This decision completes the second of three procedural tracks that were established for Phase 2 of this resource adequacy (RA) proceeding.1 The Phase 2 Scoping Memo identified eight topics for consideration in Track 2, summarizing them as follows:
a. Centralized capacity market, bilateral trading, and alternative market design
b. Registration/tagging for RA capacity
c. Multi-year forward commitment time horizons
d. [Load-serving entity (LSE)] opt-out from cost allocation mechanism (D.06-07-029)
e. Coordination of RA program with [the California Independent System Operator Corporation's (CAISO's) Market Redesign and Technology Update (MRTU)] as necessary
f. Procurement obligations for resource mix and ancillary services
g. Market power mitigation
h. Planning Reserve Margin (Phase 2 Scoping Memo at 17.)
In this decision we examine proposals that focus on topics a, c, and d. Market power mitigation is considered in the context of our evaluation of the other topics, not as a stand-alone issue. We are considering the planning reserve margin (PRM) in a separate proceeding (Rulemaking (R.) 08-04-012). Other topics were, or will be, addressed elsewhere.
Pursuant to the schedule and procedure established by the Phase 2 Scoping Memo and subsequent rulings by the assigned Commissioner and Administrative Law Judge (ALJ), the record for Track 2 was developed through filed proposals, stakeholder meetings and workshops facilitated by the Commission's Energy Division, an Energy Division report on Track 2 issues (Staff Report) prepared in collaboration with the CAISO,2 a supplemental staff report, motions to supplement the record, and pre- and post-workshop comments. The following table summarizes this process:
Development of the Track 2 Record
Initial proposals filed |
March 30, 2007 |
Energy Division-facilitated stakeholder meeting |
April 25, 2007 |
Pre-workshop comments filed |
May 18, 2007 |
Pre-workshop reply comments filed |
July 13, 2007 |
New/updated proposals filed |
August 3, 2007 |
Energy Division-facilitated workshops |
August 15, 20-22, and 27-28, 2007 |
Energy Division Staff Report on Track 2 Issues released |
January 18, 2008 |
Post-workshop comments filed |
February 29, 2008 |
Post-workshop reply comments filed |
March 14, 2008 |
Motions to supplement the record granted by amended Phase 2 Scoping Memo |
June 17, 2008 |
Energy Division-facilitated workshops |
August 22 and 25, 2008 |
Motion to supplement the record granted by ALJ Ruling |
August 6, 2008 |
Supplemental Staff Report issued |
September 17, 2008 |
Comments on supplemental staff report filed |
October 1, 2008 |
Reply comments on supplemental staff report filed |
October 8, 2008 |
As detailed in the following table, which lists the parties and indicates the acronyms used in this decision to identify parties, 31 parties or party coalitions filed a total of 90 documents containing Track 2 proposals and/or comments.
Parties Filing Track 2 Proposals and/or Comments
Filing Party or Parties For party groups, the parties listed below did not, in all cases, participate in each of the filings of the group |
Acronym or Title for Party or Party Group |
Initial Proposals 3/30/07 |
Pre-workshop comments 5/18/07 |
Pre-workshop reply comments 7/13/07 |
New/ updated proposals 8/03/07 |
Post-workshop comments 2/29/08 |
Post-workshop reply comments 3/14/08 |
Supp. comments 10/01/08 |
Supp. reply comments 10/08/08 |
Aglet Consumer Alliance |
Aglet |
X |
X |
X |
X |
X |
X |
X |
X |
Alliance for Retail Energy Markets |
AReM |
X |
X |
X |
X |
X |
X |
||
Bilateral Trading Group (APS Energy Services, California Electricity Oversight Board, California Large Energy Consumers Association, California Manufacturers & Technology Association, City and County of San Francisco, Shell Energy North America (US), L.P., DRA, Energy Users Forum, J. Aron & Company, TURN, and Direct Energy, LLC.) |
BTG |
X |
X |
X |
X |
X |
X |
||
Cogeneration Association of California |
CAC |
X |
|||||||
California Independent System Operator Corporation |
CAISO |
X |
X |
X |
X |
X | |||
Calpine Corporation |
Calpine |
X |
X |
X |
X |
X | |||
California Forward Capacity Market Advocates (FPL Energy, NRG Energy, Reliant Energy, SCE, and SDG&E |
CFCMA |
X |
X |
X |
X |
X |
X |
X | |
Capacity Market Advocacy Group (Commerce Energy, Constellation Energy Commodities Group, Inc, Edison Mission Energy, FPL Energy Project Management, Mirant Corporation, Reliant Energy, Inc, SCE, and SDG&E) |
CMAG |
X |
|||||||
California Municipal Utilities Association |
CMUA |
X |
|||||||
Complete Energy Holdings LLC |
Complete Energy |
X |
X | ||||||
Constellation Energy Commodities Group, Inc., Constellation NewEnergy, Inc., and Constellation Generation Group, LLC |
Constellation |
X |
X |
X |
X |
X |
X |
X |
|
Coalition of California Utility Employees |
CUE |
X |
X |
X |
|||||
Division of Ratepayer Advocates |
DRA |
X |
Filing Party or Parties For party groups, the parties listed below did not, in all cases, participate in each of the filings of the group |
Acronym or Title for Party or Party Group |
Initial Proposals 3/30/07 |
Pre-workshop comments 5/18/07 |
Pre-workshop reply comments 7/13/07 |
New/ updated proposals 8/03/07 |
Post-workshop comments 2/29/08 |
Post-workshop reply comments 3/14/08 |
Supp. comments 10/01/08 |
Supp. reply comments 10/08/08 |
Dynegy Morro Bay LLC, Dynegy Moss Landing LLC, Dynegy South Bay, LLC, and Dynegy Oakland LLC |
Dynegy |
X |
X |
X | |||||
Electricity Consumers Resource Council |
ELCON |
X |
|||||||
Ice Energy, Inc. |
Ice Energy |
X |
|||||||
Independent Energy Producers Association |
IEP |
X |
X |
X |
X |
X |
|||
Constellation; SDG&E; AES Southland, LLC; Calpine; CFCMA; Complete Energy; Dynegy; IEP; Mirant; and Sempra Global |
N/A |
X |
|||||||
AReM; AES Southland, LLC; CFCMA; Complete Energy; Constellation; Dynegy; IEP; LS Power Associates, LP; Mirant; and Sempra Global |
N/A |
X | |||||||
Kinder Morgan Energy Partners, L.P. |
Kinder Morgan |
X |
|||||||
Mirant California LLC, Mirant Delta LLC, and Mirant Potrero LLC |
Mirant |
X |
X |
X |
X | ||||
Morgan Stanley Capital Group, Inc. |
Morgan Stanley |
X |
|||||||
NRG Energy, Inc. |
NRG |
X |
X |
||||||
Pacific Gas and Electric Company |
PG&E |
X |
X |
X |
X |
X |
X |
X |
X |
PPM Energy |
PPM Energy |
X |
|||||||
Reliant Energy, Inc. |
Reliant/RRI |
X |
X |
||||||
Southern California Edison Company |
SCE |
X |
X |
||||||
San Diego Gas & Electric Company |
SDG&E |
X |
|||||||
Sempra Global |
Sempra Global |
X |
|||||||
The Utility Reform Network |
TURN |
X |
|||||||
Western Power Trading Forum |
WPTF |
X |
1 See Assigned Commissioner's Ruling and Scoping Memo for Phase 2 (Phase 2 Scoping Memo), issued December 22, 2006. Track 1 addressed RA program implementation for the 2008 compliance year and was concluded by Decision (D.) 07-06-029. Track 3 addresses how the RA program will be extended to small and multi-jurisdictional LSEs. On June 17, 2008 the Assigned Commissioner issued an amended scoping memo for Phase 2 (Amended Phase 2 Scoping Memo). The statutory deadline for resolving the proceeding was extended by the Commission in several decisions.
2 Although the CAISO collaborated with our Energy Division staff in the preparation of the Staff Report, the CAISO maintained its party status and did not participate in the Commissions deliberations.