6. Award to TURN

We award TURN $13,430.72 for contributions to D.02-01-063. Consistent with previous Commission decisions, we will order that interest be paid on the award amount (calculated at the three-month commercial paper rate), commencing the 75th day after Joint Intervenors filed their compensation request. Interest will continue until the utility makes full payment. Although D.02-01-063 was issued in dockets related to Southern California Edison Company, as the utility who was the subject of the instant proceeding, SDG&E will pay the full award.

As in all intervenor compensation decisions, we put Joint Intervenors on notice that the Commission Staff may audit records related to this award. Adequate accounting and other documentation to support all claims for intervenor compensation must be made and retained. The records should identify specific issues for which Joint Intervenors request compensation, the actual time spent, the applicable hourly rate, and any other costs for which compensation is claimed.