11. Submittal of Documents to Principal Hearing Officer

All documents required to be filed or served in this proceeding shall be submitted to the principal hearing officer by e-mail addressed to

tom@cpuc.ca.gov, facsimile sent to (415) 703-1723, or by personal delivery in order to arrive on or before the due date.

IT IS SO RULED.

Dated August 29, 2001, at San Francisco, California.

Appendix A

Schedule for Environmental (CEQA) Review

Application of Wild Goose (01-06-029)

This schedule includes general timelines for environmental review of the above application under CEQA. Since we do not yet know the exact dates on which the draft EIR and final EIR will issue, it is not possible to designate specific dates. The Commission shall give the parties and the public notice additional notice

of the dates of events and the procedure for public participation when specific dates can be set.

Event

Estimated Timeline

Application of Wild Goose complete
(for CEQA purposes)

            Fall 2001

Notice of Preparation

            Fall 2001

Scoping meeting in the local community8/comments on scope of EIR

    Fall 2001

Draft EIR issues

    Winter 2002

Public review period for draft EIR9

    Winter 2002 (45 days)

Public participation hearing in local community on both draft EIR and Wild Goose application10

    Winter 2002

Final EIR issues

    Spring 2002

Proposed decision on certification of EIR and approval of project

No later than 90 days after submittal of
Phase I and Phase II

Appendix B

Resolution ALJ-164

NOTE: See CPUC Formal Files for Appendix B.

APPENDIX C

Wild Goose Service List

Appendix D

8 At this meeting, members of the Commission CEQA team will discuss potential environmental effects of the project, in order to determine the issues to be addressed in the EIR. The public will have an opportunity to participate in this meeting. 9 The public review period for the draft EIR will be 45 days. During this time, the public and the parties may review copies of the draft EIR and submit written comments to the Commission. 10 Members of the public are invited to attend the public participation hearing to present comments on the draft EIR and the application to the principal hearing officer. Representatives of Wild Goose will be available to answer questions about the proposed expansion. (END OF APPENDIX A)

Previous PageTop Of PageNext PageGo To First Page