ALJ/HSY/acr Date of Issuance 4/26/2012

Decision 12-04-022 April 19, 2012

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

In The Matter of the Application of SAN DIEGO GAS & ELECTRIC COMPANY (U902E) for a Permit to Construct Electrical Facilities With Voltages Between 50 kV and 200 kV and New Substations With High Side Voltages Exceeding 50 kV: The East County Substation Project.

Application 09-08-003

(Filed August 10, 2009)

Allen K. Trial for San Diego Gas & Electric Company, Applicant.

Jeanne B. Armstrong for San Diego Rural Fire District.

Stephen C. Volker for Backcountry Against Dumps.

INTERIM DECISION CERTIFYING ENVIRONMENTAL IMPACT REPORT/ENVIRONMENTAL IMPACT STATEMENT

INTERIM DECISION CERTIFYING ENVIRONMENTAL IMPACT REPORT/ENVIRONMENTAL IMPACT STATEMENT

1. Summary

This interim decision certifies that the Environmental Impact Report/Environmental Impact Statement for the East County Substation, Tule Wind, and Energia Sierra Juarez Generation Tie-In Projects was completed in compliance with the California Environmental Quality Act, that the Commission has reviewed and considered it prior to approving the project, and that the Environmental Impact Report/Environmental Impact Statement reflects the Commission's independent judgment.