"Resource procurement traditionally involves the Commission developing appropriate frameworks so that the entities it regulates will provide reliable service at least cost. This involves determining an appropriate demand forecast and then ensuring that the utility either controls, or can reasonably be expected to acquire, the resources necessary to meet that demand, even under stressed conditions such as hot weather [footnote omitted] or unexpected plant outages. `Resource adequacy' seeks to address these same issues. In developing our policies to guide resource procurement, the Commission is providing a framework to ensure resource adequacy by laying a foundation for the required infrastructure investment and assuring that capacity is available when and where it is needed." (D.04-01-050, pp. 10-11.)


D.04-01-050 adopted the following RAR policies, applicable to the LSEs:


(1) Each LSE within an IOU's service territory has an obligation to acquire sufficient reserves for its customers' load located within that service territory.


(2) Each LSE is subject to a planning reserve margin (PRM) requirement of 15-17% for all months of the year. Each LSE must meet this obligation no later than January 1, 2008 through a gradual phase-in, with interim benchmarks becoming effective in 2005.


(3) Each LSE must forward contract 90% of its summer (May through September) peaking needs (loads plus planning reserves) a year in advance, subject to adjustment if implementation would result in significantly increased costs or foster collusion and/or the exercise of market power in the Western energy markets.


(4) The 5% target limitation on utilities' reliance on the spot market (i.e., Day-Ahead, Hour-Ahead, and Real-Time energy) to meet their energy needs is continued in effect.


(5) The Commission reiterated its commitment that full value be given to the preferred resources identified in the California Energy Action Plan and to the long-term California Department of Water Resources (DWR) contracts.


"In an April 28, 2004 letter to President Michael Peevey, Governor Schwarzenegger indicated that the `Commission's phase-in date [for resource adequacy] of 2008 is too slow.' President Peevey's response, also dated April 28, concurred with the Governor's assessment and indicated that the phase-in `needs to be accelerated to ensure system reliability.' The Joint Opening Statement of President Peevey and Commissioner John Geesman of the California Energy Commission at the April 30 prehearing conference indicated that `we will look closely not only at refinement of the existing requirements, but also their acceleration as requested by the Governor.'"

3 The workshops were held pursuant to the February 13, 2004 Assigned Administrative Law Judge's Ruling (ALJ) on the Scope and Schedule of Resource Adequacy Workshops (February 13 Ruling) issued in Rulemaking (R.) 01-10-024, the predecessor of the instant proceeding. The order instituting this rulemaking (OIR) explicitly provided that this is the successor proceeding to R.01-10-24 and that the record in that proceeding is fully available for consideration in this proceeding. (OIR, p. 25, Ordering Paragraph 3.) 4 See 107 FERC 61,274. 5 Consistent with earlier practice as permitted by this Commission, DWR submitted comments and replies by memorandums from its California Energy Resources Scheduling unit.

Previous PageTop Of PageNext PageGo To First Page