V. Long-Term Planning Assumptions and Policy Guidance

A. Utilities' Current Filings

1. Parties Positions

2. Discussion

B. Integrated Approach

1. Energy Efficiency

a) Procedural Issues Related to Efficiency Rulemaking 01-08-028

b) Other Issues

      (1) Valuing Non-Utility Energy Savings in Procurement Forecasts

2. Demand Response

    "Funding for price-responsive demand response programs is also addressed in D.03-06-032. In Ordering paragraph 22, we state:

      `The total cost expenditures authorized as a result of this decision are capped at $33.0 million over the two calendar years, exclusive of revenue shortfalls and costs related to `other incentives' which are part of the DWR revenue requirement. Each IOU shall use the cost recovery mechanisms previously adopted in D.03-03-036 as applicable to all Phase 1 programs.'

    "PG&E's long-term plan includes its existing demand reduction programs and three new price-responsive programs. No additional funding is requested here. PG&E provides a conservative forecast, testifying on the difficulty of estimating demand reduction levels from new DR programs given various uncertainties. ORA testifies it reviewed the request and supports PG&E's filing on this issue. We adopt PG&E's demand reduction proposal.

    "SDG&E's plan reflects an aggressive demand response forecast and encourages the Commission to consider an incentive mechanism for all demand-side programs. SDG&E does not request any funding authorization here.

    "In its `preferred plan,' SCE requests $40 million in
    pre-approved funding for seven years and approval of a `new and improved' Air-conditioning (A/C) Cycling Program (ACCP). Further, SCE states program review should not be subject to after-the-fact reasonableness review. ORA testifies the expected peak load reduction from this program seems unrealistic and does not support the funding request. CEC recommends this program be referred to R.02-06-001 for in-depth examination.

    "We agree with CEC and ORA's recommendation that new ACCP programs need to be reviewed in R.02-06-001 or its successor demand response rulemaking. This allows for program specifics to be carefully examined and for the necessary evaluation and measurement standards to be adopted. The Commission can then directly authorize funding that proceeding. SCE's proposed program is an emergency-demand response program, and the future of these programs, in relation to price-response programs, is a policy issue for R.02-06-001 or its successor. We do not approve SCE's request for funding."78

3. Renewables

4. Distributed Generation

5. Transmission

6. Fuel Diversity in Non-Renewables

7. QFs

· The QF must have been in operation and under contract to provide power with an IOU at any point between January 1, 1998 and the effective date of this decision; and

· The QF contract must be set to expire before January 1, 2005, or have already expired.

a) Parties' Comments on the Proposed Decisions

b) Parties' Recommendations Not Yet Discussed

      CCC Positions

c) Discussion

C. Performance Incentives for Procurement Activities

1. Parties' Positions

2. Discussion

D. Other Proposals

1. CPA Peaker Initiative

2. City of San Diego's Proposal

3. CAC/EPUC's Request for Clarification of Net v. Gross Load Calculation

76 Opening Brief, pp. 1-4. 77 Discussion of Proposed Energy Savings Goals For Energy Efficiency Programs in California, Energy Efficiency and Demand Analysis Division, California Energy Commission, September 2003 78 D.03-12-062, pp. 69-72. 79 ORA Direct Testimony, June 23, 2003, p. 43. 80 Comments of the California Energy Commission on the Proposed Decisions of Commissioner Peevey and Administrative Law Judge Walwyn, December 5, 2003, p. 5. 81 Ibid., p. 6. 82 PG&E 2004 plan, p. 4-4. 83 PG&E long-term plan, p. 6-19. 84 PG&E 2004 plan, p. 4-5. 85 See also PG&E 2004 plan, p. 1-17, PG&E long-term plan, 1-21. 86 Pub. Util. Code § 399.14(a)(1)(A)(ii), as added by SB 67, allows an electrical corporation to undertake renewables procurement to fulfill its RPS obligations once the Commission has determined "[t]he electrical corporation is able to procure eligible renewable energy resources on reasonable terms, those resources can be financed if necessary, and the procurement will not impair the restoration of an electrical corporation's creditworthiness. This provision shall not apply before April 1, 2004, for any electrical corporation that on June 30, 2003, is in federal court under Chapter 11 of the federal bankruptcy law." 87 Pub. Util. Code § 399.14(a)(3)(A) requires the renewable procurement plan to include: "[a]n assessment of annual or multiyear portfolio supplies and demand to determine the optimal mix of renewable generation resources with deliverability characteristics that may include peaking, dispatchable, baseload, firm, and as-available capacity." 88 Transcript 3864-5, Volume 31. 89 In assessing deliverability for specific PPAs the utilities propose entering, we should also look to see that the supplier pays for any network upgrades needed to ensure power deliverability under the contract. 90 Exhibit 49, pages 5-6. 91 Page 22. 92 Page 23. 93 Page 9. 94 DOE/EIA State Electricity Profiles 2001, published October 2003, Energy Information Administration, US Department of Energy. 95 Southern California Edison and San Diego Gas & Electric, 70 FERC 61,215 (1995) 96 SDG&E commented only on the QF price risk hedging issue, which we will not address in this section of the decision. 97 CAC/EPUC did not file reply comments. 98 292.304 (f) Periods during which purchases not required. 99 We note that the right to seek any such waiver rests with the state regulatory commission, and not with the utilities over which any such commission may have regulatory authority. 100 The wind QF at issue is only 65 kilowatts (kW) in size and as such is subject to PURPA's standard rates requirement for QFs that have a design capacity of 100 kW or less, as set forth in 18 CFR 292.304 (c):
101 "Midland Power serves approximately 8,600 households, businesses and organizations that purchase more than 208 million kilowatt-hours annually" [roughly corresponding to a system capacity of 20 megawatts (MW)]. Source: http://www.midlandpower.com/asp/AboutUs/. 102 SCE-LTP-Rebuttal, p.100. 103 CPA Decision D03-001, pages 5-6. 104 Page 29. 105 Page 37. 106 CPA Energy Resource Investment Plan - 2003-2004, page 27. Emphasis in the original. 107 Page 33. 108 TURN Opening Brief, page 17. 109 CEC Opening Brief, page 20. 110 WPTF Opening Brief, page 42. 111 See D.02-03-055 and Water Code § 80110. 112 Tr. (Pettingill) at 4378-4381. 113 California Independent System Operator Corporation, 104 FERC ¶ 61,196 (August 12, 2003) in docket Nos. ER98-997-000; ER98-997-002; ER98-1309; ER02-2297-001; and ER02-2298-001. 114 ISO Opening Brief, p. 73. 115 Joint Parties Opening Brief, p. 15.

Previous PageTop Of PageNext PageGo To First Page