Communications Division

RESOLUTION T-17265

Carrier Oversight and Programs Branch

May 6, 2010

Tier Designation

Advertised Speeds

Average Speeds

Pricing Plan $ per Month

Downstream mbps

Upstream mbps

Downstream mbps

Upstream mbps

Residential

         

Entry-Level

5

2

5

2

$33.95

Maximum

35

5

20

5

$99.00

Other Residential Tiers

20

3

20

3

$59.95

Business or Institutions

   

Entry Level

10

3

10

3

$79.95

Maximum

50

5

50

5

$399.99

Other Business or Institution Tiers (30%) Discount for Critical and Strategic Institutions

50

20

50

20

$279.95

Event

Payment Cycle 1

(Day/Month)

Payment Cycle 2

(Day/Month)

Invoices due from Audeamus Telecommunications, Inc. to CD

5th of Month 1

20th of Month 1

Payment letters from CD to Information and Management Services Division (IMSD) 6

On 19th of Month 1

On 4th of Month 2

Invoices submitted from IMSD to State Controller's Office (SCO) for payments

20th through 26th of Month 1

5th through 13th of Month 2

THEREFORE, IT IS ORDERED that:

1

Project Name

Audeamus - Tranquillity and West Fresno

 

2

Project Plan

Offer High Speed internet, data, long distance and video (IPTV). The proposed technology to provide these services is the same standards-based point-to-point FTTP Technology.

 

3

Project Size (in square miles)

20.6 (0.6 Unserved and 20 Underserved)

 

4

Download speed

Business - 10-50 Mbps, can provide up to 100Mbps

Residential - 5-35 Mbps, up to 100Mbps

5

Upload speed

Business - 3-20 Mbps, can provide up to 100Mbps

Residential - 2-5 Mbps, up to 100Mbps

6

Location

Fresno County

 

a)

Community Name

Tranquillity

 
   

West Fresno

 
       

b)

CBGs /Household Income

UNSERVED

 
   

060190082002

$13,128

       
   

UNDERSERVED

 
   

060190041001

$16,651

   

060190039005

$13,263

   

060190039004

$13,263

       

c)

ZIP Codes

UNSERVED

 
   

93668

 
       
   

UNDERSERVED

 
   

93722

 
   

93706

 
       

7

Estimated Potential Subscriber Size

   

a)

Households

234 Unserved; 351 Underserved

 

b)

Subscribers

134 Unserved; 228 Underserved

 

8

Deployment Schedule (from Commission approval)

18 months

 

9

Proposed Project Budget

$3,320,470

 
 

CASF

$1,154,495.50

 
 

CIAC

   
 

Amount of CASF Funds Approved

$1,154,495.50

 

1 SB 1193 (Chapter 393, Stats. of 2008) established the California Advanced Services Fund as a new public purpose program.

2 The American Recovery and Reinvestment Act (Recovery Act) appropriates $7.2 billion for grants and loans to support broadband deployment on a national level. The Recovery Act offers a unique and ground breaking opportunity for California to partner with the federal government and other state agencies in advancing the goal of bridging the digital divide.

3 Audeamus subsequently modified its request on March 31, 2010, as discussed below.

4 Ponderosa CableVision has also been granted 50% grant and 50% loan funding under the Recovery Act's first round.

5 Since Audeamus has been awarded a combined 50% loan which was not anticipated and 50% grant, CASF will grant matching funds of up to 10% plus half of the amount requested from Recovery Act that was denied. This amount denied from ARRA would be 30% (80% requested less the 50% granted). One half of this amount would be 15%. This 15% will be added to the 10% requested in the application..

6 The above schedule is contingent on the CASF recipient submitting clear, complete, and error-free invoices to CD. Additional time to process payments may be necessary if CD finds problems with the submitted invoices.