Word Document PDF Document

R E S O L U T I O N

Resolution E-4495 . Pacific Gas and Electric Company requests for approval of deviation from California Public Utilities Code Section 320.

PROPOSED OUTCOME: This resolution grants the request and authorizes Pacific Gas and Electric (PG&E) to relocate approximately 1,300 feet of 12 kV aerial power distribution lines and replace four wood poles and a stub pole and guy along Highway 12 at Madrone Road in Sonoma County. Highway 12 is within a state scenic corridor.

ESTIMATED COST: This project costs $154,652.  It is to be funded by the State Highway Operation and Protection Program (SHOPP), under the safety category (Program Code 201.010).  The construction capital cost of the project is being shared with the Sonoma County through a cooperative agreement, with the County sharing roughly 1/3 of the construction capital cost.

By Advice Letter 4029-E and Supplemental
Advice Letter 4029-E-A dated May 2, 2012.

______________________________________________________________

SUMMARY

California Public Utilities Commission (CPUC) approves the California Public Utilities Code Section 320 (P.U. Code § 320) deviation request, because it has a much lower cost than undergrounding the facilities, local government approval, is visually consistent with the existing facilities, and it can be seen with certainty that the project will not have a significant effect on the environment.

BACKGROUND

California P.U. Code § 320 was enacted in 1971 and reads in part as follows:

The legislature hereby declares that it is the policy of this state to achieve, whenever feasible and not inconsistent with sound environmental planning, the undergrounding of all future electric and communication distribution facilities which are proposed to be erected in proximity to any highway designated a state scenic highway pursuant to Article 2.5 (commencing with Section 260) of Chapter 2 of Division 1 of the Streets and Highways Code and which would be visible from such scenic highways if erected above ground. The Commission shall prepare and adopt by December 31, 1972, a statewide plan and schedule for the undergrounding of all such utility distribution facilities in accordance with the aforesaid policy and the rules of the Commission relating to the undergrounding of facilities.

The CPUC shall require compliance with the plan upon its adoption.

In order to facilitate administration, letter requests for deviations will be accepted, reviewed by the Commission staff and, where appropriate, approved by Commission resolution. (74 CPUC 457, D.80864)

NOTICE

PROTESTS

The CPUC received no protests.

DISCUSSION:

Higher undergrounding cost and the consistency of the project with the existing environmental conditions are the determining factors in the CPUC staff recommendation.

Nature of the Project

Pole relocations would allow Caltrans to install traffic signals, perform minor road widening and roadway intersection improvements, and to improve safety and traffic flow at the intersection.

Economic feasibility

Options

Administrative/ Overhead Cost

Labor Cost

Material Cost

Total Cost

Comparative Cost Ratio

Overhead

$23,086

$90,425

$41,141

$154,652

1:1

Underground

$39,161

$673,709

$100,416

$813,286

5.26:1

10. The cost of the underground option at this location would exceed placing this segment of power line overhead by 5.26 to 1.

11. By a letter dated January 28, 2010, Sonoma County Department of Transportation and Public Works indicates that relocation of a limited number of aerial utility poles would not negatively impact the visual integrity of the surrounding environment, hence supports the overhead alternative.

12. The California Department of Transportation acted as the Lead Agency pursuant to CEQA for the environmental review of the project.

Top Of Page