Environmental Review and CEQA Compliance

The California Environmental Quality Act of 1970 (CEQA, Public Resources Code Section 21000 et seq.) applies to discretionary projects to be carried out or approved by public agencies. A basic purpose of CEQA is to inform governmental decision-makers and the public about potential, significant environmental effects of the proposed activities. Since the project is subject to CEQA and the Commission must issue a discretionary decision in order for the project to proceed (i.e., the Commission has the exclusive authority to approve the project pursuant to Section 1202 of the Public Utilities Code), the Commission must consider the environmental consequences of the project by acting as either a lead or responsible agency under CEQA.

The lead agency is either the public agency that carries out the project,2 or the one with the greatest responsibility for supervising or approving the project as a whole.3 Here, the County is the lead agency for this project because the project is being constructed by them, and is subject to their review and approval, and the Commission is a responsible agency because it has jurisdiction to issue a permit for the project. As a responsible agency under CEQA, the Commission must consider the lead agency's environmental documents and findings before acting on or approving this project.4

In issuing D.07-07-003, the Commission found the County's Notice of Exemption adequate and the project exempt from CEQA. The County offered evidence to show that on March 17, 2006, it filed a Notice of Exemption for work at the proposed new crossing. The notice concludes that construction of a pedestrian walkway is classified as a minor alteration of an existing facility involving negligible or no expansion of use as described in State CEQA Guidelines Section 15301(c) and which will not result in a significant effect on the environment, and is therefore categorically exempt from CEQA review under Pub. Res. Code § 21084 and CEQA Guideline §15301(c). The exemption was filed with the County Clerk and was available for public review for 30 days.

The project for the new pedestrian at-grade crossing has not changed from the original design. Because the application requests modification of an existing decision for a project which has not been altered, we find no reason to disturb those original findings. We find that no further environmental review by the Commission is necessary.

Filing Requirements and Staff Recommendation

The application is in compliance with the Commission's filing requirements, including Rule 3.7 of Rules of Practice and Procedure, which relates to the construction of a public highway across a railroad.

RCES recommends that the requested time extension to complete construction of the subject crossing and fulfill the remaining requirements of the settlement agreement laid out in D.07-07-003 be approved for at least an additional two years. Staff recommends an additional 6 month period to account for potential unforeseen delays, and suggests extending the authorization period to January 13, 2012.

Categorization and Need for Hearings

In Resolution ALJ 176-3262, dated October 14, 2010, and published in the Commission Daily Calendar on October 15, 2010, the Commission preliminarily categorized this application as ratesetting, and preliminarily determined that hearings were not necessary. No protests have been received. Given these developments, it is not necessary to disturb the preliminary determinations made in Resolution ALJ 176-3262.

Waiver of Comment Period

This request for an extension of the authorization period is an uncontested matter in which the decision grants the relief requested. Accordingly, pursuant to Section 311(g)(2) of the Public Utilities Code and Rule 14.6(c)(2) of the Commission's Rules of Practice and Procedure, the otherwise applicable 30-day period for public review and comment is waived.

Assignment of Proceeding

Richard Clark is the assigned Examiner in this proceeding.

Findings of Fact

1. Notice of the application was published in the Commission's Daily Calendar on October 15, 2010. There are no unresolved matters or protests. A public hearing is not necessary.

2. The County requests that the authority granted under Public Utilities Code Sections 1201-1205 by Decision 07-07-003, to construct a new at-grade pedestrian crossing over the track and right-of-way of UPRR in San Miguel, San Luis Obispo County be extended until at least July 13, 2011.

3. As evidenced by Exhibit 2 to the County's application, UPRR does not object to the requested time extension.

4. The County will be the lead agency for design, funding, and construction of the pedestrian crossing.

5. The County will take ownership and maintenance responsibilities after the pedestrian crossing is constructed.

6. The County is the lead agency for this project under CEQA.

7. The County adopted the Notice of Exemption and has determined the project to be categorically exempt from further environmental review under CEQA.

8. The project's environmental documentation has not changed from the documentation provided at the public hearings.

Conclusions of Law

1. The County's determination of the project to be categorically exempt and the Notice of Exemption as the documentation required by CEQA for the project are adequate for our decision-making purposes.

2. The application is uncontested and a public hearing is not necessary.

3. The application should be granted as set forth in the following order.

ORDER

IT IS ORDERED that:

1. The authority granted to the County of San Luis Obispo by Commission Decision 07-07-003 to construct an at-grade pedestrian crossing to be identified as CPUC Crossing No. 001E-203.35-D, over the track and right-of-way of the Union Pacific Railroad Company in the town of San Miguel, County of Santa Clara is extended for a period of 30 months from the original expiration of July 12, 2009, to January 12, 2012.

2. The County of San Luis Obispo shall notify the California Public Utilities Commission's Consumer Protection and Safety Division - Rail Crossing Engineering Section at least five (5) business days prior to opening the crossing. Notification should be made to rces@cpuc.ca.gov .

3. Within 30 days after completion of the work under this order, the County of San Luis Obispo shall notify the Rail Crossings Engineering Section in writing, by submitting a completed Commission Standard Form G (Report of Changes at Highway Grade Crossings and Separations), of the completion of the authorized work. Form G requirements and forms can be obtained at the California Public Utilities Commission web site Form G page at http://www.cpuc.ca.gov/formg . This report may be submitted electronically to rces@cpuc.ca.gov as outlined on the web page.

4. Within 30 days after completion of the work under this order, Union Pacific Railroad shall notify the Federal Railroad Administration of the existence of the crossing by submitting a U.S.DOT CROSSING INVENTORY FORM, form FRA F6180.71. A copy is to be provided concurrently to the Commission's Consumer Protection and Safety Division - Rail Crossings Engineering Section. This copy of the form may be submitted electronically to rces@cpuc.ca.gov .

5. The County of San Luis Obispo shall comply with all applicable rules, including the California Public Utilities Commission General Orders and the California Manual on Uniform Traffic Control Devices.

6. This authorization shall expire if not exercised by January 12, 2012, unless time is extended or if the above conditions are not satisfied. The California Public Utilities Commission may revoke or modify this authorization if public convenience, necessity, or safety so require.

7. Any further request for extension of the authorization period must be submitted to the Commission at least 30 days before the expiration of that period. A copy of the request must be sent to all interested parties.

8. The application is granted as set forth above.

9. Application 10-10-009 is closed.

Date April 14, 2011, at San Francisco, California.

2 CEQA Guidelines (Title 14 of the California Code of Regulations), Section 15051(a).

3 CEQA Guidelines (Title 14 of the California Code of Regulations), Section 15051(b).

4 CEQA Guidelines, Sections 15050(b) and 15096.

Previous PageTop Of PageGo To First Page