As a compromise among their respective litigation positions, and subject to the recitals and reservations set forth in this Settlement Agreement, the Settling Parties agree that:

· With respect to system resource need and the integration of intermittent renewable resources into the CAISO grid, the Settling Parties encourage the Commission, in conjunction with the CAISO's ongoing work on this subject, to further examine this issue expeditiously in the next Long-Term Procurement Plan (LTPP) cycle or in an extension of the current LTPP cycle.

· All references to a potential "need to add capacity for renewable integration purposes" shall be interpreted within the context of the CAISO process which considers alternatives as further described in Section III.C below to determine the type of resources (including existing units) available to meet any defined needs. There is no presumption that any Phase 1 "need" requires the addition of new gas-fired generation resources above and beyond those needed to meet the current planning reserve margin.

· As requested by the Commission, the CAISO developed a methodology for assessing renewable integration resource needs (the "CAISO methodology"), and applied this methodology with the assistance of the IOUs to assess the need for flexible capacity for the four CPUC-Required Scenarios and one other CPUC scenario analyzed by the CAISO. The results show no need to add capacity for renewable integration purposes above the capacity available in the four scenarios for the planning period addressed in this LTPP cycle (2012-2020). The additional scenario studied by the CAISO did show need.

· The IOUs applied the same CAISO methodology for the IOU Common Scenarios using different assumptions from those used in the CPUC-Required Scenarios. The results of the IOUs' modeling show need for additional capacity for renewable integration purposes under certain circumstances.

· The resource planning analyses presented in this proceeding do not conclusively demonstrate whether or not there is need to add capacity for renewable integration purposes through the year 2020, the period to be addressed during the current LTPP cycle. The Settling Parties have differing views on the input assumptions used in, and conclusions to be drawn from the modeling. There is general agreement that further analysis is needed before any renewable integration resource need determination is made. [...] (Settlement Agreement at 4-5.)

TURN has been monitoring the development of the CAISO methodology for assessing renewable integration resource needs and believes that the model cannot be relied upon to authorize any additional procurement at this time. (The Utility Reform Network (TURN) Opening Brief at 1.)

In the opinion of the GPI, the overwhelming conclusion of the analyses presented in Testimony by the CAISO and the utilities is that it makes little difference which renewables development trajectory is followed. The costs are all about the same, the environmental improvements are all about the same, and despite the fact that promising new technologies for improving grid operations are left out of the analysis, there is still no identified need for new fossil-fired resources for purposes of renewables integration in any of the PUC-defined scenarios. (Green Power Opening Brief at 15-16.)

Regarding Track I, CBE is a party to the settlement agreement submitted on August 3, 2011. CBE recommends the Commission approve the proposed settlement. In so doing, CBE requests that the Commission specifically find that the evidence presented in this proceeding does not establish a need for new generation to integrate renewables. CBE further requests that the Commission specifically find that neither Pacific Gas and Electric ("PG&E) nor Southern California Edison ("SCE") have requested or established a need for new generation to meet local area need. (Communities for a Better Environment (CBE) Opening Brief at 2.)

[E]ven if system-wide studies do not identify a need for additional resources on a statewide basis, there may nevertheless still be a need for new resources to meet local resource adequacy criteria. (Id. at 5.)

Current and expected wholesale market conditions do not provide uncontracted existing generation resources with reasonable opportunities to secure sufficient and stable revenue streams to recover going forward costs, including maintenance necessary to ensure availability in the future. As a result, if a procurement mechanism is not adopted in the near term to address this situation, economic retirements should be expected. (Calpine Opening Brief at 3.)

Q So you don't know whether there are any other uncontracted combined cycle units outside of Calpine's fleet?

A I strongly suspect there are, but I don't know that for a fact. (Calpine witness Barmack, Transcript vol. 6 at 865-866.)

Q Dr. Barmack, what units other than the Calpine units do you believe are at risk of shutting down?

A It would be purely speculation on my part, but I'm aware of other combined cycles that were built around the same time as many of our units... I'm not aware of whether those units are contracted or not. (Id. at 888.)

Q So Calpine hasn't provided any information about the cost of operating the existing units in its combined cycle fleet to the Commission in this proceeding, has it?

A No. We haven't provided information about the specific economics of our units. (Id. at 851.)

During cross-examination, Calpine witness Barmack acknowledged that there are significant regulatory limitations on Calpine's ability to retire a power plant. As Dr. Barmack acknowledged, under the Commission's General Order ("GO") 167, Calpine is obligated to maintain its generating units in California in readiness for service unless the Commission, after consultation with the CAISO, affirmatively declares that the units are unneeded during a specified period of time. Moreover, under GO 167, Calpine is obligated to notify the Commission and the CAISO in writing at least 90 day in advance of any planned change in the long term status of any Calpine unit in California. Under the CAISO's tariff, the CAISO has the authority to issue a "risk of retirement" designation to keep a resource in operation that is otherwise at risk of retirement during the current "resource adequacy" year if the CAISO believes the resource will be needed for reliability by the end of the following calendar year. Thus, a number of regulatory protections are in place to assure that Calpine's units, if needed for reliability in California, will remain on-line and operational. (PG&E Opening Brief at 13-14.)

Even if the short-term operating economics are unfavorable, Woodruff explains that Calpine has a variety of options including asset sales or temporary shutdown. The notion that Calpine would physically dismantle these units, which is the basis of their request, is simply not credible. (Id. at 5.)

7 Motion For Expedited Suspension Of Track 1 Schedule, And For Approval Of Settlement Agreement Between And Among Pacific Gas And Electric Company, Southern California Edison Company, San Diego Gas & Electric Company, The Division Of Ratepayer Advocates, The Utility Reform Network, Green Power Institute, California Large Energy Consumers Association, The California Independent System Operator, The California Wind Energy Association, The California Cogeneration Council, The Sierra Club, Communities For A Better Environment, Pacific Environment, Cogeneration Association Of California, Energy Producers And Users Coalition, Calpine Corporation, Jack Ellis, Genon California North LLC, The Center For Energy Efficiency And Renewable Technologies, The Natural Resource Defense Council, NRG Energy, Inc., The Vote Solar Initiative, And The Western Power Trading Forum.

8 Rule 12.1(d) states: "The Commission will not approve settlements, whether contested or uncontested, unless the stipulation or settlement is reasonable in light of the whole record, consistent with law, and in the public interest."

9 While the focus of this proceeding extends out to 2020, it is important to note that the record similarly does not support a finding of need for additional generation beyond 2020. Accordingly, it is also reasonable to defer procurement of generation for any estimated need after 2020.

10 We note that Calpine filed a notice with the Commission under GO 167 on 11/22/11, stating that it intended to retire its Sutter Energy Center generation plant in 2012. Draft Resolution E-4471 orders Calpine not to retire the Sutter plant. http://docs.cpuc.ca.gov/word_pdf/COMMENT_RESOLUTION/157581.pdf.

Previous PageTop Of PageNext PageGo To First Page