4. RA Program Modifications

4.1. Standard Capacity Product

4.1.1. Continue the Exemption for Demand Response

4.1.2. No Change to Replacement Obligation

· Include "delivery requirements and penalties and replacement obligations in the [CAISO] tariff" so that "the CAISO then becomes responsible for enforcing delivery rather than each individual LSE, i.e., the CAISO assesses penalties and procures replacement capacity in the event that a supplier is unable to deliver RA capacity that has been sold and pledged for RA compliance."10 We refer to this approach as "tariff-based replacement."

· "[A]dd a Planned Outage Adder (POA) to each LSE's RA Requirement. The POA would account for planned outages that the [CAISO] has historically approved at-the-time-of the monthly supply plan submittal."11

4.2. Qualifying Capacity

4.2.1. Resource Classification Proposals

4.2.2. Counting Rules for Non-Dispatchable Resources
(QC Report - Section 10)

4.2.3. No Change to the Counting of Distribution Resources

"TURN fully agrees with the Energy Division's suggestion that "all resources should either be counted [as a reduction] in the load forecast or as a resource, but it is important to avoid double counting." Indeed, this seems to reflect simple common sense. The problem may therefore be more of an implementation question than a policy issue, one that will require some coordination between the CEC's load forecasting process and the CPUC's counting rules for distributed resources."

"SDG&E therefore recommends that each utility include in their distribution-level interconnection studies an assessment of whether the interconnecting generators should be treated as fully deliverable for Resource Adequacy purposes. This determination would establish a rebuttable presumption that the subject resources interconnected to the distribution system on the non-customer side of the meter should be certified as RA resources. If the CAISO believes the utility's determination creates a reliability concern, it can conduct the appropriate deliverability analysis for the amount of generation capacity that reaches the transmission system and present the results to the Commission to rebut the presumption in favor of deliverability."

4.2.4. Eliminate Forced Outages and Derates from Data to Calculate QC and Possibly Include Resources Using Historical Data in the SCP

" . . . modify its RA counting rules either to: (1) eliminate forced outage and de-rate hours from its calculation of the QC of RA resources, or (2) use proxy energy output values for those hours. The ISO believes that the second option could be implemented by adopting an approach similar to the methodology the CPUC has previously approved to account for scheduled outages in the QC calculation for these types of resources."33

"Given the disparate RA counting rules, it is simply not possible to fashion an equitable and workable standard availability incentive for all types of resources. Given the strong existing incentives for intermittent and CHP resources to maintain high availabilities, CalWEA and the CCC submit that it is not worthwhile to try to "destandardize" the SCP availability incentive simply so that it can be applied to these resources. As a result, it is reasonable to retain the exemption for these resources."36

4.2.5. Demand Response

4.2.5.1. Counting Proxy Demand Resource and
Supply-Side DR

"If California is going to treat demand resources comparably to generation resources, the demand response provider, representing the resource, should be able to register the capacity associated with the resource that is participating through the CAISO. The determination of whether or not the registered capacity is capable of performing at that level will be based upon the actual performance of the resource or, if not called within a commitment period, testing. If the resource does not perform to the capacity level specified, the resource will face penalties."43

4.2.5.2. Grossing-Up DR for Avoided Line Losses

DR RA Value = 1.15 * DR Load Impact * (1.00/(1.00 - T&D Line Loss Rate)) where, T&D Line Loss Rate = 3% + IOU-specific Distribution Loss Factors.

4.2.5.3. Continued Full Year Local RA Credit for Air Conditioner Cycling (AC Cycling) Programs

"While the AC cycling programs may not be available during the winter, the associated AC load also is not there in the off-peak months, which should translate into a lower local RA requirement. But the CAISO does not believe that it is practical to develop monthly or seasonal local RA obligations, because of the extensive amount of work that would entail. TURN submits that it makes little sense to require LSEs to acquire replacement local RA capacity in the off-peak months because of the absence of AC cycling when we don't even know what the real need for local RA capacity really is in those same off-peak months."

"For ease of administration, however, SDG&E urges the Commission to refrain from implementing the proposed change in hours until the 2012 RA compliance year. As noted in the January workshop, the proposed hours do not align with most current IOU demand response program designs. The currently approved IOU demand response program cycle runs from 2009 through 2011. Beginning in early 2011, IOUs will begin filing applications for the 2012 - 2014 demand response program cycle. SDG&E believes that the proposed change in hours could be incorporated into the 2012 - 2014 applications, and if approved, implemented in the 2012 programs."63

"TURN believes that this Commission should endorse the principal of employing the revised hours at this time, so that everyone will be on notice that program changes may need to be considered in the next round of DR program applications. Since those applications are likely to be filed in early 2011, this year's RA decision would the appropriate place to establish such policy guidance, so that it can be taken into account in the upcoming utility applications."64

· The proposed change in measurement hours will be implemented for compliance year 2012, but not 2011. Beginning in 2012, the measurement hours shall be the hours shown in Table 2 of the QC Report:

· To ease the transition to the new measurement hours,
DR program operators may request that specific DR programs continue to be measured using the existing hours (2 p.m. to
6 p.m.) during 2012, or potentially future years, if they have a fixed operational period set by a Commission decision. In order for DR program operators to request use of the 2 p.m. to 6 p.m. measurement hours, the operator shall file a proposal to do so in Phase 2 of this proceeding that identifies, at a minimum, the specific program(s), it's (their) operational period(s), a specific citation from a Commission decision setting this operational period, and when the operational period may be changed. To be clear, we anticipate that most or all DR programs that will be evaluated in the 2012-2014 DR program applications will not use this process. Only those programs whose operational periods cannot be changed in those applications or another venue in time for 2012 implementation (for instance due to previously adopted rate design) should use this process.

4.3. Implementation Proposals

4.3.1. Resource Adequacy Penalties

 

Small Procurement Deficiency

System Procurement Deficiency

Local Procurement Deficiency

Replaced within five business days of the date of notification

$1,500/incident

$9.99/kW-month

$3.33/kW-month

 

Small Procurement Deficiency

System Procurement
Deficiency

Local Procurement
Deficiency

Replaced within

five business days of the

date of notification

$1,500/incident

$3.33/kW-month

$5.00/kW-month

Replaced after five

business days of the date

of notification

$3,000/incident

$6.66/kW-month

$9.99/kW-month

 

Small Procurement Deficiency

System Procurement Deficiency

Local Procurement
Deficiency

Replaced within

10 business days of the

Date of notification

$1,500 first incident

in calendar year;

$3,000 for each

incident thereafter in

a calendar year

$5.00/kW-month

$1.70/kW-month

Replaced after

10 business days from the date of notification or not

Replaced

LSE pays the

applicable System or

local RA penalty for

the deficiency

$9.99/kW-month

$3.33/kW-month

(1) a demonstration that the LSE reasonably and in good faith solicited bids for its RAR capacity needs along with accompanying information about the terms and conditions of the Request for Offer or other form of solicitation; and

(2) a demonstration that despite having actively pursued all commercially reasonable efforts to acquire the resources needed to meet the LSE's local procurement obligation, it either:

    (a) received no bids; or

    (b) received no bids for an unbundled RA capacity contract of under $40 per kW-year or for a bundled capacity and energy product of under $73 per kW-year; or

    (c) received bids below these thresholds but such bids included what the LSE believes are unreasonable terms and/or conditions, in which case the waiver request must demonstrate why such an LSE's waiver request that meets these requirements is a necessary but not a sufficient condition for the grant of such waiver. The Commission will also consider other information brought to its attention regarding the reasonableness of the waiver request"72

"LSE's may request a waiver up to 10 days prior to the year-ahead local RA compliance filing or the True-up Filing for local RA, as applicable. The Energy Division must rule on the request on or before the date the applicable Local RA filing is due. If the Energy Division rejects the waiver request, the LSE will have 15 days from the date of notification of the rejection to procure additional capacity, no penalty will apply unless the LSE fails to cure the deficiency within the 15 days of notification of rejection. The Commission should state in a decision that, barring an overriding demonstrable circumstance, satisfaction of the requirements in
D.06-06-064 is a sufficient condition to grant a waiver request."
73

4.3.2. Discussion

 

Small Procurement Deficiency

System Procurement Deficiency

Local Procurement
Deficiency

Replaced within

five business days of the date of notification

$1,500 first incident

in calendar year;

$3,000 for each

incident thereafter in

a calendar year

$3.33/kW-month

$3.33/kW-month

Replaced after

five business days

from the date of

notification or

not replaced

LSE pays the

applicable System or

Local RA penalty for

the deficiency

$6.66/kW-month

$3.33/kW-month

4.3.3. Load forecast timeline

4.3.4. RA Record Retention Policy

4.3.5. Local Area Substitution

9 We adopted this rule in D.06-07-031; see p. 10 of that decision for details.

10 Calpine Proposals at 5-6.

11 SCE March 5, 2010 Proposal at 1.

12 SCE March 5, 2010 Proposal at 1.

13 SCE March 5, 2010 Proposal at 1.

14 SCE March 5, 2010 Proposal at 1.

15 SCE March 5, 2010 Proposal at 1.

16 SCE March 5, 2010 Proposal at 1.

17 SCE March 5, 2010 Proposal at 1.

18 CAISO Revised Draft Final Proposal at 7; http://www.caiso.com/2771/27717a905e6a0.pdf.

19 See: CalWEA/CCC Comments pg 11; WPTF Comments at 3-4; Calpine Comments
at 10; Dynegy Comments at 7; and Mirant Comments at 5-6.

20 Calpine Comments at 10.

21 Dynegy Comments at 7.

22 SDG&E Comments at 7.

23 AReM Reply Comments at 4.

24 AReM Reply Comments at 4.

25 DRA Comments at 2; CAISO Comments at. 2; CLECA Comments at 5; SDG&E Comments at 5; CAC Reply Comments at. 10; and PG&E comments at 10.

26 TURN Reply Comments at 3.

27 SDG&E Reply Comments at 1.

28 For clarification, we use the term "QC Report" to refer to the Energy Division document used in workshops, while the "QC Methodology Manual" is what is adopted today.

29 See: CAISO Comments at. 21, Calpine Comments at. 4-6, Dynegy Comments at 14, PG&E Comments at 4, and SCE Comments at 21-22.

30 Calpine Comments at 6.

31 CAC proposals at 9.

32 CAISO Comments at 17-18.

33 CAISO Proposals at 5.

34 CalWEA/CCC Comments at 2-3.

35 CalWEA/CCC Comments at 6.

36 CalWEA/CCC Comments at 10.

37 Dynegy Reply Comments at 5.

38 CalWEA/CCC Comments at 7-8.

39 PG&E Comments at 5; SCE Comments at 8; SDG&E Comments at 8.

40 See, e.g. D.09-06-028 at 42; D.06-07-031 at 4; D.05-10-042 at 26; D.04-10-035 at 42.

41 EnerNOC Proposals at 7.

42 Ibid.

43 EnerNOC Comments at 7-8.

44 AReM Comments at 5-6; TURN Comments at 4; and NAPP Reply Comments at 4-5.

45 TURN Comments at 4.

46 CLECA Comments at 4; Dynegy Comments at 13; PG&E Comments at 4; SCE Comments at 23-26; and DRA Reply Comments at 9.

47 Dynegy Comments at 13.

48 SCE Reply Comments at 11.

49 EnerNOC Reply Comments at 5.

50 EnerNOC Reply Comments at 5-6.

51 DRA Comments at 3; TURN Comments at 3-4; SDG&E Comments at 9-10.

52 SCE Proposals at 9 and SCE Comments at 18.

53 CAISO Comments at 19.

54 CAISO Proposals at 10.

55 CAISO Comments at 11.

56 Dynegy Comments at 12.

57 DRA Comments at 3, TURN Comments at 4-5, SDG&E Reply Comments at 7, PG&E Reply Comments at 1.

58 TURN Comments at 4-5.

59 QC Report at 25.

60 DRA Comments at 3.

61 February 18, 2010 Workshop Summary at 5.

62 PG&E Comments at 2.

63 SDG&E Comments at 12.

64 TURN Comments at 3.

65 SCE Comments at 27 and SCE Reply Comments at 12.

66 D.09-08-028 at 26.

67 HE indicates "hour ending," or the 60 minutes that end at the numbered hour, in
24-hour time. For example, HE17 indicates the 60 minutes beginning at 16:00
(i.e. 4:00 p.m.) and ending at 16:59.

68 At Conclusions of Law 25 and 26.

69 At 68-69.

70 At 94 and Conclusion of Law 21.

71 SCE Comments on Phase 1 issues at 12.

72 D.06-06-064 at 72-73.

73 Alternative Proposal to Modify Current RA Penalty Structure at 6.

74 Calpine comments at 3.

75 D.06-06-064 at 68-69.

76 CAISO Comment on Phase 1 issues at 15.

77 SCE comments on Phase 1 at 11.

Previous PageTop Of PageNext PageGo To First Page