1 Motion for Approval of Settlement Agreement Revising Distribution Level Interconnection Rules and Regulations ("Motion for Approval of the Rule 21 Settlement"), filed 3/16/2012 in CPUC Order Instituting Rulemaking (R.) 11-09-011. The attachments to the Motion for Approval of the Rule 21 Settlement include a Settlement Agreement ("Settlement Agreement"), a Proposed Rule 21 Revised Tariff ("Proposed Rule 21 Tariff"), Proposed Rule 21 Interconnection Agreements ("Proposed Rule 21 IAs"), and Proposed Rule 21 Interconnection Requests ("Proposed Rule 21 IRs") (jointly, the "Proposed Rule 21 Settlement"). The Settling Parties are: Aloha Systems, California Farm Bureau Federation, Center for Energy Efficiency and Renewable Technologies, Clean Coalition, Interstate Renewable Energy Council, Pacific Gas & Electric, San Diego Gas & Electric, Sierra Club, Solar Energy Industries Association, Southern California Edison, SunEdison, Sunlight Partners, Sustainable Conservation, and Vote Solar Initiative (jointly, "Settling Parties"). The Motion for Approval of the Rule 21 Settlement is available at http://docs.cpuc.ca.gov/efile/MOTION/162852.pdf.

2 Proposed Resolution No. L-436, Resolution Adopting New Regulations Regarding Public Access to Records of the California Public Utilities Commission and Requests for Confidential Treatment of Records ("Proposed Resolution L-436"), posted at http://docs.cpuc.ca.gov/WORD_PDF/COMMENT_RESOLUTION/162152.pdf. Proposed Resolution L-436 is presently scheduled to be considered by the CPUC at the 4/19/2012 meeting.

3 Proposed Pub. Util. Code section 321.9(a)(2)(A)-(M) would include the number of personnel and consultants working on interconnection matters for each electrical corporation; date of the interconnection application; queue position date; county and state location; study group, if in a cluster study; size of project; technology type; interconnection procedure status for each project; interconnection voltage; whether an interconnection agreement has been signed; initial requested in-service date; current requested in-service date; and interconnection studies completed for each project (with dates of completion, costs charged to applicants, actual costs to the electrical corporations completing the studies, and status of the application).

4 Proposed Rule 21 Tariff, Sec. E.5.d(i)-(ii). Requires the IOUs to publish online queues containing: assigned [interconnection request] number; queue position; date the interconnection request was received by the utility; date the interconnection request was determined to be complete and valid; applicant's requested review process; original and currently requested in-service date; agreed-upon or actual commercial operation date; maximum summer and winter electrical output; type of generating or storage facility; fuel source; proposed point of interconnection location by substation/area, circuit, county, and state.

5 See Settlement Agreement, Sec. II.G.1-3 (identifying Settling Parties' minimum proposed requirements for staff proposal on reporting requirements to be filed in R.11-09-011).

6 See Settlement Agreement, Attachment B, Recommended Scope of Phase 2 Issues ("Study deposits, pursuant to which the IOUs shall collect and provide data on the actual cost of system impact studies and facilities studies"). See also Proposed Rule 21 Tariff, Sec. E.3.a (setting out Detailed Study deposit amounts).

7 Proposed Rule 21 Tariff, Sec. F.1.d and Sec. K.

8 Proposed Rule 21 Tariff, Sec. E.5.d states, "Distribution Provider shall publish and update monthly on its website the interconnection queue for all Interconnection Requests governed by this Rule with a Point of Interconnection on Distribution Provider's Distribution System that have been assigned a queue position." To provide a basis for publication of an integrated queue incorporating interconnection requests for exporting generating facilities queued under both Rule 21 and the utility's FERC-jurisdictional wholesale distribution tariff, the proposed Rule 21, Sec. E.5.d further states, "Nothing here prohibits Distribution Provider from publishing this queue combined with other interconnection requests to Distribution Provider's Distribution System."

9 Proposed Pub. Util. Code sec. 321.9(c).

10 Id.

11 D. 00-11-001, page 4 (ordering IOUs to adopt a specific confidentiality statement within Rule 21, stating: "Any information pertaining to Generating and/or Interconnection Facilities provided to an Electrical Corporation by an Electricity Producer shall be treated by the Electrical Corporation in a confidential manner.") That confidentiality rule has not been subsequently modified. See D.00-12-037 (adopting full text of Rule 21).

12 Motion for Approval of Rule 21 Settlement, p. A-5.

13 Proposed Rule 21 Tariff, Sec. D.7.b.

14 Proposed Rule 21 Tariff, Sec. D.7.a, "Confidential Information shall include, without limitation, confidential, proprietary or trade secret information relating to the present or planned business of Applicant, Customer, Producer, or Distribution Provider [...] including all information relating to a Party's technology, research and development, business affairs, and pricing.

15 Standardization of Small Generator Interconnection Agreements and Procedures, Order No. 2006, FERC Stats. & Regs. ¶ 31,180 (2005) ("Order No. 2006"),
pages 34-36.