8. Schedule

A PHC is set for June 14, 2010 at 10:00 a.m. in the Commission Courtroom, State Office Building, 505 Van Ness Avenue, San Francisco, California. At the PHC, the parties should be prepared to discuss the issues addressed in this order, as well as any procurement-related policy proposals not ruled out of scope in this OIR. In lieu of PHC statements, we request that parties file comments on the Preliminary Scoping Memo contained herein.

Track I - Preliminary Schedule

Proceeding Milestone

Date

Ruling on Preliminary Planning Standards

May 2010

Ruling on Energy Efficiency Assumptions

May 2010

Comments due on Preliminary Scoping Memo

June 4, 2010

Prehearing Conference

June 14, 2010

Draft ED Staff Report on renewables assumptions

June 2010

Comments / Reply and Party Alternative Proposals on DR, renewables, and other non-renewables assumptions

June 2010

Scoping Memo for Track I

July 2010

Deadline for inputs to Track II

November 2010

IOUs file system resource plans

Q1 2011

Testimony, Briefs, and Hearings (If Necessary)

Q2 2011

Proposed Decision

Q3 2011

Decision

Q4 2011

Track II - Preliminary Schedule

Proceeding Milestone

Date

Ruling on Preliminary Planning Standards

May 2010

Comments due on Preliminary Scoping Memo

June 4, 2010

Prehearing Conference

June 14, 2010

Scoping Memo for Track II

To Be Determined

Process:

    · Input Received from Tracks I and III

    · IOU Bundled Plans and Testimony

    · Intervenor Testimony

    · Evidentiary Hearings

    · Post-hearing Briefs

    · Post-hearing Reply Briefs

    · Preparation of the decision on IOU bundled procurement plans.

December 2010 through October 2011

Proposed Decision(s) on IOU-specific Bundled Procurement Plans

November 2011

Track III - Preliminary Schedule

Proceeding Milestone

Date

Comments due on Preliminary Scoping Memo

June 4, 2010

Prehearing Conference

June 14, 2010

Scoping Memo for Track III

To Be Determined

Proposals, Comments, and/or Workshops

June 2010 to October 2011

Deadline for inputs to Track II

November 2010

Assigned Commissioner Rulings or Decisions on Track III Issues and Assumptions

As Appropriate

Each of the issue areas outlined in the Preliminary Scoping Memo will likely require different types and degrees of public participation. Therefore, we delegate further definition of procedure and schedule for each issue area to the assigned Commissioner and ALJ as determined in the Scoping Memo or later ruling. We leave open the possibility that issue areas may be decided upon individually in interim decisions, if necessary. In addition, we authorize the assigned Commissioner and ALJ to organize issues within the proceeding, including moving issues between tracks.

This proceeding will conform to the statutory case management deadline for ratesetting matters set forth in § 1701.5. In particular, it is our intention to resolve all relevant issues within 24 months of the date of the assigned Commissioner's Scoping Memo for each track. In using the authority granted in § 1701.5(b) to set a time longer than 18 months, we consider the number and complexity of the tasks and the need to coordinate with other proceedings.