Word Document PDF Document

ALJ/DMG/gd2 Date of Issuance 10/10/2011

Decision 11-10-002 October 6, 2011

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Application of Southern California Edison Company (U338E) for a Commission Finding that its Procurement-Related and Other Operations for the Record Period January 1 Through December 31, 2009 Complied with its Adopted Procurement Plan; for Verification of its Entries in the Energy Resource Recovery Account and Other Regulatory Accounts; and for Recovery of $29.947 Million Recorded in Four Memorandum Accounts.

Application 10-04-002

(Filed April 1, 2010)

DECISION ON SOUTHERN CALIFORNIA EDISON COMPANY 2009 ENERGY RESOURCE RECOVERY ACCOUNT COMPLIANCE AND REASONABLENESS REVIEW

TABLE OF CONTENTS

APPENDIX - The Commission Process for Review and Approval of the Forecast ERRA Revenue Requirement and the Recorded Procurement Costs

DECISION ON SOUTHERN CALIFORNIA EDISON COMPANY 2009 ENERGY RESOURCE RECOVERY ACCOUNT COMPLIANCE AND REASONABLENESS REVIEW

Top Of PageNext PageGo To First Page