ALJ/EDF/eap/lil Date of Issuance 4/12/2010

Decision 10-04-010 April 8, 2010

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Application of San Diego Gas & Electric Company (U902E) for Adoption of its 2010 Energy Resource Recovery Account Revenue Requirement Forecast and Review of its Power Procurement Balancing Account.

Application 09-10-003

(Filed October 1, 2009)

DECISION ADOPTING SAN DIEGO GAS & ELECTRIC COMPANY'S
2010 ENERGY RESOURCE RECOVERY ACCOUNT REVENUE
REQUIREMENT FORECAST AND REVIEWING ITS POWER
PROCUREMENT BALANCING ACCOUNT

Summary

In this decision, we adopt San Diego Gas & Electric Company's (SDG&E) amended 2010 Energy Resource Recovery Account (ERRA) forecast load, available resources and costs, and approve SDG&E's amended forecasted 2010 ERRA revenue requirement. The adopted forecasts consist of a $827.956 million 2010 ERRA forecast revenue requirement, $46.908 million 2010 forecast ongoing Competitive Transition Charge (CTC) revenue requirement, 2010 market benchmark price of $58.54/megawatt-hour (MWh) for calculating CTC, and a $61.05/MWh for calculating the Power Charge Indifference Adjustment.