During the record period, SCE operated and maintained four peaker generating plants (peakers), each consisting of a single generator of 49 MW rated capacity. SCE has provided testimony to demonstrate that its peaker facilities are operated in a prudent manner during the Record Period. In its testimony, DRA indicates that the forced outages that occurred at SCE's peakers were not unreasonable.
Based on the testimonies of SCE and DRA, we conclude that the SCE peakers were operated reasonably during the Record Period.