027

Yes

14. Date of Issuance of Final Decision:

August 24, 2009

Yes

15. File date of compensation request:

October 23, 2009

Yes

16. Was the request for compensation timely?

Yes

PART II: SUBSTANTIAL CONTRIBUTION

A. Claimant's description of claimant's contribution to the final decision (see § 1802(i), § 1803(a) & D.98-04-059)

Contribution

Citation to Decision or Record

Showing Accepted by CPUC

Policy Issue - Cost Effectiveness: TURN provided analysis and argument showing that the utilities cost-effectiveness calculations improperly value local T&D benefits and are incorrect with respect to the inclusion and quantification of certain costs (labor adders, etc.).

The Commission concluded that "some of these criticisms may have merit" but concluded that it was unnecessary to address the merits of these issues because the "estimates" used for c/e in "while somewhat flawed" were "sufficient for our purposes in this proceeding." (p. 17) The Commission concluded that these issues should be addressed in R.07-01-041.

Nahigian Direct Testimony, Sections II.B, III.A and B and IV.A.

D.09-08-027, Sec. 7.1, p. 16-19.

Although TURN's analysis was helpful in generally establishing the usefulness and limits of the utility cost effectiveness estimates, the Commission used the utilities' estimates and deferred the more general policy discussion to R.07-01-041. See disallowances in Section D.

Policy Issue - Baseline measurement:

TURN recommended against the use of SCE's proposed 3-in-10 baseline method and recommended that the Commission direct the utilities to place customers with highly variable loads on programs that do not require baseline calculation.

The Commission agreed and ordered that all utilities use the 10-in-10 baseline methodology, and likewise ordered the utilities to prepare a report that would include "a plan for steering highly variable load customers towards demand response programs that do not require baseline calculation."

Schilberg Direct Testimony, p. 9-11.

D.09-08-027, Sec. 17.4, p. 139-142.

Yes

Policy Issue - Emergency Demand Response:

TURN argued that the Commission should not include PG&E's Air Conditioner Cycling program in its adopted cap on emergency-triggered DR. The Commission agreed and modified the Proposed Decision to reflect this recommendation.

TURN Comments on Proposed Decision, p. 4.

Compares Sections 9 of PD and D.09-08-027.

Yes

Policy - MRTU Integration:

TURN Recommended that the Commission proceeding slowly to implement functionality less than full participating load functionality until further developments of MRTU capabilities.

The Commission as a general matter agreed that "it would be best to wait to make major changes to programs until the benefits of those changes are found to outweigh the costs." (p. 129)

Schilberg Direct Testimony, p. 3-6.

D.09-08-027, Sec. 16.3 and 16.4, p. 126-132.

Yes

SDG&E BIP - SDG&E requested 1657067, a slight increase over 2008. TURN recommended 993000. The Commission authorized 1475423 based on 2008 actual, a difference of about $200,000.

Nahigian Direct Testimony, Sec. V.F.

D.09-08-027, Sections 10.1.1.2 and 10.1.1.3

Yes

PG&E's Capacity Bidding Program: TURN recommended discontinuing the CBP due to its low cost effectiveness, or alternatively, reducing the budget by over $4 million based on excessive administrative costs.

The Commission agreed that the low b/c ratio warrants reduced funding and that administrative expenses "should not be greater than the amount spent on incentives." (p. 50). The Commission thus reduced the authorized budget by almost $3 million.

Nahigian Direct Testimony, Sec. III.D.

D.09-08-027, Sec. 10.2.2.3

"As noted by TURN and DRA, the benefit to cost ratio of this program, and especially the day-ahead option, are far below one, so it does not appear that this program is cost effective for PG&E at this time. However, there is value to having this program or a similar option operate statewide, and we hope that the benefit to cost ratio may be improved in the future. Given the relatively low benefit to cost ratio of PG&E's program, however, it would not be reasonable to fully fund this program as requested by PG&E. Specifically, it is reasonable to expect that the funding spent on administrative expenses for a program should not be greater than the amount spent on incentives. For this reason, we will continue the PG&E program as an aggregator-managed program, but with a lower budget than proposed by PG&E. PG&E requests $4,623,609 for administrative activities, and $1,564,685 for incentives. We authorize a total funding of $3,615,076 for PG&E's Capacity Bidding Program for 2009-2011, as noted below."

Yes

SDG&E's Capacity Bidding Program:

TURN recommended a reduction of program costs of about $3.5 million based on excessive administrative costs and historical recorded expenses. TURN also argued that the b/c ratio was lower than calculated by SDG&E due to an unrealistic forecast of load impacts.

The Commission agreed that it "is not clear whether the estimates of program potential load impact" are realistic, but then accepted SDG&E's contention that interest in the program will increase. The Commission agreed that administrative costs should be no higher than incentives, but reduced the budget by only $400,000 due to the expectation of higher future incentive costs.

Nahigian Direct Testimony, Sec. V.E., p. 38.

Schilberg Direct Testimony, p. 8-9.

D.09-08-027, Sec. 10.2.2.3, p. 50: "Consistent with our policy that the administrative costs should not exceed the incentive costs for a program in a given year, we reduce SDG&E's proposed budget for this program by approximately $400,000, the amount of the excess administrative costs for 2009."

Yes

PG&E's Critical Peak Pricing Program:

TURN recommended elimination of funding due to D.08-07-045 or reduction based on 2006-08 recorded. The Commission rejected TURN's position, but alternatively found that "At the same time, we recognize that the funding for Critical Peak Pricing authorized in this decision should be discontinued if a new default Critical Peak Pricing program is adopted in A.09-02-022."

Nahigian Direct Testimony, Sec. III.J.

D.09-08-027, Sec. 10.2.3.

Yes

PG&E's PeakChoice:

TURN recommended a $9.2 million reduction in funding due to excessive administrative costs. The Commission agreed with TURN that the administrative costs for PeakChoice are too high compared to total program costs. The Commission agreed that program costs should be no more than incentives and reduced budget from $16.9 million to $9.0 million, a reduction of almost $8 million.

Nahigian Direct Testimony, Sec. III.E., p. 13-14.

D.09-08-027, Sec. 11.1.3.

"The forecasted expenditures for PeakChoice in 2008 were approximately $2.8 million; as noted by TURN; total estimated costs of this program from its adoption in 2007 through the end of 2008 were approximately $4 million. These numbers are much lower than the $16.9 million requested by PG&E for this program in its application. PG&E does not provide sufficient rationale for such a large budget request.

...

In addition, as TURN notes, PG&E's proposed administrative costs for this program are extremely high compared to the estimated costs of incentives under the program. As discussed above with respect to PG&E's Capacity Bidding Program, it is reasonable to expect that administrative expenses for a program should not be greater than the amount spent on incentives. We approve a total budget for 2009-2011 of $9 million, which allows for some growth of the program over 2008 forecast levels."

Yes

PG&E's BEC/ABEC programs - TURN and DRA both recommended discontinuation of this program due to extremely low cost effectiveness. TURN also argued that the non-quantifiable benefits promoted by PG&E were not unique to this program. The Commission agreed on both counts and ordered discontinuation of both BEC and ABEC. PG&E had requested budgets of $15.384 million for these programs.

Nahigian Direct Testimony, Sec. III.C., p. 11-12.

D.09-08-027, Sec. 11.1.4

Yes

PG&E Legacy Conversion and Supportive Activities - TURN recommended eliminating the Legacy Demand Response Conversion program. The Commission agreed and reduced PG&E's budget for miscellaneous supportive activities from $29,483,000 requested to 16,902,000, by completely eliminating three projects, including the Legacy DR Conversion project.

Nahigian Direct Testimony, Sec. III.H., p. 17.

D.09-08-027, Sec. 11.4

"Several of these items, including PG&E's Legacy Demand Response Conversion, a Marketing Decision Support System upgrade, and Interval Meters and SDG&E's Codes and Standards are not sufficiently supported by information in the utilities' applications, and may be duplicative of activities already funded in these utilities' AMI, energy efficiency or other proceedings. We do not approve additional funding for these efforts, which are not justified by supportive information in the applications."

Yes

TA/TI for SCE - TURN recommended a reduction of about $35 million based on recorded costs in 2006-08 and high administrative costs relative to incentives. The Commission agreed with SCE that certain "administrative" costs really reflect program costs. The Commission rejected TURN's argument about recorded costs based on SCE's contention of "committed" funds, but also found that "SCE's method of reporting money spent under its Technical Assistance and Technology Incentives program makes it difficult to determine the demand for this program or the budget required to sustain it through 2011. To address this, we require SCE to add a line to all future reports on this program to show the funds committed under this program in a given month and year." (p. 82)

Nahigian Direct Testimony, Sec. IV.B.

D.09-08-027, Sec. 12.1.1.1 and 12.1.3

Yes

TA/TI for PG&E - TURN recommended 1) a reduction of about 2.22 million due to high administrative costs, and 2) rejection of proposal to reduce customer contribution for new construction. The Commission agreed with TURN on the second point and found that "There is not sufficient information in the record on the desirability of making this change or the possible implications on PG&E's line extension rules." (p. 83)

Nahigian Direct Testimony, Sec. III.F.

D.09-08-027, Sec. 12.1.1.2 and 12.1.3

Yes

SDG&E TA/TI - TURN recommended a eliminating SDG&E's TA/TI budget due to SDG&E's claims in the AMI proceeding. The Commission found that it is not reasonable to expect the benefits of AMI since SDG&E has not fully deployed the AMI system. The Commission stated that by 2012 "we expect SDG&E will be able to substantiate the claims made in its AMI proceeding by substantially reducing or eliminating Technical Assistance and Technology Incentives costs." (p. 82)

D.09-08-027, Sec. 12. 1.1.3 and 12.1.3

Yes

Emerging Markets and Technologies: TURN recommended eliminating SDG&E's budget based on overlap with AMI funding and reducing SCE's budget based on 2008 recorded spending. The Commission rejected TURN's arguments to reduce funding, though the Commission did require annual reporting of project results.

Nahigian Direct Testimony, Sec. V.A and B.

D.09-08-027, Sec. 12.2.2 and 12.2.3

Yes

Education, Marketing and Outreach: TURN objected to budgets for utility-specific outreach and marketing campaigns and recommended specific cuts to several requests based on recorded historical spending.

The proposed decision approved budgets only for 2009 and ordered that budgets for 2010-11 be established in A.08-07-021.

The final Decision adopted the requested budgets but directed the utilities to coordinate these activities with similar activities funded in the energy efficiency proceedings and noted that these activities and budgets "may be reviewed and revised" in A.08-07-021. (p. 98)

TURN Opening Brief, p. 28-30.

D.09-08-027, Sec. 13, p. 94-98.

Proposed Decision, p. 88 ("We defer review of the utilities' requested budgets for these specialized marketing programs for 2010 and 2011 to A.08-07-021 et al.").

TURN did not prevail on most specific issues in these areas. See disallowances in Section D.

Pilot Programs: PG&E Smart AC: TURN recommended against authorization of PG&E's SmartAC Ancillary Services Pilot as duplicative of SCE's pilot. The Commission approved continuation of this pilot for 2010-11 without any further findings or discussion of the record.

PG&E's Integration Pilots: The Commission disagreed with TURN's recommendation not to approve PG&E's intermittent generation integration pilots.

Schilberg Direct Testimony, p. 2.

D.09-08-027, Sec. 14, p. 98.

Nahigian Direct Testimony, Sec. III.I.

D.09-08-027, Sec. 14.1.1, p. 99-102.

The Commission disagreed with TURN's recommendations in this area. The Commission approved the continuation of PG&E's SmartAC Ancillary Services Pilot and approved PG&E's intermittent generation integration pilots.

See disallowances in Section D.

EM&V:

TURN recommended reducing the EM&V budgets of SCE and SDG&E. The Commission rejected this recommendation. TURN also recommended against using $162,000 for finalizing the evaluation of the terminated PEAK program. While, the Commission concluded that "it is not necessary to provide funding for evaluation of activities that we are denying or discontinuing in this application," TURN is unsure whether this directive applied to the PEAK program EM&V.

D.09-08-027, Sec. 23.1 and 23.2.

Although TURN did not make a substantial contribution in this area, we have previously disallowed all of TURN's hours related to its efforts on marketing and education budgets, so we make no further reductions for the Commission's rejection of TURN's recommendations in this area.

Process for Future Program and Budget Modifications: TURN opposed the utility requests to use advice letters for program revisions and recommended that any material changes to programs be addressed in applications.

The Commission affirmed its earlier Ruling that any program changes must be submitted via an application.

Nahigian Direct Testimony, Sec. II.D., p. 8.

D.09-08-027, Sec. 25.3. Note that the Decision does not discuss TURN's position in Sec. 25.2, but TURN did submit testimony on this issue.

Yes

Permanent Load Shifting: TURN opposed Transphase's standard offer proposal as too expensive based on too high an incentive level compared to cost. The Commission essentially agreed with TURN's (and the IOUs') position that the proposed program was not cost effective and too expensive

Nahigian Rebuttal Testimony, p. 1-6.

D.09-08-027, Sec. 21.3, p. 173-182.

Yes

Backup Generation: TURN opposed the proposal by BluePoint Energy to make backup generators a demand response program eligible for TA/TI incentives based on both policy and factual grounds. The Commission agreed with TURN's analysis.

Nahigian Rebuttal Testimony, p. 6-9.

D.09-08-027, Sec. 20.1, p. 165-167.

Yes

B. Duplication of Effort (§§ 1801.3(f) & 1802.5):

 

Claimant

CPUC Verified

a. Was DRA a party to the proceeding? (Y/N)

Y

Yes

b. Were there other parties to the proceeding? (Y/N)

Y

Yes

c. If so, provide name of other parties: San Francisco Community Power, North American Power Partners, EnerNOC, Energy Connect, Alliance for Retail Energy Markets, CPower, CLECA, Transphase, Energy Curtailment Specialists, Inc., Chapeau, Inc., California Demand Response Coalition

Yes

d. Claimant's description of how it coordinated with DRA and other parties to avoid duplication or how your participation supplemented, complemented, or contributed to that of another party:

    Most of the parties to the proceeding were demand response aggregators or vendors whose interests were not aligned with TURN's interests. Their participation added to TURN's workload on issues such as permanent load shifting, backup generation and cost effectiveness analysis.

    TURN explicitly coordinated with the DRA to allocate workload. The result was that TURN focused on program A&G costs, including marketing and education, as well as load impacts and certain cost-effectiveness issues. The DRA took the lead on aggregator contract issues and certain cost-effectiveness issues. DRA also addressed various program-specific issues. TURN supplemented DRA's analysis with independent argument concerning PG&E's BEC program.

Yes

C. Additional Comments on Part II:

#

Claimant

CPUC

Comment

1

X

 

TURN has identified the majority of recommendations and issues which we addressed in testimonies and/or briefs, including both issues where our recommendations were not accepted. While TURN has not identified absolutely all issues or recommendations, especially if the Commission did not adopt TURN's position or analysis, we did identify the issues that accounted for the vast majority of TURN's time and expenses in this proceeding.

While there were several large dollar recommendations made by TURN (reducing SCE's TA/TI costs, SDG&E's program costs, Marketing, Education and Outreach Costs) which the Commission rejected, TURN suggests that the net contribution by TURN based on the specific recommendations adopted by the Commission (net reduction of about $27 million), recommendations adopted by the proposed decision (reducing ME&O costs) as well as the contribution to the Commission's deliberations and analyses on other issues warrant our request for full recovery of all costs and expenses in this proceeding.

PART III: REASONABLENESS OF REQUESTED COMPENSATION

(Completed by Claimant except where indicated)

A. General Claim of Reasonableness (§§ 1801 & 1806):

Concise explanation as to how the cost of claimant's participation bears a reasonable relationship with benefits realized through participation (include references to record, where appropriate)

CPUC Verified

 

TURN had recommended total reduction in utility budgets of about $147 million, including about $30 million in reductions for administrative costs associated with specific utility programs (TURN Opening Brief, p. 2-3). The other recommended reductions concerned TA/TI programs, marketing education and outreach (ME&O) spending and AMI overlap. The Commission reduced total program spending by about $52 million. The reductions which were based in whole or in part on TURN's specific recommendations totaled almost $27 million, as shown in the Table below (based on Tables in Section 24 of D.09-08-027 and the text identified in Part II.A. above):

 Program

Requested

Authorized

Difference

SDG&E BIP

$1,657,067

$1,457,423

$199,644

PG&E Peak Choice

$16,954,000

$9,000,000

$7,954,000

PG&E Legacy Conversion

$4,828,000

$0

$4,828,000

PG&E CBP

$6,674,000

$3,615,076

$3,058,924

PG&E BEC

$15,382,000

$4,623,996

$10,758,004

Total

$26,798,572

TURN's analyses and recommendations were the primary basis for reductions of about $16 million. TURN provided independent argument to support DRA's analysis against continuation of the BEC program, which resulted in a budget reduction of another $10.8 million.

Assuming that our participation contributed about 50% to the elimination of the BEC program, TURN thus suggests that our participation resulted in reduced ratepayer costs of about $21.4 million over the three-year period 2009-2011. This ratepayer benefit justifies our participation in this proceeding and the requested compensation request.

TURN also notes that the Commission adopted several policy recommendations (baseline methodology, future evaluations of pilot results, etc.) that should provide direct and indirect rate payer benefits.

After the reductions and

disallowances we make to this claim, the remainder of TURN's hours and costs are reasonable and should be compensated.

     

B. Specific Claim*:

Claimed

CPUC Award

ATTORNEY AND ADVOCATE FEES

Item

Year

Hours

Rate $

Basis for Rate

Total $

Year

Hours

Rate $

Total $

M. Hawiger

2009

139.0

325

D.08-08-027

45,175.00

2009

114.35

325

37,163.75

M. Hawiger

2008

34.25

325

D.08-08-027

11,131.25

2008

29.75

325

9,668.75

M. Florio

2009

1.0

535

D.09-08025

535.00

2009

1.0

535

535.00

H. Goodson

2009

0.5

280

D.09-10051

140.00

2009

0

280

0

N. Suetake

2008

4.5

225

D.09-04-027

1,012.50

2008

4.5

225

1,012.50

Subtotal: $57,993.75

Subtotal: $48,380.00

EXPERT FEES

Item

Year

Hours

Rate $

Basis for Rate

Total $

Year

Hours

Rate $

Total $

B. Marcus

2008

3.50

250

D.08-11-053

875.00

2008

3.5

250

875.00

J. Nahigian

2008

271.75

190

D.09-04-027

51,632.50

2008

201.37

190

38,260.30

J. Nahigian

2009

84.75

190

D.09-04-027

ALJ 235

16,102.50

2009

56.75

190

10,782.50

G. Schilberg

2008

106.11

200

D.09-04-027

ALJ 235

21,222.00

2008

96.91

200

19,382.00

G. Schilberg

2009

17.84

200

D.09-04-027

ALJ 235

3,568.00

2009

16.09

200

3,218.00

G. Jones

2008

1.98

120

D.09-04-027

237.60

2008

1.98

120

237.60

Subtotal: $93,637.60

Subtotal: $72,755.40

INTERVENOR COMPENSATION CLAIM PREPARATION **

Item

Year

Hours

Rate $

Basis for Rate*

Total $

Year

Hours

Rate $

Total $

M. Hawiger

2009

12.00

162.50

D.08-08-027

1,950.00

2009

12.00

162.50

1,950.00

M. Hawiger

2008

.25

162.50

D.08-08-027

40.63

2008

.25

162.50

40.63

Subtotal: $1,990.63

Subtotal: $1,990.63

COSTS

#

Item

Detail

Amount

Amount

1

Xeroxing

Photocopies for pleadings not emailed

114.00

114.00

Subtotal: $114.00

Subtotal: $114.00

TOTAL REQUEST: $153,735.98

TOTAL AWARD: $123,240.03

*We remind all intervenors that Commission staff may audit their records related to the award and that intervenors must make and retain adequate accounting and other documentation to support all claims for intervenor compensation. Claimant's records should identify specific issues for which it seeks compensation, the actual time spent by each employee or consultant, the applicable hourly rates, fees paid to consultants and any other costs for which compensation was claimed. The records pertaining to an award of compensation shall be retained for at least three years from the date of the final decision making the award.

**Reasonable claim preparation time typically compensated at ½ of preparer's normal hourly rate.

C. Attachments or Comments Documenting Specific Claim (not attached to final Decision):

Attachment or Comment #

Description/Comment

Attach 1

Certificate of Service

Attach 2

Attorney Time Sheets

Attach 3

Expert Witness Time Sheets

Attach 4

Direct Expenses

Comment 1

Reasonableness of Attorney Time: Most of the attorney hours in this proceeding reflect work performed by Marcel Hawiger, the lead attorney representing TURN in this proceeding. Mr. Hawiger spent approximately 170 hours, or the equivalent of four weeks of work, on this proceeding. Mr. Hawiger reviewed all the applications and testimonies, drafted all briefs and pleadings, conducted cross examination of utility witnesses and performed all discovery and other procedural work in this proceeding. Given the magnitude of the requests by the three IOUs for programs spanning three years, TURN suggests that this amount of attorney time represents a reasonable expenditure of effort. TURN also suggests that our relative success in contributing to Commission findings that resulted in over $20 million in disallowances warrants full compensation for TURN's attorney time.

 

Comment 2

Allocation of attorney time by issue: TURN used the following codes to identify the primary issue categories: MRTU (issues related to MRTU pilots and transition to MRTU), Policy (policy issues related to price responsive and emergency DR programs), A&G (administrative and general cost levels of utility programs), BEC (issues related to PG&E's BEC/ABEC program), C/E (cost effectiveness methodology and calculations), MEO (marketing, education and outreach costs), DISC (discovery issues). TURN used the code "GP" to describe work that is generic to proceedings (reading pleadings and testimonies of other parties, attending PHCs) and the term "#" to describe work that included more than one issue category. Much of the work labeled as GP, CE or # related to analysis or pleading preparation concerning specific utility programs (Section 5 of TURN's opening brief).

Based on a review of attorney time sheets and briefs, TURN estimates the following allocation of attorney time by issue category:

Code

Issues

Approximate Allocation of Time

MRTU

Analysis of MRTU pilot

10

A&G

Level of A&G expenses for programs

20

C/E

Program cost effectiveness; General c/e measurement issues

10

BEC and Other Utility Programs

C/E of the BEC/ABEC programs

30

MEO

Marketing and education budgets

10

Policy

Policy issues related to authorization of price-responsive and emergency DR programs

20

Total

100

   

Comment 3

Reasonableness of Expert Witness Fees: TURN appreciates that this request includes considerable time spent by our two expert witnesses from JBS Energy, Inc. Participation in this proceeding required the witnesses to review voluminous testimony and data submissions by the three large electric IOUs (SDG&E, PG&E and SCE) pertaining to multiple demand response programs, with requests for funding spanning the next three years (2009-2011).

Mr. Jeff Nahigian was the lead witness on cost-effectiveness and program cost issues. Mr. Nahigian reviewed historical cost data for all the programs in order to base his recommendations for future program costs. Mr. Nahigian identified numerous disallowances due to excessive administrative (A&G) expenses and due to overlap with prior AMI proceedings. The Commission did not agree with the AMI-related disallowances but generally agreed with Mr. Nahigian's recommendation to limit A&G costs to no more than forecast incentive costs, resulting in disallowances totaling about $16 million.

Ms. Gayatri Schilberg was the lead witness addressing load impact measurement, baseline methodology and MRTU integration. The Commission adopted her two primary policy recommendations concerning baseline and MRTU integration. The Commission did not adopt her specific recommendations concerning disallowances of certain pilot programs.

The Commission is familiar with the work of Mr. Nahigian and Ms. Schilberg from numerous past proceedings. TURN suggests that the time spent by these witnesses in this proceeding represents an efficient and effective use of witness expertise to review the necessary information, perform the analysis and form useful recommendations for the Commission's consideration.

 

D. CPUC Disallowances & Adjustments:

TURN's timesheets for its experts does not indicate allocation of time by major issue as required in D.98-04-059 (p.48). In Section C-Comment #3 of this claim, TURN states that expert Nahigian focused on cost-effectiveness and program cost issues by reviewing historical cost data for all the programs in order to base his recommendations for future program costs and expert Schilberg focused on issues relating to load impact measurement, baseline methodology and MRTU integration. Faced with the task of allocating expert time by major issue, we totaled hours spent reviewing, prepping, drafting and editing testimony presented by TURN in this proceeding. We then independently reduce these hours to determine the disallowances outlined in Section D. We caution TURN to comply with the requirement and allocate time for all participants, including its experts, by major issue in future claims to avoid the potential of erroneous disallowances.

#

Reason

2009-Nahigian

TURN requests 2.5 hrs of travel time, logged under professional hours for Nahigian's attendance at a hearing on 01-09-09. This time is designated as "routine commuting" and as such is not compensable. (reduced $475)

Policy Issue and Cost Effectiveness

Hawiger 2009 (all CE hrs)- reduced .25 hrs=$81.25

Nahigian 2008 (30% reduction)-reduced 42.23 hrs=$8,023.70

Nahigian 2009 (30% reduction)-reduced 7.5 hrs=$1,425

Education, Marketing and Outreach

Goodson 2009 (all MOE hrs)-reduced .50 hrs=$140

Hawiger 2009 (40% reduction in A&G hours)-reduced 6.9 hrs=$2,242.50

Nahigian 2008 (20% reduction)-reduced 28.15 hrs=$5,348.50

Nahigian 2009 (20% reduction)-reduced 5.0 hrs=$950

Pilot Programs

Schilberg 2008 (30% reduction)-reduced 9.2 hrs=$1,840

Schilberg 2009 (30% reduction)-reduced 1.75 hrs= $350

TURN's Reply Brief filed on

02-11-09

TURN requests a total of approximately 59 hrs (including Hawiger's 28.25 hours and Nahigian's 26 hours) in compensation for the preparation of this 24-page document. We find these hours to be excessive given the scope of the document and its length. As such we reduce these hours by 50%, as follows:

2009 Hawiger reduced 14 hours

2009 Nahigian reduced 13 hours

General (GP) Preparation Hours

We reduce TURN's general preparation hours equal to the same reduction percentage per work year we have listed above:

2008 Hawiger reduced 4.5 hrs (24% of GP hrs)=$1,462.50

2009 Hawiger reduced 3.5 hrs (13% of GP hrs)=$1,137.50

PART IV: OPPOSITIONS AND COMMENTS

Within 30 days after service of this claim, Commission Staff

or any other party may file a response to the claim (see § 1804(c))

A. Opposition: Did any party oppose the claim (Y/N)?

No

B. Comment Period: Was the 30-day comment period waived (see Rule 14.6(2)(6)) (Y/N)?

Yes

FINDINGS OF FACT

1. Claimant has made a substantial contribution to Decision (D.) D.09-08-027 as modified by D.09-10-006.

2. The claimed fees and costs are comparable to market rates paid to experts and advocates having comparable training and experience and offering similar services.

3. The total of reasonable contribution is $123,240.03.

CONCLUSION OF LAW

1. The claim, with any adjustment set forth above, satisfies all requirements of Public Utilities Code §§ 1801-1812.

ORDER

1. Claimant is awarded $123,240.03.

2. Within 30 days of the effective date of this decision, Southern California Edison Company, San Diego Gas & Electric Company, and Pacific Gas and Electric Company shall pay their respective shares of the award. We direct Southern California Edison Company, San Diego Gas & Electric Company, and Pacific Gas and Electric Company to allocate payment responsibility among themselves, based on their California-jurisdictional gas and electric revenues for the 2008 calendar year, to reflect the year in which the proceeding was primarily litigated. Payment of the award shall include interest at the rate earned on prime, three-month commercial paper as reported in Federal Reserve Statistical Release H.15, beginning January 6, 2010, the 75th day after the filing of claimant's request, and continuing until full payment is made.

3. The comment period for today's decision is waived.

4. This proceeding remains open to address a pending application for rehearing.

5. This order is effective today.

Dated April 8, 2010, at San Francisco, California.

APPENDIX

Compensation Decision Summary Information

Compensation Decision:

D1004026

Modifies Decision? No

Contribution Decision(s):

D0908027 as modified by D0910006

Proceeding(s):

A0806001, A0806002, and A0806003

Author:

ALJ Hecht

Payer(s):

Southern California Edison Company, San Diego Gas & Electric Company, and Pacific Gas and Electric Company

Intervenor Information

Intervenor

Claim Date

Amount Requested

Amount Awarded

Multiplier?

Reason Change/Disallowance

The Utility Reform Network

10-23-09

$153,735.98

$123,240.03

No

lack of substantial contribution and the disallowance of hours for routine travel

Advocate Information

First Name

Last Name

Type

Intervenor

Hourly Fee Requested

Year Hourly Fee Requested

Hourly Fee Adopted

Marcel

Hawiger

Attorney

The Utility Reform Network

$325

2008

$325

Marcel

Hawiger

Attorney

The Utility Reform Network

$325

2009

$325

Michel

Florio

Attorney

The Utility Reform Network

$535

2009

$535

Hayley

Goodson

Attorney

The Utility Reform Network

$280

2009

$280

Nina

Suetake

Attorney

The Utility Reform Network

$225

2008

$225

Bill

Marcus

Expert

The Utility Reform Network

$250

2008

$250

Jeff

Nahigian

Expert

The Utility Reform Network

$190

2008

$190

Jeff

Nahigian

Expert

The Utility Reform Network

$190

2009

$190

Gayatri

Schilberg

Expert

The Utility Reform Network

$200

2008

$200

Gayatri

Schilberg

Expert

The Utility Reform Network

$200

2009

$200

Gerrick

Jones

Economist

The Utility Reform Network

$120

2008

$120

(END OF APPENDIX)

Top Of PageGo To First Page