7. Schedule

The Water Division requested a delay in the schedule because weather conditions in the mountainous areas near Strawberry are likely to interfere with audits and discovery of Water Company documents.

The schedule for this proceeding follows:

Event

Date

Water Division serves proposed direct testimony

March 5, 2004

End of discovery

March 24, 2004

Respondents serve proposed rebuttal testimony

March 26, 2004

Water Division serves proposed reply testimony

April 2, 2004

Deadline for filing any prehearing motions (motions in limine)

April 9, 2004

Responses to any prehearing motions (motions in limine)

April 14, 2004

Final prehearing conference; marking of exhibits

April 16, 2004
10:00 a.m. to noon

Evidentiary hearing

April 19-23, 2004
9:00 a.m. to noon; 1:30-3:00 p.m. each day

Opening briefs

May 14, 2004

Reply briefs

May 28, 2004

Submission of proceeding

May 28, 2004

Presiding Officer's decision

July 27, 2004

Deadline for appeal of Presiding Officer's decision

August 26, 2004

Probable Commission consideration of any appeal

September 2, 2004

Unless otherwise indicated, all hearings and conferences will be held in Commission hearing rooms, 505 Van Ness Ave., San Francisco, CA 94102