Word Document PDF Document

Resolution E-4465. San Diego Gas and Electric Company (SDG&E) Request to Establish the Revenue Requirement and Regulatory Account Update Associated with the El Dorado Power Plant Facility.

PROPOSED OUTCOME: Approves SDG&E's purchase price of the El Dorado Power Plant (now named the Desert Star Energy Center) and the proposed revenue requirement for non-fuel costs beginning October 1, 2011 through December 1, 2015. Revenues will be tracked through SDG&E's Non-Fuel Generation Balancing Account.

ESTIMATED COST: $300.744 million in utility-owned generation non-fuel operating costs, for October 1, 2001 through December 31, 2015.

By Advice Letter 2292-E Filed on September 23, 2011.

10. AL 2292-E forecasted a revenue requirement for October 1, 2011 through December 31, 2015 of $300.744 million, an increase for this period of
$11.726 million over that submitted in AL 2204-E.

11. AL 2292-E also indicated an increased estimated net book value to
$215.1 million for the El Dorado Power Plant.

12. AL 2292-E also submitted a name change for the plant to Desert Star Energy Center as of the October 1, 2011 plant ownership transfer date.

13. The Utility Consumers' Action Network submitted a timely protest to
AL 2292-E on October 12, 2011, asserting that the beginning net book value for the plant may have been overstated.

14. The protest also asserted that Long-Term Service Agreement costs should be expensed, not capitalized, and that SDG&E customers should not have to pay for any capitalized LTSA costs.

15. SDG&E submitted a timely reply to the protest, addressing UCAN's statements.

16. In its protest reply, SDG&E agreed that an independent audit should be performed to confirm that the purchase price of the plant and the beginning net book value protected ratepayers' interest, and was consistent with
D.07-11-046 and AL 2204-E.

17. The forecasted revenue requirement increase of $11.736 million between
AL 2204-E and AL 2292-E is associated with increases in depreciation, Federal tax, and return on equity line items resulting from adopted increases in the plant's net book value, which the Commission finds reasonable.

18. Based on review of SDG&E's AL 2204-E and AL 2292-E, attachments to these advice letters, and the independent auditor's report, it is reasonable to conclude that SDG&E expenses and does not capitalize LTSA costs.

19. The independent auditor's report found the balance sheet free of material misstatement.

20. SDG&E submitted a Desert Star Energy Center revenue requirement based on a ratebase of approximately $211 million, and provided information through responses to data requests confirming that information.

21. D.07-11-046 approved the cost recovery framework for generation plant purchases at the time of ownership transfer through the advice letter process, requiring that only reasonable forecasted costs will be included for recovery in rates.

22. The Commission finds that the additional cost of capitalized items and the resulting increase in the plant's net book value and revenue requirement are reasonable costs and are authorized for recovery in rates.

23. SDG&E included capitalized inventory of approximately $7 million in rate base, consistent with existing CPUC-authorized policy.

24. The independent auditor's report confirms that the use of estimates is consistent with generally accepted accounting principles.

25. The methodology SDG&E used in developing the revenue requirement resulting from the plant's beginning net book value is correct, beginning with a net book value that is consistent with the results of the independent auditor's report.

26. All changes to the NGBA tariff proposed in Attachment A to AL 2292-E should be approved.

27. UCAN's protest should be denied based on review of AL 2292-E and related documents, including the independent' auditor's report.

1 Independent Auditors' Report to the Shareholders of San Diego Gas & Electric Company and Sempra Generation, issued by Deloitte & Touche, LLP, February 17, 2012.

2 See SDG&E's NGBA tariff, Preliminary Statement Part II.

3 D.07-11-046, p. 2, footnote 3: "The offered price of the El Dorado Option, as defined in the Equity Purchase Option Agreement, is equal to the closing book value of the plant at the time of transfer in 2011, which is currently estimated by El Dorado to be $189 million."

4 AL 2204-E, page 3-4: "The offered price of the Plant, as defined in the Equity Purchase Option Agreement is equal to the closing book value of the plant at the time of transfer in 2011 which is estimated to be $189 million. . . In addition to the $189 million estimated book value, there are $10.5 million in capital additions consisting of IT and other capital improvements."

5 SDG&E AL 2292-E, p. 2.

6 Independent Auditors' Report to the Shareholders of San Diego Gas & Electric Company and Sempra Generation, issued by Deloitte & Touche, LLP, February 17, 2012; p. 7.

7 AL 2292-E, p. 3.

8 October 20, 2012 Reply of San Diego Gas & Electric to the Utility Consumers' Action Network (UCAN) Protest of Advice Letter 2292-E, Revenue Requirement and Regulatory Account Update Associated with the EL Dorado Power Plant Facility, p. 2.

9 Ibid, pp. 2 and 3: "Prior to SDG&E's October 1, 2011 acquisition and operation of the El Dorado Power Plant, the plant did NOT operate under regulated utility guidelines and consequently was NOT held to those same principles . . . SDG&E cannot control its affiliated company's decision whether it needs to capitalize or expense these LTSA costs if necessary at all given its rates were the subject of FERC's market based rate authorization. Therefore, whether or not these cost would have been expensed, if at all, is unrelated to this transaction."

10 Ibid, p. 2.

11 D.07-11-046, mimeo at 12.

12 Id.

13 Report prepared by Van Horn Consulting, see D.07-11-046, mimeo at 15.

14 D.11-07-046, mimeo at 17.

15 See footnote 12.

16 This agreement was executed with the City of Boulder City, Nevada in
December 2002, with the option to purchase energy on a fixed-heat rate, variable natural gas price basis plus a fixed margin at the time of energy consumption. This option has never been exercised.

17 All affiliate agreements, with the exception of those with SDG&E and its subsidiaries, terminated in October 2011, at the time the Company was purchased. Also in accordance with the agreement, outstanding amounts due from or due to affiliates of the Company were settled at the time of purchase.

18 Id at 7.

19 D.07-11-046 at 20.

20 Exclusive of any pre-existing capitalized LTSA amounts.

21 Response to October 24, 2011 data request: "While the net book value of the plant on the transfer date was $215 million, only $209 million was placed into rate base. Additionally, some IT costs incurred at SDG&E were also included in rate base bringing the total to $211 million. The difference between the purchase price and the amount rate based was the previously capitalized LTSA costs that were removed from being "capitalized." LTSA costs are expensed by regulated California utilities and are not capitalized. SDG&E expenses them in the year when costs are incurred and it is not included within the rate base."

22 Response to October 24, 2011 data request: "This project includes labor, hardware, licensing, and other telecom equipment, totaling approximately $1.7 million."

23 D.08-07-046, mimeo at 18.

24 Preliminary Statement Non-Fuel Generation Balancing Account (NGBA), revised
Cal P.U.C. Sheet No. 22507-E canceling revised Cal P.U.C. Sheet No. 22081-E: "The adopted generation non-fuel revenue requirement shall consist of the adopted operating and maintenance, and capital-related costs approved in D.07-11-046 and updated through advice letter upon in-service date of October 1, 2011. The fuel costs of Desert Star Energy Center shall be recorded in the Energy Resource Recovery Account (ERRA)."

Top Of Page