Rate Element

Adopted Rate

SFV Reservation Charge ($/dth/day)

$0.11269

MFV Reservation Charge ($/dth/day)

$0.09015

MFV Volumetric Charge ($/dth)

$0.02653

Interruptible Volumetric Charge ($/dth)

$0.11269

21 The JRR is Exhibit JRR-1, and is sponsored by SDG&E/SoCalGas, CMTA, DRA, RES, SCGC, and TURN.

22 This adopts Recommendation No. 1 of Exhibit No. JRR-1.

23 These are Recommendations Nos. 4 and 4.a of Exhibit No. JRR-1.

24 D.09-11-006, Appendix A (BCAP Phase II Settlement Agreement), Section II.B.2.C.

25 Some customers are served directly from the backbone transmission system without using local transmission lines.

26 SDG&E/SoCalGas determine the portion of the backbone transmission costs that should be assigned to local transmission using "cold year annual average throughput" (2,651 MMcfd) and the percentage of the utilities' 1-in-10 year peak day end-use demand served directly from the backbone transmission system without using local transmission lines (35 percent).

27 D.04-09-022 authorized SDG&E and SoCalGas to establish Otay Mesa as a joint receipt point into their systems. D.06-04-033 determined that the function of the SDG&E transmission system and the Rainbow Corridor would change from a local transmission function to backbone transmission function when SDG&E/SoCalGas began transporting regasified liquefied natural gas from the Otay Mesa receipt point into SDG&E/SoCalGas service territory. No party disputes that gas has been received into the SDG&E/SoCalGas system at the Otay Mesa receipt point, but some argue that not enough gas has been received to justify treating any portion of the SDG&E transmission system as "backbone."

28 It is unreasonable to reclassify a pipeline based on the volume of gas received at a receipt point because a pipeline would constantly change classification with the daily ebbs and flows of gas through a receipt point, and such an ongoing reclassification of pipelines would make it impossible to determine the cost of the backbone transmission system.

29 SDG&E/SoCalGas initially recommended a backbone transmission system revenue requirement of $119.8 million, DRA and TURN initially recommended a revenue requirement of $157.5 million, and SCGC initially recommended a revenue requirement of $80.0 million. CCC, IP, and Watson recommend a revenue requirement of
$94.6 million.

30 This adopts Recommendation No. 2.a of Exhibit No. JRR-1.

31 SDG&E/SoCalGas calculate the reservation charge for firm backbone capacity by using the average daily firm contract demand quantity (CDQ) during the 15-month period. SDG&E/SoCalGas convert this volume to Dth by applying a British Thermal Unit conversion factor (i.e., multiplying the CDQ by 1.0302), multiplying the result by 365 days to derive the annual capacity in "thousands of dekatherms" (MDth), and dividing this result by 1000 to derive the annual capacity in Dths (i.e., Dth/year). SDG&E/SoCalGas then divide the annual backbone transmission revenue requirement by the derived Dth/year to determine the backbone transportation rate per Dth.

32 This adopts Recommendation No. 2.a.i of Exhibit No. JRR-1.

33 "Billing determinant" refers to the denominator by which costs are divided to determine a rate.

34 Exhibit No. JRR-1, Recommendation No. 2.a.ii.

35 See Exhibit SD/SCG-8 (Average Daily Total of the Firm Contracted Capacity and Interruptible Utilization of Access Rights 10/1/09 - 9/30/10).

36 Elasticity of demand (demand elasticity) quantifies the extent to which demand for a product will decline in response to a price increase, and rise in response to a price decrease (i.e., it is the percentage change in quantity demanded in response to a one percent change in price). Demand elasticity is usually quantified by dividing the percentage change in the quantity of the product purchased by the percentage change in the price of the product.

37 SDG&E/SoCalGas initially proposed to base their proposed reservation charge on firm contract demand volumes, excluding average interruptible usage volumes, because SDG&E/SoCalGas assumed that usage would decrease as a result of increased rates. See Exhibit SD/SCG-3 at 4:7 - 10. No party raised concerns about this approach to accounting for demand elasticity, and some parties' proposals implicitly make the same assumption. See SCGC-1 at 17:15 - 22 and Table 4 at 18. See also TR 173:21 - 174:2.

38 The JRR's assumed capacity of 3,100 Mdth/day is approximately eleven percent lower than the actual contracted firm capacity of 3,489 Mdth/day for the period ending September 30, 2010, reported in Exhibit SD/SCG-8.

39 This adopts Recommendation No. 2.b of Exhibit No. JRR-1.

40 The variable/usage component of the MFV rate includes variable O&M costs, rate of return, and taxes related to the backbone transmission system.

41 This adopts Recommendation No. 2.b.i of Exhibit No. JRR-1.

42 Exhibit No. JRR-1, Recommendations Nos. 2.b.ii and 2.b.iii (Note: Recommendation No. 2.b.iii is mislabeled as "2.b.ii").

43 This adopts Recommendation No. 2.b of Exhibit No. JRR-1.

44 CCC, IP, and Watson oppose this recommendation. CCC and Watson recommend a 78/22 percent split. IP recommends an 81/19 percent split, if its proposed revenue requirement is adopted. Alternatively, IP recommends an 65/35 percent split, if the Commission adopts a revenue requirement that is higher than that proposed by IP.

45 This adopts Recommendation No. 2.c of Exhibit No. JRR-1.

46 IP and Watson state that the amount of FAR capacity sold substantially exceeds the amount of capacity actually scheduled and used. They argue that using the amount of capacity sold to compute the interruptible rate will result in a rate that is too low to recover the revenue requirement if all shippers take interruptible service.

47 This adopts Recommendation No. 14 of Exhibit No. JRO-1. In connection with this recommendation, as discussed elsewhere in this decision, JRO Recommendation
No. 13.d recommends approval of the proposal to modify the Integrated Transmission Balancing Accounting (ITBA) account so as not to record transmission fuel costs.

48 This adopts Recommendation No. 3 of Exhibit No. JRR-1.

49 The actual rates charged beginning October 1, 2011 will reflect the balance in the BTBA as of July 31, 2011. As a result, the actual rates will differ from those listed here.

50 The interim rate adopted by D.06-03-021 was not cost-based but was initially set at $0.05/dth until a cost study identifying backbone transmission costs was completed.

Previous PageTop Of PageNext PageGo To First Page