I. INTRODUCTION

The Utility Reform Network ("TURN") filed an application for rehearing of Decision (D.) 09-12-047 ("Decision") on January 25, 2010. In D.09-12-047, the Commission adopted a Self Generation Incentive Program ("SGIP") budget of $83 million for 2010 and 2011. In addition, the Decision allows the continued practice of tracking carryover amounts, amounts previously authorized but unspent, from earlier SGIP budgets and allowing those amounts to augment the 2010 and 2011 authorized SGIP budgets. The California Energy Storage Alliance ("CESA"), the California Center for Sustainable Energy ("CCSE"), the California Clean DG Coalition ("Clean DG"), and FuelCell Energy Inc. ("FSE") all filed responses to TURN's application.

We have carefully considered the arguments presented by TURN and are of the opinion that no grounds for rehearing have been demonstrated. Therefore, we are denying TURN's application for rehearing.