A PHC is set for June 14, 2010 at 10:00 a.m. in the Commission Courtroom, State Office Building, 505 Van Ness Avenue, San Francisco, California. At the PHC, the parties should be prepared to discuss the issues addressed in this order, as well as any procurement-related policy proposals not ruled out of scope in this OIR. In lieu of PHC statements, we request that parties file comments on the Preliminary Scoping Memo contained herein.
Track I - Preliminary Schedule
Proceeding Milestone |
Date |
Ruling on Preliminary Planning Standards |
May 2010 |
Ruling on Energy Efficiency Assumptions |
May 2010 |
Comments due on Preliminary Scoping Memo |
June 4, 2010 |
Prehearing Conference |
June 14, 2010 |
Draft ED Staff Report on renewables assumptions |
June 2010 |
Comments / Reply and Party Alternative Proposals on DR, renewables, and other non-renewables assumptions |
June 2010 |
Scoping Memo for Track I |
July 2010 |
Deadline for inputs to Track II |
November 2010 |
IOUs file system resource plans |
Q1 2011 |
Testimony, Briefs, and Hearings (If Necessary) |
Q2 2011 |
Proposed Decision |
Q3 2011 |
Decision |
Q4 2011 |
Track II - Preliminary Schedule
Proceeding Milestone |
Date |
Ruling on Preliminary Planning Standards |
May 2010 |
Comments due on Preliminary Scoping Memo |
June 4, 2010 |
Prehearing Conference |
June 14, 2010 |
Scoping Memo for Track II |
To Be Determined |
Process: · Input Received from Tracks I and III · IOU Bundled Plans and Testimony · Intervenor Testimony · Evidentiary Hearings · Post-hearing Briefs · Post-hearing Reply Briefs · Preparation of the decision on IOU bundled procurement plans. |
December 2010 through October 2011 |
Proposed Decision(s) on IOU-specific Bundled Procurement Plans |
November 2011 |
Track III - Preliminary Schedule
Proceeding Milestone |
Date |
Comments due on Preliminary Scoping Memo |
June 4, 2010 |
Prehearing Conference |
June 14, 2010 |
Scoping Memo for Track III |
To Be Determined |
Proposals, Comments, and/or Workshops |
June 2010 to October 2011 |
Deadline for inputs to Track II |
November 2010 |
Assigned Commissioner Rulings or Decisions on Track III Issues and Assumptions |
As Appropriate |
Each of the issue areas outlined in the Preliminary Scoping Memo will likely require different types and degrees of public participation. Therefore, we delegate further definition of procedure and schedule for each issue area to the assigned Commissioner and ALJ as determined in the Scoping Memo or later ruling. We leave open the possibility that issue areas may be decided upon individually in interim decisions, if necessary. In addition, we authorize the assigned Commissioner and ALJ to organize issues within the proceeding, including moving issues between tracks.
This proceeding will conform to the statutory case management deadline for ratesetting matters set forth in § 1701.5. In particular, it is our intention to resolve all relevant issues within 24 months of the date of the assigned Commissioner's Scoping Memo for each track. In using the authority granted in § 1701.5(b) to set a time longer than 18 months, we consider the number and complexity of the tasks and the need to coordinate with other proceedings.