3. Discussion

3.1. CAISO and Utility Roles in Assuring Reliability

3.1.1. Incremental Improvement

"In making plans to procure a mixture of resources, the utilities should take into account the Commission's longstanding procurement policy priorities - reliability, least cost, and environmental sensitivity. While each of these priorities is important individually, they are also strongly interrelated. Increased reliability may increase procurement costs." (D.02-10-062, mimeo., pp. 17-18.)

"We direct the utilities to include a local reliability component in their next procurement plan. This approach will facilitate a more comprehensive approach to resource planning. It is our intent that this approach will increase the effectiveness of resource procurement and result in lower costs to ratepayers." (D.04-01-050, mimeo., p. 129.)

3.1.2. Reliance on RMR Contracts

"They [RMR units] are predominantly in transmission-constrained areas where local generation near load balances the limitation on imports over constrained transmission lines. While RMR serves an important purpose, RMR contracts are annual contracts that detract from a comprehensive infrastructure planning approach. They are also expensive, costing $360 million in 2003. ... The IOUs in their long-term procurement plans are in a position to foster a more comprehensive approach to meeting local and system needs through long range plans that incorporate generation, transmission, and demand-side trade-off analysis from a least cost perspective. We direct the utilities to include a local reliability component in their next procurement plan. This approach will facilitate a more comprehensive approach to resource planning. It is our intent that this approach will increase the effectiveness of resource procurement and result in lower costs to ratepayers." (D.04-01-050, mimeo. pp. 128-129).

"Finally, assume that in addition to a general service area-wide requirement, LSEs must satisfy a resource adequacy requirement for any load pockets in their service areas. In preparing and documenting both the input assumptions (e.g., definition of load pockets, load forecasts for such load pockets, resources tabulated by load pocket, etc.) and results (e.g., additional resources required, costs of these additional resources, reduction in RMR costs, etc.) of these two alternative possibilities for the deliverability issue, the differences between these two variants of each Resource Plan should be thoroughly explained." (Ruling dated June 4, 2004, Attachment A, page 9.)

3.1.3. Modify Restriction on Use of Bilateral Negotiated Contracts

"First, for short-term transactions of less than 90 days duration and less than 90 days forward, the IOUs are authorized to continue to use negotiated bilaterals subject to the strong showing standard we adopted in D.02-10-062, as modified by D.03-06-067. Any such negotiated bilateral transactions shall be separately reported in the utilities quarterly compliance filings.

"Second, utilities may use negotiated bilateral contracts to purchase longer term non-standard products provided they include a statement in quarterly compliance filings to justify the need for a non-standard product in each case. The justification must state why a standard product that could have been purchased through a more open and transparent process was not in the best interest of ratepayers.

"Last, we expand the authorization for use of negotiated bilaterals for standard products in instances where there are five or fewer counterparties who can supply the product, as suggested by SCE. We limit this authority, however, only to the two categories of gas products cited by SCE: gas storage and pipeline capacity. In such instances, the utility needs to affirm that five or fewer counterparties in the relevant market offered the needed product. Any resulting contract shall be separately reported in the utilities' quarterly compliance filings." (D.03-12-062, mimeo. pp. 39-40.)

3.1.4. Spot Market Transactions Limitation Relaxed

"this guideline applies to energy procurement in Day-Ahead, Hour-Ahead, and Real-Time markets and it is intended to represent a target amount, rather than a hard limit, as there may be economic reasons justifying a utility's decision to exceed the target (i.e., least-cost dispatch). We also find that this guideline provides an appropriate balance between procurement flexibility and reliability." (D.03-12-062, mimeo. page 10.)

Finding of Fact 4 states the point precisely:

"The 5% of monthly need target on spot market purchases from D.02-10-062 provides a balance between procurement flexibility and reliability and it is reasonable to continue to require the utilities to justify a higher level." (D.03-12-062, mimeo. p. 81.)

3.2. Application to Southern California and Statewide

"would create a dangerous disconnect between the party identifying the reliability needs and the parties responsible for the costs of meeting those needs. If these costs will show up `on the books' of the IOUs and not the ISO, there will be no inherent checks and balances in the process. The ISO will not have to weigh the potential for increased procurement costs against the sometimes marginal reliability benefits of a particular change in practice. This will create a powerful incentive for the ISO to over-prescribe reliability requirements in order to make life easier for the system operators, without any effective recourse by the people who pay the bills." (TURN Comments, page 5.)

3.3. Monitoring Plan

3.4. Cost Recovery

2 We also note that, according to DWR, many of the identified congestion issues arise as a result of the administration of a DWR contract with Sempra Energy Resources. DWR says that this contract is currently the subject of a dispute being addressed through arbitration, and the Commission's decision may impact the operational administration of the contract. Neither DWR nor any other entity or party, however, provides any other information or any recommendations regarding how today's decision should or should not be made to influence administration of this contract, and positively or negatively affect the congestion and reliability issues presented here. 3 AB 57 adds Section 454.5 to the Public Utilities Code. 4 PG&E says its access to information is limited by Standards of Conduct adopted pursuant to Federal Energy Regulatory Commission (FERC) Orders 888, 889 and 2004. 5 Based on a preliminary analysis, we do not understand FERC's Order No. 2004 (Standards of Conduct for Transmission Providers, 105 FERC ¶ 61,248 (2003), Order on Reh'g 107 FERC ¶ 61,032 (2004) ("Order No. 2004") to prohibit LSEs from receiving information from the CAISO that is necessary or useful for LSEs to make procurement and scheduling decisions that facilitate the reliable operation of the grid. Rather, Order No. 2004 principally prohibits Transmission Providers from providing transmission information to their Energy Affiliates. See 105 FERC at ¶ 52; 18 C.F.R 358.5 (a) and (b)("the proposed prohibitions prevent a Transmission Provider from giving its Marketing or Energy Affiliates undue preferences over their unaffiliated customers through the exchange of `insider' information"). Order No. 2004 does not apply to ISOs, and so does not appear to prohibit the CAISO from sharing information with LSEs or other market participants. See 105 FERC at ¶ 16, 23; 18 C.F.R 358.1(c). And, of course, the CAISO is not affiliated with any market participant in California. For both of these reasons, Order No. 2004 does not appear to apply to the CAISO. Moreover, Order No. 2004-A specifically provides that a Transmission Provider may "share information necessary to maintain the operations of the transmission system" even with affiliated entities. See 18 C.F.R. 358.5(b)(8). 6 See 107 FERC 61,240, 107 FERC 61,112, and 102 FERC 61,314. FERC's June 2, 2004 order essentially reinforces its March 25 order where it stated that "rather than focusing on and using stand-alone RMR agreements, [ISO-NE] should incorporate the effect of those agreements into a market-type mechanism." 7 "Negotiated bilateral transactions lack transparency and are more appropriately restricted to limited circumstances." (D.03-12-062, mimeo. page 83, Finding of Fact 16.) 8 D.03-12-062, mimeo. page 26. 9 This authority should not be construed as a change or relaxation of any currently applicable affiliate transactions restrictions. 10 CAISO is currently in the process of designating Etiwanda Units 3 and 4 as RMR units. Despite an FERC ruling that this capacity had to be offered at cost to the market as compensation for past abuses, and the Commission's D.04-01-050 encouraging utility procurement of this cost-based capacity, the capacity was not contracted for at the last opportunity. 11 For SCE, we understand these to be SCE's Reliability Services Rate Schedule, Appendix VI to SCE's Transmission Owner Tariff. For PG&E, we understand these to be PG&E's Reliability Services Tariff, and/or the Reliability Services Balancing Account in its Transmission Owner Tariff.

Previous PageTop Of PageNext PageGo To First Page