Comments on Proposed Decision

The proposed decision of the Assigned Commissioner in this matter was mailed to the parties in accordance with Pub. Util. Code § 311(d) and Rule 77.1 of the Rules of Practice and Procedure. Comments were received from CEC and UC, filing jointly, and PG&E, Sempra, BOE, SCGC, and The Utility Reform Network.

We have carefully considered the comments on the issues addressed in today's decision. In response to comments, we have modified the draft decision to clarify certain accounting and implementation instructions, and provided R&D definitions. We have also carefully considered parties' comments regarding the R&D program, and concluded that CEC should act as administrator, although we have not modified the R&D funding mechanism or oversight by this Commission.

Due Dates for AB 1002 Implementation Program

The following table summarizes certain dates and deadlines actions are to be undertaken on an ongoing basis. Refer to the discussion in the decision and ordering paragraphs for further details on the instructions to be followed.

Due Date:

Party responsible:

Action:

Quarterly

Energy Division

Disperse remittances deposited in the Fund to utilities less adjustments for Commission and BOE administrative costs, R&D funding and BOE refunds.

Quarterly

BOE

Provide Energy Division with copies of Natural Gas Surcharge Returns from utilities and consumers and identify amounts paid.

Quarterly

Utilities

Provide Energy Division and R&D Administrator copies of BOE returns showing amounts collected and remitted for R&D program funding.

Quarterly

Utilities

Provide Energy Division copies of BOE returns showing amounts collected and remitted for Commission and BOE administrative expenses.

March 31

R&D Administrator

Provide Energy Division with Annual Report on R&D activities and spending.

July 31

(except for program Year 2005)

R&D project developers

Provide descriptions of potential R&D projects to Energy Division and R&D Administrator for consideration in upcoming year.

August 31

BOE

Unless previously submitted, provide copies of Natural Gas Surcharge Returns for utilities and consumers showing gas volumes used to calculate remittances.

August 31

(except for program Year 2005)

R&D Administrator

Provide proposed annual R&D program to the Energy Division.

September 30

Energy Division

Obtain Commission and BOE costs for administering AB 1002 recoverable through the surcharge.

Prior to October 31

Energy Division

Provide utilities with allocation of R&D, Commission and BOE administrative costs, and interstate pipeline customer gas volumes used for setting surcharge rates.

October 31

Utilities

File ALs with proposed surcharge rates with requested effective date of January 1. Energy Division to promptly notify BOE of approved surcharge rates.

Annually

Utilities

Review customer accounts for collections received from exempt customers and issue refunds according to instructions discussed in decision.

Annually

Third Party Gas Storage

Submit customer lists to BOE and the Commission.