The proposed decision (PD) of the Administrative Law Judge (ALJ) in this matter was mailed to the parties in accordance with § 311, and comments were allowed in accordance with Rule 14.3. Comments were filed on May 10, 2010, by AReM/CLECA, Calpine, DRA, GWF, IEP, PG&E, and TURN. Reply comments were filed on May 17, 2010, by AReM/CLECA, Calpine, CURE, DRA, GWF, PG&E, and TURN. These comments have been reflected, as appropriate, in the final decision adopted by the Commission.
On July 9, 2010, Contra Costa Generating Station, LLC filed a motion for party status. This motion is denied because there are no further formal opportunities for parties to participate in this application before the Commission acts on the proposed decision.