| Word Document PDF Document |
ALJ/CAB/JMH/jva Mailed 12/2/2005
Decision 05-12-009 December 1, 2005
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking to Promote Policy and Program Coordination and Integration in Electric Utility Resource Planning. |
Rulemaking 04-04-003 (Filed April 1, 2004) |
Order Instituting Rulemaking to Promote Consistency in Methodology and Input Assumptions in Commission Applications of Short-run and Long-run Avoided Costs, Including Pricing for Qualifying Facilities. |
Rulemaking 04-04-025 (Filed April 22, 2004) |
OPINION REGARDING EXPIRING QUALIFYING FACILITY CONTRACTS
This decision continues the interim relief as provided in Decision (D.) 04-01-050 for Qualifying Facilities (QFs) with expired or expiring contracts from January 1, 2006 until the Commission issues a final decision in the combined two dockets, Rulemaking (R.) 04-04-003 and R.04-04-025. The Investor-Owned Utilities (IOUs) are to continue purchasing power pursuant to a five-year SO1 contract from QFs with a contract set to expire during this term. The pricing terms should be consistent with the guidelines provided in D.04-01-050, and shall be modified to reflect said revised QF pricing policy, as of the effective date of a Commission decision adopting such a revised pricing policy.